|  |  |  | ||||
|  |  |  | ||||
|  |  |  | ||||
|  |  | Job No.: TCS00694/13 |  |  | ||
|  |  |  |  |  | ||
|  |  | Agreement No. CE 45/2008
  (CE)  Liantang/Heung Yuen Wai  Boundary Control Point
  and Associated Works |  |  | ||
|  |  |  |  |  | ||
|  |  | Monthly Environmental Monitoring and Audit Report (No.30)
  ¡V January 2016 |  |  | ||
|  |  | Prepared For |  |  | ||
|  |  | Civil Engineering and Development Department (CEDD) |  |  | ||
| Date | Reference No. | Prepared By | Certified By | 
| 16
  February 2016 | TCS00694/13/600/R0135v2 | 
 | 
 | 
| Nicola Hon (Environmental Consultant) | Tam Tak Wing (Environmental Team Leader) | 
| Version | Date | Remarks | 
| 1 | 15 February 2016 | First
  Submission | 
| 2 | 16 February 2016 | Amended
  against the IEC¡¦s comments on 16 February 2016 | 
|  |  |  | 

executive summary
ES01           
This is the 30th monthly EM&A report presenting the monitoring
results and inspection findings for the reporting period from 1 to 31 January
2016 (hereinafter ¡¥the Reporting Period¡¦).
Environmental Monitoring
and Audit Activities
ES02           
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project is
divided to six CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (TCSS), Contract 5 (CV/2013/03), Contract 6
(CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03           
In the Reporting Period, the construction
works under Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project
currently included Contract 2, Contract 3, Contract 5, Contract 6 and Contract
SS C505.  In addition, site
preparation work for Contract 7 has been commenced in January 2016.  Environmental monitoring activities
under the EM&A programme in the Reporting Period are summarized in the
following table.
| Environmental Aspect | Environmental
  Monitoring Parameters / Inspection | Reporting Period | |
| Number of Monitoring
  Locations to undertake | Total Occasions   | ||
| Air Quality | 1-hour TSP | 9 | 135 | 
| 24-hour TSP | 9 | 48 | |
| Construction Noise | Leq(30min) Daytime | 10 | 50 | 
| Water Quality | Water in-situ
  measurement and/or sampling | WM1 & WM1-C, | 13(*) | 
| WM2A & WM2A-C | 14(*) | ||
| WM2B & WM2B-C | 20(*) | ||
| WM3 &WM3-C | 13(*) | ||
| WM4, WM4-CA &WM4-CB | 13(*) | ||
| Joint Site Inspection / Audit | IEC, ET, the Contractor and RE joint site Environmental Inspection and
  Auditing | Contract 2 | 4 | 
| Contract 3 | 4 | ||
| Contract 5 | 4 | ||
| Contract 6 | 4 | ||
| Contract 7 | 2 | ||
| Contract SS C505 | 4 | ||
(*) Monitoring day
Breach of Action and Limit (A/L) Levels
ES04           
In the Reporting Period, no air quality and
construction noise exceedance was registered for the Project.  For water quality monitoring, a total of
twenty-three (23) Limit/Action Levels exceedances were recorded, namely one (1)
AL and twelve (12) LL exceedance of turbidity and one (1) AL and nine (9) LL exceedance
of Suspended Solids for the Project. The summary of exceedance in the Reporting
Period is shown below.
| Environmental
   Aspect | Monitoring Parameters | Action Level | Limit Level | Event & Action | ||
| NOE Issued | Investigation Result | Corrective Actions | ||||
| Air Quality | 1-hour TSP | 0 | 0 | 0 | -- | -- | 
| 24-hour TSP | 0 | 0 | 0 | -- | -- | |
| Construction Noise | Leq(30min) Daytime | 0 | 0 | 0 | -- | -- | 
| Water Quality | DO | 0 | 0 | 0 | -- | -- | 
| Turbidity | 1 | 12 | 13 | The Contractor of C6 were advised to
  improve the water mitigation measure as per the ISEMM of the EM&A
  Manual   | Improvement works have been
  undertaken by the Contractor C6  | |
| SS | 1 | 9 | 10 | |||
Environmental
Complaint
ES05           
In this Reporting Period, one (1) verbal
complaint received by the Contractor and two (2) documented environmental
complaints regarding
wastewater / muddy water related to Contracts 6 were received and
lodged by EPD on 14 and 20 January 2016 respectively.  Follow up actions have been undertaking
by the Contractor to resolve the deficiencies and investigation report
conducted by ET had submitted to all relevant parties.  
Notification of Summons and Successful Prosecutions
ES06           
No environmental summons or successful
prosecutions were recorded in the Reporting Period.  However, a warning letter from EPD was
issued to Contract 6 on 1 February 2016 regarding Non Compliance (NC) with APCO
for the non-covered dump trucks travelling to Fill Bank at TM Area 38 on 14 and
18 January 2016 respectively.  The
Contractor has explained to the EPD that all dump trucks under the Contract
were well covered before leaving the site, however, some drivers of the dump
trucks immediately opened the cover when they just get into Fill Bank at TM
Area 38 and captured by the CCTV.  A
briefing and warning letter has given to the relevant drivers to prevent
reoccurrence of similar case. 
 
