Job No.: TCS00670/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report (No.27)
¡V October 2015 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
12
November 2015 |
TCS00694/13/600/R0025v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
11 November 2015 |
First
Submission |
2 |
12 November 2015 |
Amended
according to the IEC¡¦s comments on 11 November 2015 |
|
|
|
executive summary
ES01
This is the 27th monthly EM&A report presenting the monitoring
results and inspection findings for the reporting period from 1 to 31 October 2015
(hereinafter ¡¥the Reporting Period¡¦).
Environmental Monitoring
and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project is
divided to six CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (TCSS), Contract 5 (CV/2013/03), Contract 6
(CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03
In the Reporting Period, the construction
works for Contract 6 was commenced on 23 October 2015 and therefore the active
contracts would be included Contract 2, Contract 3, Contract 5, Contract 6 and
Contract SS C505. Environmental
monitoring activities under the EM&A programme in the Reporting Period are
summarized in the following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
114 |
24-hour TSP |
9 |
33 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
47 |
Water Quality |
Water sampling |
5 |
13(*) |
6 |
4 (*) |
||
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and
Auditing |
Contract 2 |
4 |
Contract 3 |
4 |
||
Contract 5 |
4 |
||
Contract 6 |
2 |
||
Contract SS C505 |
4 |
(*) Monitoring day
Breach of Action and Limit (A/L) Levels
ES04
In the Reporting Period, no air quality and noise
exceedance was registered for the Project. For water quality, total of fifteen (15)
Limit Level exceedances, namely four (4) exceedances of turbidity and four (4) exceedances
of suspended solids recorded at WM2A and four (4) exceedances of turbidity and three
(3) exceedance of suspended solids recorded at WM2B. The summary of exceedance
in the Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
||
NOE Issued |
Investigation Result |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
-- |
-- |
Turbidity |
0 |
8 |
8 |
-
The exceedances are
under investigation |
N/A |
|
SS |
0 |
7 |
7 |
Environmental
Complaint
ES05
In this Reporting Period, no environmental
complaints were received related to the EM&A programme.
Notification of
Summons and Successful Prosecutions
ES06
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
ES07
No reporting changes were made in the
Reporting Period.
ES08
In this Reporting Period, joint site inspection to evaluate the site environmental
performance at Contract 2 has been carried out by the RE, IEC, ET
and the Contractor on 2, 9, 16, 20 and 30 October 2015.. No
non-compliance was noted.
ES09
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 5, 16, 19 and 26 October 2015. No non-compliance was noted.
ES10
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
5 has been carried out by the RE, IEC, ET and the Contractor on 8, 14, 22 and 29 October 2015. No non-compliance was noted.
ES11
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 23 and 29 October 2015. No
non-compliance was noted.
ES12
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 22 and 28 October 2015. No non-compliance was noted.
Future Key Issues
ES13
During dry season,
special attention should be paid on the potential construction dust impact
since most of the construction sites are adjacent to villages. The Contractor
should fully implement the construction dust mitigation measures properly.
ES14
The Contractor was also
reminded to prevent muddy water or other water pollutants from site surface flow
to local stream such as Kong Yiu Channel and Ma
Wat Channel or public area. Water
quality mitigation measures to prevent surface runoff into nearby water bodies
or public areas should paid attention and fully implemented.
ES15
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
ES16
Since most of
construction sites under the Project are located adjacent to villages, the
Contractors should fully implement air quality mitigation measures to reduce
construction dust emission.
Table of Contents
2 Project
Organization and Construction progress
2.1 Construction
Contract Packaging
2.5 Summary of Environmental Submissions
3 Summary
of Impact Monitoring Requirements
3.4 Monitoring
Frequency and Period
3.8 Derivation
of Action/Limit (A/L) Levels
3.9 Data
Management and Data QA/QC Control
4.2 Air
Quality Monitoring Results in Reporting Month
5 Construction
Noise Monitoring
5.2 Noise
Monitoring Results in Reporting Month
6.2 Results
of Water Quality Monitoring
7.2 Records
of Waste Quantities
8.2 Findings
/ Deficiencies During the Reporting Month
9 Environmental
Complaint and Non-Compliance
9.1 Environmental
Complaint, Summons and Prosecution
10 Implementation
Status of Mitigation Measures
10.2 Tentative
Construction Activities in the Coming Month
10.3 Key
Issues for the Coming Month
11 Conclusions
and Recommendations
List
of TABLES
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Impact
Monitoring Stations - Air Quality
Table 3-3 Impact
Monitoring Stations - Construction Noise
Table 3-4 Impact
Monitoring Stations - Water Quality
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Construction
Noise Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action and Limit
Levels for Water Quality
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1a
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM4B
Table 4-5 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM5a
Table 4-6 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM6
Table 4-7 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM7a
Table 4-8 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM8