ES07           
No reporting changes were made in the
Reporting Period. 
ES08           
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 8, 15, 22 and 29 January 2016.  No
non-compliance was noted. 
ES09           
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 4, 11, 20 and 25 January 2016.  No non-compliance was noted.
ES10           
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
5 has been carried out by the RE, IEC, ET and the Contractor on 7, 12, 19 and 26 January 2016.  No non-compliance was noted.
ES11           
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 21 and 28 January 2016.  No non-compliance was noted.
ES12           
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 20 and 27 January 2016.  No non-compliance was noted.
ES13           
Although
construction activities under Contract 7 have not yet commenced,
site preparation work was carried out in the Reporting Period.  Therefore, two occasions of joint site
inspection by the RE, IEC and ET with the Contractor to evaluate the site
environmental performance were carried out on 5 and 26 January 2016. 
No non-compliance was noted.
Future Key Issues
ES14           
During dry season,
special attention should be paid on the potential construction dust impact
since most of the construction sites are adjacent to villages. The Contractor
should fully implement the construction dust mitigation measures properly.
ES15           
The Contractor was
reminded to prevent muddy water or other water pollutants from site surface flow
to local stream such as Kong Yiu Channel, Ma Wat
Channel, Ping Yuen River or public area.  For all Contracts, water quality mitigation
measures to prevent muddy runoff into nearby water bodies or public areas
should paid attention and fully implemented in particular for Contract 6.
ES16           
Construction noise would
be a key environmental issue during construction work of the Project.  Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
Table of Contents
2     Project
Organization and Construction progress  
2.1            Construction
Contract Packaging
2.5            Summary of Environmental Submissions
3     Summary
of Impact Monitoring Requirements
3.4            Monitoring
Frequency and Period
3.8            Derivation
of Action/Limit (A/L) Levels
3.9            Data
Management and Data QA/QC Control
4.2            Air
Quality Monitoring Results in Reporting Month
5     Construction
Noise Monitoring
5.2            Noise
Monitoring Results in Reporting Month   
6.2            Results
of Water Quality Monitoring
7.2            Records
of Waste Quantities
8.2            Findings
/ Deficiencies During the Reporting Month
9     Environmental
Complaint and Non-Compliance
9.1            Environmental
Complaint, Summons and Prosecution
10   Implementation
Status of Mitigation Measures
10.2          Tentative
Construction Activities in the Coming Month
10.3          Key
Issues for the Coming Month
11   Conclusions
and Recommendations
List
of TABLES
Table 2-1        Status
of Environmental Licenses and Permits of the Contracts
Table 3-1        Summary
of EM&A Requirements
Table 3-2        Impact
Monitoring Stations - Air Quality
Table 3-3        Impact
Monitoring Stations - Construction Noise
Table 3-4        Impact
Monitoring Stations - Water Quality
Table 3-5        Air
Quality Monitoring Equipment
Table 3-6        Construction
Noise Monitoring Equipment
Table 3-7        Water
Quality Monitoring Equipment
Table 3-8        Action
and Limit Levels for Air Quality Monitoring
Table 3-9        Action
and Limit Levels for Construction Noise
Table 3-10      Action and Limit
Levels for Water Quality 
Table 4-1        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1a
Table 4-2        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Table 4-3        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Table 4-4        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM4B
Table 4-5        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM5a
Table 4-6        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM6
Table 4-7        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM7a
Table 4-8        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM8
Table 4-9        Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Table 5-1        Summary
of Construction Noise Monitoring Results (Contract 3 and 5)
Table 5-2        Summary
of Construction Noise Monitoring Results (Contract 2 and 6)
Table 6-1        Summary
of Water Quality Monitoring Results for Contract 2 and 3
Table 6-2        Summary
of Water Quality Monitoring Results for Contract 5 and SS C505
Table 6-3        Summary
of Water Quality Monitoring Results for Contract 6
Table 6-4        Summary
of Water Quality Monitoring Results for Contract 2 and 6
Table 6-5        Breaches
of Water Quality Monitoring Criteria in Reporting Period
Table 6-6        Summary
of Water Quality Exceedance in the Reporting Period
Table 7-1        Summary
of Quantities of Inert C&D Materials
Table 7-2        Summary
of Quantities of C&D Wastes
Table 8-1        Site
Observations for Contract 2
Table 8-2        Site
Observations for Contract 3
Table 8-3        Site
Observations for Contract 5
Table 8-4        Site
Observations for Contract 6
Table 8-5        Site
Observations for Contract SS C505
Table 8-6        Site
Observations for Contract 7
Table 9-1        Statistical
Summary of Environmental Complaints
Table 9-2        Statistical
Summary of Environmental Summons
Table 9-3        Statistical
Summary of Environmental Prosecution
Table 10-1      Environmental
Mitigation Measures
List of Appendices
Appendix
A    Layout Plan of the
Project
Appendix
B    Organization Chart
Appendix
C    3-month rolling
construction program
Appendix
D    Designated
Monitoring Locations as Recommended in the Approved EM&A Manual
Appendix
E    Monitoring
Locations for Impact Monitoring
Appendix
F     Calibration
Certificate of Monitoring Equipment and HOKLAS-accreditation Certificate of the
Testing Laboratory
Appendix
G    Event and Action
Plan
Appendix
H    Impact Monitoring
Schedule
Appendix
I     Database of
Monitoring Result
Appendix
J     Graphical
Plots for Monitoring Result
Appendix
K    Meteorological
Data
Appendix
L    Waste Flow Table 
Appendix
M   Implementation Schedule
for Environmental Mitigation Measures
Appendix
N    Investigation
Report for Exceedance
1.1.1                
Civil Engineering and Development Department is the Project Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE)
Liantang / Heung Yuen Wai Boundary Control Point and Associated Works, which is
a Designated Project to be implemented under Environmental Permit number EP-404/2011/C granted on 12 March
2015.  
1.1.2                
The Project consists of two main components: Construction of a Boundary
Control Point (hereinafter referred as ¡§BCP¡¨); and Construction of a connecting
road alignment.  Layout plan of the Project is shown in Appendix A.
1.1.3                
The proposed BCP is located at the boundary with Shenzhen near the
existing Chuk Yuen Village, comprising a main passenger building with passenger
and cargo processing facilities and the associated customs, transport and
ancillary facilities.  The
connecting road alignment consists of six main sections:
1)            
Lin Ma Hang to Frontier Closed Area (FCA) Boundary ¡V this section
comprises at-grade and viaducts and includes the improvement works at Lin Ma