Table 4-9 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Table 5-1 Summary
of Construction Noise Monitoring Results (Contract 3 and 5)
Table 5-2 Summary
of Construction Noise Monitoring Results (Contract 2 and 6)
Table 6-1 Summary
of Water Quality Monitoring Results for Contract 2 and 3
Table 6-2 Summary
of Water Quality Monitoring Results for Contract 5 and SS C505
Table 6-3 Summary
of Water Quality Monitoring Results for Contract 6
Table 6-4 Summary
of Water Quality Monitoring Results for Contract 2 and 6
Table 6-5 Breaches
of Water Quality Monitoring Criteria in Reporting Period
Table 7-1 Summary
of Quantities of Inert C&D Materials
Table 7-2 Summary
of Quantities of C&D Wastes
Table 8-1 Site
Observations for Contract 2
Table 8-2 Site
Observations for Contract 3
Table 8-3 Site
Observations for Contract 5
Table 8-4 Site
Observations for Contract 6
Table 8-5 Site
Observations for Contract SS C505
Table 9-1 Statistical
Summary of Environmental Complaints
Table 9-2 Statistical
Summary of Environmental Summons
Table 9-3 Statistical
Summary of Environmental Prosecution
Table 10-1 Environmental
Mitigation Measures
List of Appendices
Appendix
A Layout Plan of the
Project
Appendix
B Organization Chart
Appendix
C 3-month rolling
construction program
Appendix
D Designated
Monitoring Locations as Recommended in the Approved EM&A Manual
Appendix
E Monitoring
Locations for Impact Monitoring
Appendix
F Calibration
Certificate of Monitoring Equipment and HOKLAS-accreditation Certificate of the
Testing Laboratory
Appendix
G Event and Action
Plan
Appendix
H Impact Monitoring
Schedule
Appendix
I Database of
Monitoring Result
Appendix J Graphical Plots for
Monitoring Result
Appendix
K Meteorological
Data
Appendix
L Waste Flow Table
Appendix
M Implementation Schedule
for Environmental Mitigation Measures
1.1.1
Civil Engineering and Development Department is the Project Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE)
Liantang / Heung Yuen Wai Boundary Control Point and Associated Works, which is
a Designated Project to be implemented under Environmental Permit number EP-404/2011/C granted on 12 March
2015.
1.1.2
The Project consists of two main components: Construction of a Boundary
Control Point (hereinafter referred as ¡§BCP¡¨); and Construction of a connecting
road alignment. Layout plan of the Project is shown in Appendix A.
1.1.3
The proposed BCP is located at the boundary with Shenzhen near the
existing Chuk Yuen Village, comprising a main passenger building with passenger
and cargo processing facilities and the associated customs, transport and
ancillary facilities. The
connecting road alignment consists of six main sections:
1)
Lin Ma Hang to Frontier Closed Area (FCA) Boundary ¡V this section
comprises at-grade and viaducts and includes the improvement works at Lin Ma
Hang Road;
2)
Ping Yeung to Wo Keng Shan ¡V this section
stretches from the Frontier Closed Area Boundary to the tunnel portal at Cheung
Shan and comprises at-grade and viaducts including an interchange at Ping
Yeung;
3)
North Tunnel ¡V this section comprises the tunnel segment at Cheung Shan
and includes a ventilation building at the portals on either end of the tunnel;
4)
Sha Tau Kok Road ¡V this section stretches from the tunnel portal at Wo Keng Shan to the tunnel portal south of Loi Tung and
comprises at-grade and viaducts including an interchange at Sha Tau Kok and an
administration building;
5)
South Tunnel ¡V this section comprises a tunnel segment that stretches from
Loi Tung to Fanling and includes a ventilation building at the portals on
either end of the tunnel as well as a ventilation building in the middle of the
tunnel near Lau Shui Heung;
6)
Fanling ¡V this section comprises the at-grade, viaducts and interchange
connection to the existing Fanling Highway.
1.1.4
Action-United
Environmental Services & Consulting has
been commissioned as an Independent ET to implement the relevant
EM&A program in accordance with the
approved EM&A Manual, as well as the associated duties. As part of the EM&A program, the
baseline monitoring has carried out between 13 June 2013 and 12 July
2013 for all parameters including air quality, noise and water quality
before construction work commencement.
The Baseline Monitoring Report summarized the key findings and the
rationale behind determining a set of Action and Limit Levels (A/L Levels) from
the baseline data. Also, the
Project baseline monitoring report which verified by the IEC has been submitted
to EPD on 16 July 2013 for endorsement. The major construction works of the
Project was commenced on 16 August 2013
in accordance with the EP Section 5.3 stipulation.
1.1.5
This is 27th
monthly EM&A report presenting the monitoring results and inspection
findings for reporting period from 1 to 31 October 2015.
1.2.1
The Monthly Environmental Monitoring and
Audit (EM&A) Report is structured into the following sections:-
Section 1 Introduction
Section 2 Project
Organization and Construction Progress
Section 3 Summary
of Impact Monitoring Requirements
Section 4 Air
Quality Monitoring
Section 5 Construction
Noise Monitoring
Section 6 Water
Quality Monitoring
Section 7 Waste
Management
Section 8 Site
Inspections
Section 9 Environmental
Complaints and Non-Compliance
Section 10 Implementation
Status of Mitigation Measures
Section 11 Conclusions
and Recommendations
2.1.1
To facilitate the project management and
implementation, the Project would be divided by the following contracts:
¡P
Contract 2 (CV/2012/08)
¡P
Contract 3 (CV/2012/09)
¡P
Contract 4 (NE/2014/02)
¡P
Contract 5 (CV/2013/03)
¡P
Contract 6 (CV/2013/08)
¡P
Contract 7 (NE/2014/03)
¡P
ArchSD Contract No. SS C505
2.1.2
The
details of each contracts is summarized below and the delineation of each contracts is shown in Appendix
A.