Hang Road;
2)            
Ping Yeung to Wo Keng Shan ¡V this section
stretches from the Frontier Closed Area Boundary to the tunnel portal at Cheung
Shan and comprises at-grade and viaducts including an interchange at Ping
Yeung;
3)            
North Tunnel ¡V this section comprises the tunnel segment at Cheung Shan
and includes a ventilation building at the portals on either end of the tunnel;
4)            
Sha Tau Kok Road ¡V this section stretches from the tunnel portal at Wo Keng Shan to the tunnel portal south of Loi Tung and
comprises at-grade and viaducts including an interchange at Sha Tau Kok and an
administration building;
5)            
South Tunnel ¡V this section comprises a tunnel segment that stretches from
Loi Tung to Fanling and includes a ventilation building at the portals on
either end of the tunnel as well as a ventilation building in the middle of the
tunnel near Lau Shui Heung;
6)            
Fanling ¡V this section comprises the at-grade, viaducts and interchange
connection to the existing Fanling Highway.
1.1.4                
Action-United
Environmental Services & Consulting has
been commissioned as an Independent ET to implement the relevant
EM&A program in accordance with the
approved EM&A Manual, as well as the associated duties.  As part of the EM&A program, the
baseline monitoring has carried out between 13 June 2013 and 12 July
2013 for all parameters including air quality, noise and water quality
before construction work commencement. 
The Baseline Monitoring Report summarized the key findings and the
rationale behind determining a set of Action and Limit Levels (A/L Levels) from
the baseline data.  Also, the
Project baseline monitoring report which verified by the IEC has been submitted
to EPD on 16 July 2013 for endorsement.  The major construction works of the
Project was commenced on 16 August 2013
in accordance with the EP Section 5.3 stipulation.
1.1.5                
This is 30th
monthly EM&A report presenting the monitoring results and inspection
findings for reporting period from 1 to 31 January 2016.
1.2.1                
The Monthly Environmental Monitoring and
Audit (EM&A) Report is structured into the following sections:-
Section 1     Introduction
Section 2     Project
Organization and Construction Progress
Section 3     Summary
of Impact Monitoring Requirements
Section 4     Air
Quality Monitoring
Section 5     Construction
Noise Monitoring
Section 6     Water
Quality Monitoring
Section 7     Waste
Management
Section 8     Site
Inspections
Section 9     Environmental
Complaints and Non-Compliance
Section 10   Implementation
Status of Mitigation Measures
Section 11   Conclusions
and Recommendations
2.1.1                
To facilitate the project management and
implementation, the Project would be divided by the following contracts:
¡P             
Contract 2 (CV/2012/08)
¡P             
Contract 3 (CV/2012/09)
¡P             
Contract 4 (NE/2014/02)
¡P             
Contract 5 (CV/2013/03)
¡P             
Contract 6 (CV/2013/08)
¡P             
Contract 7 (NE/2014/03)
¡P             
ArchSD Contract No. SS C505
2.1.2                
The
details of each contracts is summarized below and the delineation of each contracts is shown in Appendix
A.
Contract 2 (CV/2012/08)
2.1.3                
Contract 2 has awarded in December 2013 and
construction work was commenced on 19 May 2014.  Major Scope of Work of the Contract 2 is
listed below:
¡P               
construction of
an approximately 5.2km long dual two-lane connecting road (with about 0.4km of
at-grade road and 4.8km of tunnel) connecting the Fanling Interchange with the
proposed Sha Tau Kok Interchange;
¡P               
construction of a
ventilation adit tunnel and the mid-ventilation
building; 
¡P               
construction of
the north and south portal buildings of the Lung Shan Tunnel and their
associated slope works;
¡P               
provision and
installation of ventilation system, E&M works and building services works
for Lung Shan tunnel and Cheung Shan tunnel and their portal buildings;
¡P               
construction of
Tunnel Administration Building adjacent to Wo Keng
Shan Road and the associated E&M and building services works; and
¡P               
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works. 
Contract 3 (CV/2012/09)
2.1.4                
Contract 3 was awarded in July 2013 and
construction work was commenced on 5 November 2013.  Major Scope of Work of the Contract 3 is
listed below:
¡P               
construction of
four link roads connecting the existing Fanling Highway and the south portal of
the Lung Shan Tunnel;
¡P               
realignment of
the existing Tai Wo Service Road West and Tai Wo Service Road East;
¡P               
widening of the
existing Fanling Highway (HyD¡¦s
entrustment works);
¡P               
demolishing
existing Kiu Tau vehicular bridge and Kiu Tau footbridge and reconstruction of
the existing Kiu Tau Footbridge (HyD¡¦s entrustment
works); and
¡P               
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 4 (NE/2014/02)
2.1.5                
Contract 4 has not yet been awarded.  The work of the Contract 4 includes provision and installation of
Traffic Control and Surveillance System and the associated electrical and
mechanical works for the Project.
Contract 5 (CV/2013/03)
2.1.6                
Contract 5 has awarded in April 2013 and construction
work was commenced in August 2013. 
Major Scope of Work of the Contract 5 is listed below:
¡P               
site formation of about 23
hectares of land for the development of the BCP;
¡P               
construction of an
approximately 1.6 km long perimeter road at the BCP including a 175m long depressed
road;
¡P               
associated
diversion/modification works at existing local roads and junctions including
Lin Ma Hang Road; 
¡P               
construction of pedestrian
subway linking the BCP to Lin Ma Hang Road;
¡P               
provision of resite area with supporting infrastructure for reprovisioning of the affected village houses; and 
¡P               
construction of associated footpath, slopes, retaining structures, drainage,
sewerage, waterworks, landscaping works and other ancillary works. 
Contract 6 (CV/2013/08)
2.1.7                
Contract 6 has awarded in June 2015 and
construction work was commenced on 23 October 2015.  Major Scope of Work of the Contract 6 would
be included below:
    construction of an approximately 4.6km long dual two-lane connecting
road (with about 0.6km of at-grade road, 3.3km of viaduct and 0.7km of tunnel)
connecting the BCP with the proposed Sha Tau Kok Road Interchange and the
associated ventilation buildings; 
    associated diversion/modification works at access roads to the resite of Chuk Yuen Village; 
    provision of sewage collection, treatment and disposal facilities for
the BCP and the resite of Chuk
Yuen Village; 
    construction of a pedestrian subway linking the BCP to Lin Ma Hang
Road;
    provisioning of the affected facilities including Wo Keng Shan Road garden; and
    construction of associated footpath, slopes, retaining
structures, drainage, sewerage, waterworks, landscaping works and other
ancillary works.
Contract 7 (NE/2014/03)
2.1.8                
Contract 7 has awarded in December 2015 and
the construction works of Contract 7 will tentatively commence in February 2016.
 Major Scope of Work of the Contract
7 would be included below:
   