Contract 2 (CV/2012/08)
2.1.3
Contract 2 has awarded in December 2013 and
construction work was commenced on 19 May 2014. Major Scope of Work of the Contract 2 is
listed below:
¡P
construction of
an approximately 5.2km long dual two-lane connecting road (with about 0.4km of
at-grade road and 4.8km of tunnel) connecting the Fanling Interchange with the
proposed Sha Tau Kok Interchange;
¡P
construction of a
ventilation adit tunnel and the mid-ventilation
building;
¡P
construction of
the north and south portal buildings of the Lung Shan Tunnel and their
associated slope works;
¡P
provision and
installation of ventilation system, E&M works and building services works
for Lung Shan tunnel and Cheung Shan tunnel and their portal buildings;
¡P
construction of
Tunnel Administration Building adjacent to Wo Keng
Shan Road and the associated E&M and building services works; and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 3 (CV/2012/09)
2.1.4
Contract 3 was awarded in July 2013 and
construction work was commenced on 5 November 2013. Major Scope of Work of the Contract 3 is
listed below:
¡P
construction of
four link roads connecting the existing Fanling Highway and the south portal of
the Lung Shan Tunnel;
¡P
realignment of
the existing Tai Wo Service Road West and Tai Wo Service Road East;
¡P
widening of the
existing Fanling Highway (HyD¡¦s
entrustment works);
¡P
demolishing
existing Kiu Tau vehicular bridge and Kiu Tau footbridge and reconstruction of the existing Kiu Tau Footbridge (HyD¡¦s
entrustment works); and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 4 (NE/2014/02)
2.1.5
Contract 4 has not yet been awarded. The work of the Contract 4 includes provision and installation of
Traffic Control and Surveillance System and the associated electrical and
mechanical works for the Project.
Contract 5 (CV/2013/03)
2.1.6
Contract 5 has awarded in April 2013 and construction
work was commenced in August 2013.
Major Scope of Work of the Contract 5 is listed below:
¡P
site formation of about 23
hectares of land for the development of the BCP;
¡P
construction of an
approximately 1.6 km long perimeter road at the BCP including a 175m long
depressed road;
¡P
associated
diversion/modification works at existing local roads and junctions including
Lin Ma Hang Road;
¡P
construction of pedestrian
subway linking the BCP to Lin Ma Hang Road;
¡P
provision of resite area with supporting infrastructure for reprovisioning of the affected village houses; and
¡P
construction of associated footpath, slopes, retaining structures, drainage,
sewerage, waterworks, landscaping works and other ancillary works.
Contract 6 (CV/2013/08)
2.1.7
Contract 6 has awarded in June 2015 and construction
work was commenced on 23 October 2015. Major Scope of Work of the Contract 6 would
be included below:
construction of an approximately 4.6km long dual two-lane connecting
road (with about 0.6km of at-grade road, 3.3km of viaduct and 0.7km of tunnel)
connecting the BCP with the proposed Sha Tau Kok Road Interchange and the
associated ventilation buildings;
associated diversion/modification works at access roads to the resite of Chuk Yuen Village;
provision of sewage collection, treatment and disposal facilities for
the BCP and the resite of Chuk
Yuen Village;
construction of a pedestrian subway linking the BCP to Lin Ma Hang
Road;
provisioning of the affected facilities including Wo Keng Shan Road garden; and
construction of associated footpath, slopes, retaining
structures, drainage, sewerage, waterworks, landscaping works and other
ancillary works.
Contract 7 (NE/2014/03)
2.1.8
Contract 7 has not yet been awarded. Major Scope of Work of the Contract 7 would
be included below:
construction of the Hong Kong Special
Administrative Region (HKSAR) portion of four vehicular bridge
construction of one pedestrian bridge crossing Shenzhen (SZ) River
(cross boundary bridges)
ArchSD Contract No. SS C505
2.1.9
SS C505 has been awarded in July 2015 and
construction work was commenced on 1 September 2015. Major Scope of Work of the SS C505 would
be included below:
passenger-related facilities including
processing kiosks and examination facilities for private cars and coaches,
passenger clearance building and halls, the interior fitting works for the
pedestrian bridge crossing Shenzhen River, etc.;
cargo processing facilities including kiosks
for clearance of goods vehicles, customs inspection platforms, X-ray building,
etc.;
accommodation for the facilities inside of the
Government departments providing services in connection with the BCP;
transport-related facilities inside the BCP
including road networks, public transport interchange, transport drop-off and
pick-up areas, vehicle holding areas and associated road furniture etc;
a public carpark; and
other ancillary
facilities such as sewerage and drainage, building services provisions and
electronic systems, associated environmental mitigation measure and landscape
works.
2.2.1
The project organization is shown in Appendix
B. The responsibilities of
respective parties are:
Civil
Engineering and Development Department (CEDD)
2.2.2
CEDD is the Project Proponent and the Permit Holder of the EP of the development
of the Project and will assume overall responsibility for the project. An
Independent Environmental Checker (IEC) shall be employed by CEDD to audit the
results of the EM&A works carried out by the ET.
Architectural
Services Department (ArchSD)
2.2.3
ArchSD acts as the works agent for
Development Bureau (DEVB), for Contract SS C505 Liantang/ Heung Yuen Wai
Boundary Control Point (BCP) ¡V BCP Buildings and Associated Facilities.