construction of the Hong Kong Special
Administrative Region (HKSAR) portion of four vehicular bridge
    construction of one pedestrian bridge crossing Shenzhen (SZ) River
(cross boundary bridges)
ArchSD Contract No. SS C505
2.1.9                
SS C505 has awarded in July 2015 and
construction work was commenced on 1 September 2015.  Major Scope of Work of the SS C505 would
be included below:
   
passenger-related facilities including
processing kiosks and examination facilities for private cars and coaches,
passenger clearance building and halls, the interior fitting works for the
pedestrian bridge crossing Shenzhen River, etc.;
   
cargo processing facilities including kiosks
for clearance of goods vehicles, customs inspection platforms, X-ray building,
etc.;
   
accommodation for the facilities inside of the
Government departments providing services in connection with the BCP;
   
transport-related facilities inside the BCP
including road networks, public transport interchange, transport drop-off and
pick-up areas, vehicle holding areas and associated road furniture etc;
   
a public carpark; and 
   
other ancillary
facilities such as sewerage and drainage, building services provisions and
electronic systems, associated environmental mitigation measure and landscape
works.
2.2.1                
The project organization is shown in Appendix
B.  The responsibilities of
respective parties are:
Civil
Engineering and Development Department (CEDD)
2.2.2                
CEDD is the Project Proponent and the Permit Holder of the EP of the development
of the Project and will assume overall responsibility for the project. An
Independent Environmental Checker (IEC) shall be employed by CEDD to audit the
results of the EM&A works carried out by the ET.
Architectural
Services Department (ArchSD)
2.2.3                
ArchSD acts as the works agent for
Development Bureau (DEVB), for Contract SS C505 Liantang/ Heung Yuen Wai
Boundary Control Point (BCP) ¡V BCP Buildings and Associated Facilities.
Environmental
Protection Department (EPD)
2.2.4                
EPD is the statutory enforcement body for
environmental protection matters in Hong Kong.
Ronald Lu
& Partners (Hong Kong) Ltd (The Architect)
2.2.5                
Ronald Lu & Partners (Hong Kong) Ltd is
appointed by ArchSD as an Architect for Contract SS C505 Liantang/ Heung Yuen
Wai Boundary Control Point (BCP) ¡V BCP Buildings and Associated
Facilities.  It responsible for
overseeing the construction works of Contract SS C505 and for ensuring that the
works are undertaken by the Contractor in accordance with the specification and
contract requirements. The duties and responsibilities of the Architect with
respect to EM&A are: 
   
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the
environmental mitigation measures and their effectiveness
   
Monitor Contractors¡¦ and ET¡¦s compliance with
the requirements in the Environmental Permit (EP) and EM&A Manual
   
Facilitate ET¡¦s implementation of the EM&A
programme 
   
Participate in joint site inspection by the ET
and IEC 
   
Oversee the implementation of the agreed Event
/ Action Plan in the event of any exceedance
   
Adhere to the procedures for carrying out
complaint investigation 
   
Liaison with DSD, Engineer/Engineer¡¦s
Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s
Regulation of Shenzhen River Stage 4 (RSR 4)¡¨ Project discussing regarding the
cumulative impact issues.
Engineer
or Engineers Representative (ER)
2.2.6                
The ER is responsible for overseeing the
construction works and for ensuring that the works are undertaken by the
Contractor in accordance with the specification and contract requirements. The
duties and responsibilities of the ER with respect to EM&A are:
¡P          
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the
environmental mitigation measures and their effectiveness
¡P          
Monitor Contractors¡¦s,
ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental Permit
(EP) and EM&A Manual
¡P          
Facilitate ET¡¦s implementation of the
EM&A programme 
¡P          
Participate in joint site inspection by the
ET and IEC 
¡P          
Oversee the implementation of the agreed
Event / Action Plan in the event of any exceedance
¡P          
Adhere to the procedures for carrying out
complaint investigation 
¡P          
Liaison with DSD, Engineer/Engineer¡¦s
Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s Regulaiton of Shenzhen River Stage 4 (RSR 4)¡¨ Project
discussing regarding the cumulative impact issues. 
The
Contractor(s)
2.2.7                
There will be one contractor for each
individual works contract. Once the contractors are appointed, EPD, ET and IEC
will be notified the details of the contractor.
2.2.8                
The Contractor for Contracts under CEDD
should report to the ER. For ArchSD Contract, the Contractor should report to
the Architect or Architect¡¦s Representative (AR). The duties and
responsibilities of the Contractor are:
¡P          
Comply with the relevant contract conditions
and specifications on environmental protection 
¡P          
Employ an Environmental Team (ET) to
undertake monitoring, laboratory analysis and reporting of EM &A Facilitate
ET¡¦s monitoring and site inspection activities 
¡P          
Participate in the site inspections by the ET
and IEC, and undertake any corrective actions 
¡P          
Provide information / advice to the ET
regarding works programme and activities which may contribute to the generation