Environmental
Protection Department (EPD)
2.2.4
EPD is the statutory enforcement body for
environmental protection matters in Hong Kong.
Ronald Lu
& Partners (Hong Kong) Ltd (The Architect)
2.2.5
Ronald Lu & Partners (Hong Kong) Ltd is
appointed by ArchSD as an Architect for Contract SS C505 Liantang/ Heung Yuen
Wai Boundary Control Point (BCP) ¡V BCP Buildings and Associated
Facilities. It responsible for
overseeing the construction works of Contract SS C505 and for ensuring that the
works are undertaken by the Contractor in accordance with the specification and
contract requirements. The duties and responsibilities of the Architect with
respect to EM&A are:
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the
environmental mitigation measures and their effectiveness
Monitor Contractors¡¦ and ET¡¦s compliance with
the requirements in the Environmental Permit (EP) and EM&A Manual
Facilitate ET¡¦s implementation of the EM&A
programme
Participate in joint site inspection by the ET
and IEC
Oversee the implementation of the agreed Event
/ Action Plan in the event of any exceedance
Adhere to the procedures for carrying out
complaint investigation
Liaison with DSD, Engineer/Engineer¡¦s
Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s
Regulation of Shenzhen River Stage 4 (RSR 4)¡¨ Project discussing regarding the
cumulative impact issues.
Engineer
or Engineers Representative (ER)
2.2.6
The ER is responsible for overseeing the
construction works and for ensuring that the works are undertaken by the
Contractor in accordance with the specification and contract requirements. The
duties and responsibilities of the ER with respect to EM&A are:
¡P
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the environmental
mitigation measures and their effectiveness
¡P
Monitor Contractors¡¦s,
ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental Permit
(EP) and EM&A Manual
¡P
Facilitate ET¡¦s implementation of the
EM&A programme
¡P
Participate in joint site inspection by the
ET and IEC
¡P
Oversee the implementation of the agreed
Event / Action Plan in the event of any exceedance
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with DSD, Engineer/Engineer¡¦s Representative,
ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s Regulaiton of Shenzhen River Stage 4 (RSR 4)¡¨ Project
discussing regarding the cumulative impact issues.
The
Contractor(s)
2.2.7
There will be one contractor for each
individual works contract. Once the contractors are appointed, EPD, ET and IEC
will be notified the details of the contractor.
2.2.8
The Contractor for Contracts under CEDD
should report to the ER. For ArchSD Contract, the Contractor should report to
the Architect or Architect¡¦s Representative (AR). The duties and
responsibilities of the Contractor are:
¡P
Comply with the relevant contract conditions
and specifications on environmental protection
¡P
Employ an Environmental Team (ET) to
undertake monitoring, laboratory analysis and reporting of EM &A Facilitate
ET¡¦s monitoring and site inspection activities
¡P
Participate in the site inspections by the ET
and IEC, and undertake any corrective actions
¡P
Provide information / advice to the ET
regarding works programme and activities which may contribute to the generation
of adverse environmental impacts
¡P
Submit proposals on mitigation measures in
case of exceedances of Action and Limit levels in accordance with the Event /
Action Plans
¡P
Implement measures to reduce impact where
Action and Limit levels are exceeded
¡P
Adhere to the procedures for carrying out
complaint investigation
Environmental Team (ET)
2.2.9
Once the ET is appointed, the EPD, CEDD, ER, Architect
and IEC will be notified the details of the ET.
2.2.10
The ET shall not be in any way an associated
body of the Contractor(s), and shall be employed by the Project
Proponent/Contractor to conduct the EM&A programme. The ET should be managed by the ET
Leader. The ET Leader shall be a person who has at least 7 years¡¦ experience in
EM&A and has relevant professional qualifications. Suitably qualified staff
should be included in the ET, and resources for the implementation of the
EM&A programme should be allocated in time under the Contract(s), to enable
fulfillment of the Project¡¦s EM&A requirements as specified in the EM&A
Manual during construction of the Project. The ET shall report to the Project
Proponent and the duties shall include:
¡P
Monitor and audit various environmental
parameters as required in this EM&A Manual
¡P
Analyse the
environmental monitoring and audit data, review the success of EM&A
programme and the adequacy of mitigation measures implemented, confirm the
validity of the EIA predictions and identify any adverse environmental impacts
arising
¡P
Carry out regular site inspection to
investigate and audit the Contractors¡¦ site practice, equipment/plant and work
methodologies with respect to pollution control and environmental mitigation,
and effect proactive action to pre-empt problems
¡P
Monitor compliance with conditions in the EP,
environmental protection, pollution prevention and control regulations and
contract specifications
¡P
Audit environmental conditions on site
¡P
Report on the environmental monitoring and
audit results to EPD, the ER, the Architect, the lEC
and Contractor or their delegated representatives
¡P
Recommend suitable mitigation measures to the
Contractor in the case of exceedance of Action and Limit levels in accordance
with the Event and Action Plans
¡P
Liaise with the IEC on all environmental
performance matters and timely submit all relevant EM&A proforma
for approval by IEC
¡P
Advise the Contractor(s) on environmental
improvement, awareness, enhancement measures etc., on site
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, ET, lEC and the
Contractor(s) of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
Independent Environmental Checker (IEC)
2.2.11
One IEC will be employed for this Project.