of adverse environmental impacts 
¡P          
Submit proposals on mitigation measures in
case of exceedances of Action and Limit levels in accordance with the Event /
Action Plans 
¡P          
Implement measures to reduce impact where
Action and Limit levels are exceeded 
¡P          
Adhere to the procedures for carrying out
complaint investigation 
Environmental Team (ET)
2.2.9                
Once the ET is appointed, the EPD, CEDD, ER, Architect
and IEC will be notified the details of the ET.
2.2.10            
The ET shall not be in any way an associated
body of the Contractor(s), and shall be employed by the Project
Proponent/Contractor to conduct the EM&A programme.  The ET should be managed by the ET
Leader. The ET Leader shall be a person who has at least 7 years¡¦ experience in
EM&A and has relevant professional qualifications. Suitably qualified staff
should be included in the ET, and resources for the implementation of the
EM&A programme should be allocated in time under the Contract(s), to enable
fulfillment of the Project¡¦s EM&A requirements as specified in the EM&A
Manual during construction of the Project.  The ET shall report to the Project
Proponent and the duties shall include:
¡P          
Monitor and audit various environmental
parameters as required in this EM&A Manual
¡P          
Analyse the
environmental monitoring and audit data, review the success of EM&A
programme and the adequacy of mitigation measures implemented, confirm the
validity of the EIA predictions and identify any adverse environmental impacts
arising 
¡P          
Carry out regular site inspection to
investigate and audit the Contractors¡¦ site practice, equipment/plant and work
methodologies with respect to pollution control and environmental mitigation,
and effect proactive action to pre-empt problems 
¡P          
Monitor compliance with conditions in the EP,
environmental protection, pollution prevention and control regulations and
contract specifications 
¡P          
Audit environmental conditions on site 
¡P          
Report on the environmental monitoring and
audit results to EPD, the ER, the Architect, the lEC
and Contractor or their delegated representatives 
¡P          
Recommend suitable mitigation measures to the
Contractor in the case of exceedance of Action and Limit levels in accordance
with the Event and Action Plans 
¡P          
Liaise with the IEC on all environmental
performance matters and timely submit all relevant EM&A proforma
for approval by IEC 
¡P          
Advise the Contractor(s) on environmental
improvement, awareness, enhancement measures etc., on site 
¡P          
Adhere to the procedures for carrying out
complaint investigation 
¡P          
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, ET, lEC and the
Contractor(s) of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
Independent Environmental Checker (IEC) 
2.2.11            
One IEC will be employed for this Project.
Once the IEC is appointed, EPD, ER, the Architect and ET will be notified the
details of the IEC.
2.2.12            
The Independent Environmental Checker (IEC)
should not be in any way an associated body of the Contractor or the ET for the
Project. The IEC should be employed by the Permit Holder (i.e., CEDD) prior to
the commencement of the construction of the Project. The IEC should have at
least 10 years¡¦ experience in EM&A and have relevant professional
qualifications. The appointment of IEC should be subject to the approval of
EPD. The IEC should: 
¡P          
Provide proactive advice to the ER and the
Project Proponent on EM&A matters related to the project, independent from
the management of construction works, but empowered to audit the environmental
performance of construction 
¡P          
Review and audit all aspects of the EM&A
programme implemented by the ET 
¡P          
Review and verify the monitoring data and all
submissions in connection with the EP and EM&A Manual submitted by the ET 
¡P          
Arrange and conduct regular, at least monthly
site inspections of the works during construction phase, and ad hoc inspections
if significant environmental problems are identified 
¡P          
Check compliance with the agreed Event /
Action Plan in the event of any exceedance 
¡P          
Check compliance with the procedures for
carrying out complaint investigation 
¡P          
Check the effectiveness of corrective
measures 
¡P          
Feedback audit results to ET by signing off
relevant EM&A proforma 
¡P          
Check that the mitigation measures are
effectively implemented 
¡P          
Verify the log-book(s) mentioned in Condition
2.2 of the EP, notify the Director by fax, within one working day of receipt of
notification from the ET Leader of each and every occurrence, change of
circumstances or non-compliance with the EIA Report and/or the EP, which might
affect the monitoring or control of adverse environmental impacts from the
Project
¡P          
Report the works conducted, the findings,
recommendation and improvement of the site inspections, after reviewing ET¡¦s
and Contractor¡¦s works, and advices to the ER and Project Proponent on a
monthly basis 
¡P          
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, the Architect, ET, lEC
and the Contractor of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
2.3.1                
The concurrent construction works that may be
carried out include, but not limited to, the following:
                               
(a)           
Regulation of Shenzhen River Stage IV;
                               
(b)           
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange ¡V Contract No. HY/2012/06;
                               
(c)           
Construction of BCP
facilities in Shenzhen.
2.4.1                
In the Reporting Period, the major
construction activity conducted under the Project is located in Contracts 2, 3,
5, 6 and SS C505 and they are summarized in below.  Moreover, the 3-month rolling construction
program of the Contracts 2, 3, 5, 6 and SS C505 is enclosed in Appendix
C.  For Contract 7, construction
activities were scheduled to commence in February 2016 and therefore no
construction activities was undertaken in the Reporting Period.
Contract 2 (CV/2012/08)
2.4.2                
The
contract commenced in May 2014. In this Reporting Period, construction
activities conducted are listed below:
| Mid-Vent Portal |    
  Installation of blast curtain    
  Tube excavation (NB + SB)     
  Adit invert
  slab    
  Building works foundation | 
| North Portal |    
  Slope stablilization
  and retaining wall    
  Northbound top heading excavation and
  tunnel enlargement    
  Tunnel Boring Machine excavation | 
| South Portal |    
  Southbound and Northbound Drill and Blast excavation    
  Building works foundation and substructure | 
| Admin Building |    
  Building works foundation | 
Contract 3 (CV/2012/09)
2.4.3                
The Contract commenced in November 2013.  In this Reporting Period, construction
activities conducted are listed below:
   Cable
detection and trial trenches
   Decking
construction for Bridge E
   E&M work
for new valve control & Telemetry House
   Filling
works at Tong Hang East
   FRP Lining
on existing water main
   Storm
drain laying
   Noise
barrier construction
   Pier /
pier table construction
   Pile cap
works
   Portal
beam construction
   Pre-drilling
   Retaining
Wall construction
   Road works
at Fanling Highway
   Sewer
works
   Tree
felling works
   Utilities
duct laying
   Viaduct
segment erection
   Slope
works
   Waterworks
Contract 4 (Contract number to be assigned)
2.4.4                
The contract has not yet been awarded.
Contract 5 (CV/2013/03)
2.4.5                
The Contract awarded in April 2013 and
commenced on August 2013.  In this
Reporting Period, construction activities conducted are listed below:
   Construction
of rising main at existing Lin Ma Hang (LMH) Road
   Drainage
works of Depressed Road at BCP3
   Additional
works (Access Works) for Village House at RS4
   Drainage
works at existing LMH Road 
   Brick
laying at footpath of proposed LMH road
   Preparation
works for planting at proposed LMH road
   Installation
of Underground Utility (UU) at proposed and existing LMH road
   Irrigation
at proposed LMH Road
   Water works at
existing LMH Road
   Bituminous
laying at L15 road  existing &
proposed LMH road
   Construction of
Pavilion at Chung Yuen Ha Village
Contract 6 (CV/2013/08)
2.4.6                
Contract 6 has awarded in June 2015 and
construction work was commenced on 23 October 2015. In this Reporting Period,
construction activities conducted are listed below:
   Site
Clearance
   Slope
Works
   Site
Accesses Construction
   Ground
Investigation (GI) Works
   Soil nail
   Bored
piling
Contract 7 (NE/2014/03)
2.4.7                
Construction works of Contract 7 did not
commence in the reporting period
Contract SS C505
2.4.8                
Contract SS C505 has awarded in July 2015 and
construction work was commenced on 1 September 2015.  In this Reporting Period, construction
activities conducted are listed below:
   Excavation & fill works
   Predrilling
   Percussive piling
   Pre-boring
   Bored piling
   Pile caps
   Site office / training centre
set-up
   Structural works
   Assembly of crawler crane
   Mock up for curtain wall
   Weighbridge works
   Construction of Prototype A
2.5.1                
In according to the EP, the required documents
have submitted to EPD which listed in below:
  