Once the IEC is appointed, EPD, ER, the Architect and ET will be notified the
details of the IEC.
2.2.12
The Independent Environmental Checker (IEC)
should not be in any way an associated body of the Contractor or the ET for the
Project. The IEC should be employed by the Permit Holder (i.e., CEDD) prior to
the commencement of the construction of the Project. The IEC should have at
least 10 years¡¦ experience in EM&A and have relevant professional
qualifications. The appointment of IEC should be subject to the approval of
EPD. The IEC should:
¡P
Provide proactive advice to the ER and the
Project Proponent on EM&A matters related to the project, independent from
the management of construction works, but empowered to audit the environmental
performance of construction
¡P
Review and audit all aspects of the EM&A
programme implemented by the ET
¡P
Review and verify the monitoring data and all
submissions in connection with the EP and EM&A Manual submitted by the ET
¡P
Arrange and conduct regular, at least monthly
site inspections of the works during construction phase, and ad hoc inspections
if significant environmental problems are identified
¡P
Check compliance with the agreed Event /
Action Plan in the event of any exceedance
¡P
Check compliance with the procedures for
carrying out complaint investigation
¡P
Check the effectiveness of corrective
measures
¡P
Feedback audit results to ET by signing off
relevant EM&A proforma
¡P
Check that the mitigation measures are
effectively implemented
¡P
Verify the log-book(s) mentioned in Condition
2.2 of the EP, notify the Director by fax, within one working day of receipt of
notification from the ET Leader of each and every occurrence, change of
circumstances or non-compliance with the EIA Report and/or the EP, which might
affect the monitoring or control of adverse environmental impacts from the
Project
¡P
Report the works conducted, the findings, recommendation
and improvement of the site inspections, after reviewing ET¡¦s and Contractor¡¦s
works, and advices to the ER and Project Proponent on a monthly basis
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, the Architect, ET, lEC
and the Contractor of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
2.3.1
The concurrent construction works that may be
carried out include, but not limited to, the following:
(a)
Regulation of Shenzhen River Stage IV;
(b)
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange ¡V Contract No. HY/2012/06;
(c)
Construction of BCP
facilities in Shenzhen.
2.4.1
In the Reporting Period, the major
construction activity conducted under the Project is located in Contracts 2, 3,
5, 6 and SS C505 and they are summarized in below. Moreover, the 3-month rolling
construction program of the Contracts 2, 3, 5, 6 and SS C505 is enclosed in Appendix
C.
Contract 2 (CV/2012/08)
2.4.2
The
contract commenced in May 2014. In this Reporting Period, construction
activities conducted are listed below:
Mid-Vent Portal |
Cavern excavation
Adit invert
slab
Tube excavation (NB + SB) towards North
Portal |
North Portal |
Slope stablilization
Southbound tunnel door erection
Northbound top heading canopies and tunnel
door erection
Tunnel Boring Machine and initial drive |
South Portal |
Southbound and Northbound excavation
Drill and Blast Set Up and site
installation
Building works foundation and substructure
Building works superstructure |
|
|
Admin Building |
Removal of surcharge |
|
Contract 3 (CV/2012/09)
2.4.3
The Contract commenced in November 2013. In this Reporting Period, construction
activities conducted are listed below:
Cable
detection and trial trenches
Decking
construction for Bridge E
E&M
work for new valve control & Telemetry House
Filling
works at Tong Hang
Storm
drain laying
Noise
barrier construction
Pier /
pier table construction
Pile cap
works
Piling
works
Portal
beam erection
Pre-drilling
Road works
at Fanling Highway
Retaining
Wall construction
Socket
H-pile installation
Tree
felling works
Utilities
duct laying
Viaduct
segment erection
Slope
works
Contract 4 (Contract number to be assigned)
2.4.4
The contract has not yet been awarded.
Contract 5 (CV/2013/03)
2.4.5
The Contract awarded in April 2013 and
commenced on August 2013. In this
Reporting Period, construction activities conducted are listed below:
Re-construction
of rising main at existing Lin Ma Hang (LMH) Road
Diversion
of Underground Utility (UU) at existing LMH Road
Construction
of secondary boundary fencing
Construction of Temporary Secondary Boundary Fencing
Filling works for ArchSD permanent office
Drainage works for ArchSD permanent office
Construction
of Depressed Road at BCP3
Additional
works (Access Works) for Village House at RS4
Drainage
works at existing/proposed LMH Road
Drainage
works (Connection to Box 3) at BCP Area
Brick
laying at footpath of proposed LMH road
Irrigation
at proposed LMH Road
Formation
works at BCPB Area
Installation
of UU at proposed and existing LMH road
Road works
(kerb laying) for proposed and existing LMH road
Bituminous
laying at existing & proposed LMH road
Contract 6 (CV/2013/08)
2.4.6
Contract 6 has awarded in June 2015 and
construction work was commenced on 23 October 2015. In this Reporting Period,
construction activities conducted are listed below:
- Site
Clearance
- Slope
Works
- Site
Accesses Construction
- Ground Investigation
(GI) Works
Contract 7 (NE/2014/03)
2.4.7
Contract 7 has not yet awarded.
Contract SS C505
2.4.8
Contract SS C505 has awarded in July 2015 and
construction work was commenced on 1 September 2015. In this Reporting Period, construction
activities conducted are listed below:
Excavation
& fill works
Predrilling
Percussive
piling
Pile caps
Site
office set-up
Structure
works
2.5.1
In according to the EP, the required documents
have submitted to EPD for retention which listed in below:
Project Layout Plans of Contracts 2, 3, 5, 6 and SS C505
Landscape Plan
Topsoil Management Plan
Environmental Monitoring and Audit Programme
Baseline Monitoring Report (TCS00690/13/600/R0030v3) for the Project
Waste Management Plan of the Contracts 2, 3, 5
and SS C505
Contamination Assessment Plan (CAP) for Po
Kat Tsai, Loi Tung and the workshops in Fanling
Contamination Assessment Report (CAR) for Po
Kat Tsai, Loi Tung and the workshops in Fanling
Vegetation Survey Report
Woodland Compensation Plan
Habitat Creation Management Plan
2.5.2
Summary of
the relevant permits, licenses, and/or notifications on environmental
protection for the Project of each contracts are presented in Table 2-1.
Table 2-1 Status of Environmental
Licenses and Permits of the Contracts
Item |
Description |
License/Permit Status |
||
Ref. no. |
Effective Date |
Expiry Date |
||
Contract 2 |
||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref No.: 368864 |
31 Dec 2013 |
Till Contract ends |
2 |
Chemical Waste Producer Registration |
North Portal Waste
Producers Number: No.5213-652-D2523-01 |
25 Mar 2014 |
Till Contract ends |
Mid-Vent Portal Waste
Producers Number: No.5213-634-D2524-01 |
25 Mar 2014 |
Till Contract ends |
||
South Portal Waste
Producers Number: No.5213-634-D2526-01 |
9 Apr 2014 |
Till Contract ends |
||
3 |
Water Pollution Control Ordinance - Discharge License |
No.WT00018374-2014 |
3 Mar 2014 |
28 Feb 2019 |
No.: W5/1I389 |
28 Mar 2014 |
31 Mar 2019 |
||
No.: W5/1I390 |
19 June 2014 |
31 Mar 2019 |
||
No.: W5/1I391 |
28 Mar 2014 |
31 Mar 2019 |
||
No.: W5/1I392 |
28 Mar 2014 |
31 Mar 2019 |
||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7019105 |
8 Jan 2014 |
Till Contract ends |
5 |
Construction Noise Permit |
GW-RN0304-15 |
19 May 2015 |
14 Nov 2015 |
GW-RN0468-15 |
29 Aug 2015 |
28 Nov 2015 |
||
GW-RN0467-15 |
23 Aug 2015 |
22 Nov 2015 |
||
GW-RN0477-15 |
14 Aug 2015 |
31 Oct 2015 |
||
GW-RN0479-15 |
31 Jul 2015 |
29 Jan 2016 |
||
GW-RN0562-15 |
7 Sep 2015 |
6 Dec 2015 |
||
GW-RN0606-15 |
25 Sep 2015 |
24 Nov 2015 |
||
Contract 3 |
||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 362101 |
17 Jul 2013 |
Till Contract ends |
2 |
Chemical Waste Producer Registration |
Waste Producers Number:
No.:5113-634-C3817-01 |
7 Oct 2013 |
Till Contract ends |
3 |
Water Pollution Control Ordinance - Discharge License |
No.:WT00016832 ¡V 2013 |
28 Aug 13 |
31 Aug
2018 |
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7017914 |
2 Aug 13 |
Till Contract ends |
5 |
Construction Noise Permit |
GW-RN0230-15 |
15 Apr 2015 |
14 Oct 2015 |
GW-RN0334-15 |
8 Jun 2015 |
7 Dec 2015 |
||
GW-RN0428-15 |
9 Ju1 2015 |
31 Dec 2015 |
||
GW-RN0473-15 |
29 Jul 2015 |
17 Dec 2015 |
||
GW-RN0461-15 |
5 Aug 2015 |
8 Jan 2016 |
||
GW-RN0495-15 |
12 Aug 2015 |
11 Feb 2016 |
||
GW-RN0497-15 |
14 Aug 2015 |
13 Feb 2016 |
||
GW-RN0488-15 |
6 Sep 2015 |
22 Nov 2015 |
||
GW-RN0525-15 |
29 Aug 2015 |
13 Feb 2016 |
||
GW-RN0542-15 |
1 Sep 2015 |
25 Feb 2016 |
||
GW-RN0608-15 |
28 Sep 2015 |
29 Feb 2016 |
||
GW-RN0633-15 |
15 Oct 2015 |
29 Feb 2016 |
||
GW-RN0677-15 |
26 Oct 2015 |
29 Feb 2016 |
||
Contract 5 |
||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 359338 |
13 May 2013 |
Till the end of Contract |
2 |
Chemical Waste Producer Registration |
Waste Producers Number No.:
5213-642-S3735-01 |
8 Jun 2013 |
Till the end of Contract |
3 |
Water Pollution Control Ordinance - Discharge License |
No.: W5/1G44/1 |
8 Jun 13 |
30 Jun 2018 |
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7017351 |
29 Apr 13 |
Till the end of Contract |
Contract 6 |
||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 390614 |
29 Jun 2015 |
Till the end of Contract |
2 |
Chemical Waste Producer Registration |
Waste Producers Number No.: 5213-652-C3969-01 |
31 Aug 2015 |
Till the end of Contract |
3 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7022707 |
9 Jul 2015 |
Till the end of Contract |
4 |
Water Pollution Control Ordinance - Discharge License |
Application
is under consideration by EPD |
||
5 |
Construction Noise Permit |
GW-RN0681-15 |
26 Oct 2015 |
25 Apr 2016 |
6 |
Construction Noise Permit |
GW-RN0683-15 |
26 Oct 2015 |
25 Apr 2016 |
Contract SS C505 |
||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 390974 |
13 Jul 2015 |
Till the end of Contract |
2 |
Chemical Waste Producer Registration |
Waste
Producer No.: 5213-642-L1048-07 |
16 Sep 2015 |
Till the end of Contract |
3 |
Water Pollution Control Ordinance - Discharge License |
Application
is under consideration by EPD |
||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7022831 |
23 Jul 2015 |
Till the end of Contract |
5 |
Construction Noise Permit |
GW-RN0602-15 |
23 Sep 2015 |
21 Mar 2016 |
PP-RN0023-15 |
28 Aug 2015 |
5 Oct 2015 |
||
PP-RN0027-15 |
5 Oct 2015 |
2 Apr 2016 |
3.1.1
The Environmental Monitoring and Audit
requirements are set out in the Approved EM&A manual. Environmental issues
such as air quality, construction noise and water quality were identified as
the key issues during the construction phase of the Project.
3.1.2
A summary of construction phase EM&A
requirements are presented in the
sub-sections below.
3.2.1
The EM&A program of construction phase
monitoring shall cover the following environmental issues:
•
Air quality;
•
Construction noise; and
•
Water quality
3.2.2
A summary of the monitoring parameters is
presented in Table 3-1.
Table 3-1 Summary
of EM&A Requirements
Environmental Issue |
Parameters |
Air Quality |
1-hour
TSP by Real-Time Portable Dust Meter; and 24-hour
TSP by High Volume Air Sampler. |
Noise |
Leq(30min) in
normal working days (Monday to Saturday) 07:00-19:00 except public holiday;
and 3 sets
of consecutive Leq(5min) on restricted
hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday Supplementary
information for data auditing, statistical results such as L10 and
L90 shall also be obtained for reference. |
Water Quality |
In-situ Measurements Dissolved
Oxygen Concentration (mg/L); Dissolved
Oxygen Saturation (% ); Turbidity
(NTU); pH unit; Water
depth (m); and Temperature
(¢J). |
Laboratory Analysis
Suspended
Solids (mg/L) |
3.3.1
The designated monitoring locations as
recommended in the EM&A Manual
are shown in Appendix D. As the access to some of the designated
monitoring locations was questionable due to safety reason or denied by the
landlords, alternative locations therefore have had proposed. The proposed
alternative monitoring locations has updated in the revised EM&A Programme
which verified by IEC and certified by ET Leader prior submitted to EPD on 10
July 2013. Table 3-2, Table
3-3 and Table 3-4 are respectively listed the air quality, construction
noise and water quality monitoring locations for the Project and a map showing
these monitoring stations is presented in Appendix E.
Table 3-2 Impact
Monitoring Stations - Air Quality
Station ID |
Description |
Works Area |
Related to the Work Contract |
AM1a* |
Garden Farm,
Tsung Yuen Ha Village |
BCP |
ArchSD SS C505 Contract 5 |
AM2 |
Village House
near Lin Ma Hang Road |
LMH to Frontier
Closed Area |
Contract 5, Contract 6 |
AM3 |
Ta Kwu Ling
Fire Service Station of Ta Kwu Ling Village. |
LMH to Frontier
Closed Area |
Contract 5, Contract 6 |
AM4b^ |
House no. 10B1 Nga Yiu Ha Village |
LMH to Frontier
Closed Area |
Contract 6 |
AM5a^ |
Ping Yeung
Village House |
Ping Yeung to
Wo Keng Shan |
Contract 6 |
AM6 |
Wo Keng Shan Village House |
Ping Yeung to
Wo Keng Shan |
Contract 6 |
AM7b@ |
Loi Tung Village House |
Sha Tau Kok
Road |
Contract 2 Contract 6 |
AM8 |
Po Kat Tsai
Village No. 4 |
Po Kat Tsai |
Contract 2 |
AM9b# |
Nam Wa Po Village House No. 80 |
Fanling |
Contract 3 |
# Proposal for the change of air quality monitoring location from AM9a
to AM9b was submitted to EPD on 4 Nov 2013 after verified by the IEC and it was
approved by EPD (EPD¡¦s ref.: (15) in EP 2/N7/A/52 Pt.10 dated 8 Nov 2013).
* Proposal for the change of air quality monitoring location from AM1to
AM1a was submitted to EPD on 24 March 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (6) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
@ Proposal for the change of air quality monitoring location from AM7a to
AM7b was submitted to EPD on 4 June 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (7) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
^ proposal for change of monitoring location
are subject to approve by EPD.
Table 3-3 Impact
Monitoring Stations - Construction Noise
Station ID |
Description |
Works Area |
Related to the Work Contract |
NM1 |
Tsung Yuen Ha Village House No. 63 |
BCP |
ArchSD SS C505 Contract 5 |
NM2 |
Village House near Lin Ma Hang
Road |
Lin Ma Hang to Frontier Closed
Area |
Contract 5, Contract 6 |
NM3 |
Ping Yeung Village House (facade
facing northeast) |
Ping Yeung to Wo Keng Shan |
Contract 6 |
NM4 |
Wo Keng
Shan Village House |
Ping Yeung to Wo Keng Shan |
Contract 6 |
NM5 |
Village House, Loi Tung |
Sha Tau Kok Road |
Contract 2, Contract 6 |
NM6 |
Tai Tong Wu Village House 2 |
Sha Tau Kok Road |
Contract 2, Contract 6 |
NM7 |
Po Kat Tsai Village |
Po Kat Tsai |
Contract 2 |
NM8 |
Village House, Tong Hang |
Fanling |
Contract 2 Contract 3 |
NM9 |
Village House, Kiu
Tau Village |
Fanling |
Contract 3 |
NM10 |
Nam Wa
Po Village House No. 80 |
Fanling |
Contract 3 |
Table 3-4 Impact
Monitoring Stations - Water Quality
Station ID |
Description |
Coordinates of Designated / Alternative Location |
Nature of the location |
Related to the Work Contract |
|
WM1 |
Downstream of Kong Yiu Channel |
833 679 |
845 421 |
Alternative location located at upstream 51m of the designated location |
ArchSD SS C505 Contract 5 |
WM1- Control |
Upstream of Kong Yiu Channel |
834 185 |
845 917 |
NA |
ArchSD SS C505 Contract 5 |
WM2A |
Downstream of River Ganges |
834 204 |
844 471 |
Alternative location located at downstream 81m of the designated
location |
Contract 6 |
WM2A- Control |
Upstream of River Ganges |
835 270 |
844 243 |
Alternative location located at upstream 78m of the designated location |
Contract 6 |
WM2B |
Downstream of River Ganges |
835 433 |
843 397 |
NA |
Contract 6 |
WM2B- Control |
Upstream of River Ganges |
835 835 |
843 351 |
Alternative location located at downstream 31m of the designated
location |
Contract 6 |
WM3 |
Downstream of River Indus |
836 324 |
842 407 |
NA |
Contract 2 Contract 6 |
WM3- Control |
Upstream of River Indus |
836 763 |
842 400 |
Alternative location located at downstream 26m of the designated
location |
Contract 2 Contract 6 |
WM4 |
Downstream of Ma Wat Channel |
833 850 |
838 338 |
Alternative location located at upstream 11m of the designated location |
Contract 2 Contract 3 |
WM4¡V Control A |
Kau Lung Hang
Stream |
834 028 |
837 695 |
Alternative location located at downstream 28m of the designated
location |
Contract 2 Contract 3 |
WM4¡V Control B |
Upstream of Ma Wat Channel |
833760 |
837395 |
Alternative location located at upstream 15m of the designated location |
Contract 2 Contract 3 |
The requirements of impact monitoring are stipulated in Sections 2.1.6, 3.1.5 and 4.1.6 of the approved EM&A Manual and presented as follows.
Air Quality Monitoring
3.4.1
Frequency of impact air quality monitoring is
as follows:
1-hour TSP |
3 times every six
days during course of works |
24-hour TSP |
Once every 6 days
during course of works. |
Noise Monitoring
3.4.2
One set of Leq(30min)
as 6 consecutive Leq(5min)
between 0700-1900 hours on normal weekdays and once every week during course of
works. If construction work
necessary to carry out at other time periods, i.e. restricted time period
(19:00 to 07:00 the next morning and whole day on public holidays) (hereinafter
referred as ¡§the restricted hours¡¨), 3 consecutive Leq(5min)
measurement will depended CNP requirements to undertake. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for
reference.
Water Quality Monitoring
3.4.3
The water quality monitoring frequency shall
be 3 days per week during course of works.
The interval between two sets of monitoring shall not be less than 36
hours.
Air Quality Monitoring
3.5.1
The 24-hour and 1-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B. If the ET proposes to use a direct
reading dust meter to measure 1-hour TSP levels, it shall submit sufficient
information to the IEC to approve.
3.5.2
The filter paper of
24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.
3.5.3
All equipment to be used for air quality
monitoring is listed in Table 3-5.
Table 3-5 Air
Quality Monitoring Equipment
Equipment |
Model |
24-Hr TSP |
|
High
Volume Air Sampler |
TISCH High Volume
Air Sampler, HVS Model TE-5170* |
Calibration
Kit |
TISCH Model TE-5025A* |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3B
Laser Dust monitor Particle Mass Profiler & Counter* |
* Instrument was used in the Reporting
Period and the calibration certificate could be referred in Appendix F.
Wind Data Monitoring Equipment
3.5.4
According to the approved EM&A Manual,
wind data monitoring equipment shall also be provided and set up for logging
wind speed and wind direction near the dust monitoring locations. The equipment installation location
shall be proposed by the ET and agreed with the IEC. For installation and operation of wind
data monitoring equipment, the following points shall be observed:
1)
The wind sensors should be installed 10 m
above ground so that they are clear of obstructions or turbulence caused by
buildings.
2)
The wind data should be captured by a data logger.
The data shall be downloaded for analysis at least once a month.