Project Layout Plans of Contracts 2, 3, 5, 6, 7 and
SS C505
  
Landscape Plan
  
Topsoil Management Plan
  
Environmental Monitoring and Audit Programme
  
Baseline Monitoring Report (TCS00690/13/600/R0030v3) for the Project
  
Waste Management Plan of the Contracts 2, 3, 5,
6 and SS C505
  
Contamination Assessment Plan (CAP) for Po
Kat Tsai, Loi Tung and the workshops in Fanling
  
Contamination Assessment Report (CAR) for Po
Kat Tsai, Loi Tung and the workshops in Fanling
  
Vegetation Survey Report
  
Woodland Compensation Plan
  
Habitat Creation Management Plan
  
Wetland Compensation Plan
2.5.2                
Summary of
the relevant permits, licenses, and/or notifications on environmental
protection for the Project of each contracts are presented in Table 2-1.
Table 2-1    Status of Environmental
Licenses and Permits of the Contracts
| Item | Description | License/Permit Status | ||||
| Ref. no. | Effective Date | Expiry Date | ||||
| Contract 2 | ||||||
| 1 | Air pollution Control (Construction Dust) Regulation | Ref No.: 368864 | 31 Dec 2013 | Till Contract ends | ||
| 2 | Chemical Waste Producer Registration | North Portal Waste
  Producers Number: No.5213-652-D2523-01 | 25 Mar 2014 | Till Contract ends | ||
| Mid-Vent Portal Waste
  Producers Number: No.5213-634-D2524-01 | 25 Mar 2014 | Till Contract ends | ||||
| South Portal Waste
  Producers Number: No.5213-634-D2526-01 | 9 Apr 2014 | Till Contract ends | ||||
| 3 | Water Pollution Control Ordinance - Discharge License | No.WT00018374-2014 | 3 Mar 2014 | 28 Feb 2019 | ||
| No.: W5/1I389 | 28 Mar 2014 | 31 Mar 2019 | ||||
| No.: W5/1I390 | 19 June 2014 | 31 Mar 2019 | ||||
| No.: W5/1I391 | 28 Mar 2014  | 17 Dec 2015 | ||||
| No. WT00023063-2015 (Variation of W5/1I391) | 18 Dec 2015 | 31-Mar -2019 | ||||
| No.: W5/1I392 | 28 Mar 2014 | 31 Mar 2019 | ||||
| 4 | Waste Disposal Regulation - Billing Account for
  Disposal of Construction Waste | Account No. 7019105 | 8 Jan 2014 | Till Contract ends | ||
| 5 | Construction Noise Permit | GW-RN0479-15 | 31 Jul 2015 | 29 Jan 2016  | ||
| GW-RN0678-15 | 1 Nov 2015 | 31 Jan 2016 | ||||
| GW-RN0718-15 | 25 Nov 2015 | 24 Jan 2016 | ||||
| GW-RN0738-15 | 18 Nov 2015 | 8 May 2016 | ||||
| GW-RN0760-15 | 26 Nov 2015 | 27 Feb 2016 | ||||
| GW-RN0761-15 | 28 Nov 2015 | 27 Feb 2016 | ||||
| GW-RN0795-15  | 7 Dec 2015 | 6 Jun 2016 | ||||
| GW-RN0838-15 | 24-Dec-2015 | 23-Feb-2016 | ||||
| GW-RN0875-15 | 24-Dec-2015 | 23-Feb-2016 | ||||
| GW-RN0893-15 | 01-Jan-2016 | 27-Jun-2016 | ||||
| GW-RN0057-16 | 28-Feb-2016 | 27-May-2016 | ||||
| GW-RN0059-16 | 24-Feb-2016 | 23-Apr-2016 | ||||
| GW-RN0067-16 | 28-Feb-2016 | 27-May-2016 | ||||
| GW-RN0068-16 | 23-Feb-2016 | 22-Apr-2016 | ||||
| GW-RN0071-16 | 02-Feb-16 | 31-Jul-2016 | ||||
| Contract 3 | ||||||
| 1 | Air pollution Control (Construction Dust) Regulation | Ref. No: 362101 | 17 Jul 2013 | Till Contract ends | ||
| 2 | Chemical Waste Producer Registration | Waste Producers Number:
  No.:5113-634-C3817-01 | 7 Oct 2013 | Till Contract ends | ||
| 3 | Water Pollution Control Ordinance - Discharge License | No.:WT00016832 ¡V 2013 | 28 Aug 13 | 31 Aug
  2018 | ||
| 4 | Waste Disposal Regulation - Billing Account for
  Disposal of Construction Waste | Account No. 7017914 | 2 Aug 13 | Till Contract ends | ||
| 5 | Construction Noise Permit | GW-RN0461-15 | 5 Aug 2015 | 8 Jan 2016 | ||
| GW-RN0495-15 | 12 Aug 2015 | 11 Feb 2016 | ||||
| GW-RN0497-15 | 14 Aug 2015 | 13 Feb 2016 | ||||
| GW-RN0525-15 | 29 Aug 2015 | 13 Feb 2016 | ||||
| GW-RN0542-15 | 1 Sep 2015 | 25 Feb 2016 | ||||
| GW-RN0608-15 | 28 Sep 2015 | 29 Feb 2016 | ||||
| GW-RN0633-15 | 15 Oct 2015 | 29 Feb 2016 | ||||
| GW-RN0655-15 | 1 Dec 2015 | 29 Feb 2016 | ||||
| GW-RN0677-15 | 26 Oct 2015 | 29 Feb 2016 | ||||
| GW-RN0699-15 | 10 Nov 2015 | 27 Feb 2016 | ||||
| GW-RN0695-15 | 29 Nov 2015 | 28 Feb 2016 | ||||
| GW-RN0712-15 | 16 Nov 2015 | 29 Feb 2016 | ||||
| GW-RN0736-15 | 24 Nov 2015 | 29 Feb 2016 | ||||
| GW-RN0765-15 | 1 Dec 2015 | 27 Feb 2016 | ||||
| GW-RN0812-15 | 20 Dec 2015 | 29 Feb 2016 | ||||
| GW-RN0837-15 | 23 Dec 2015 | 29 Feb 2016 | ||||
| GW-RN0892-15 | 9 Jan 2016 | 8 July 2016 | ||||
| GW-RN0894-15 | 5 Jan 2016 | 27 Feb 2016 | ||||
|  |  | GW-RN0001-16 | 8 Jan 2016 | 27 Feb 2016 | ||
| GW-RN0049-16 | 26 Jan 2016 | 29 Feb 2016 | ||||
| GW-RN0056-16 | 2 Feb 2016 | 18 Mar 2016 | ||||
| GW-RN0060-16 | 1 Feb 2016 | 30 Jun 2016 | ||||
| GW-RN0064-16 | 16 Feb 2016 | 13 Aug 2016 | ||||
| Contract 5 | ||||||
| 1 | Air pollution Control (Construction Dust) Regulation | Ref. No: 359338 | 13 May 2013 | Till the end of Contract | ||
| 2 | Chemical Waste Producer Registration | Waste Producers Number No.:
  5213-642-S3735-01 | 8 Jun 2013 | Till the end of Contract | ||
| 3 | Water Pollution Control Ordinance - Discharge License | No.: W5/1G44/1 | 8 Jun 13 | 30 Jun 2018 | ||
| 4 | Waste Disposal Regulation - Billing Account for
  Disposal of Construction Waste | Account No. 7017351 | 29 Apr 13 | Till the end of Contract | ||
| Contract 6 | ||||||
| 1 | Air pollution Control (Construction Dust) Regulation | Ref. No: 390614 | 29 Jun 2015 | Till the end of Contract | ||
| 2 | Chemical Waste Producer Registration | Waste Producers Number No.: 5213-652-C3969-01 | 31 Aug 2015 | Till the end of Contract | ||
| 3 | Waste Disposal Regulation - Billing Account for
  Disposal of Construction Waste | Account No. 7022707 | 9 Jul 2015 | Till the end of Contract | ||
| 4 | Water Pollution Control Ordinance - Discharge License | Application
  is processing by EPD | ||||
| 5 | Construction Noise Permit | GW-RN0681-15 | 26 Oct 2015 | 25 Apr 2016 | ||
| 6 | Construction Noise Permit | GW-RN0683-15 | 26 Oct 2015 | 25 Apr 2016 | ||
| Contract SS C505 | ||||||
| 1 | Air pollution Control (Construction Dust) Regulation | Ref. No: 390974 | 13 Jul 2015 | Till the end of Contract | ||
| 2 | Chemical Waste Producer Registration | Waste
  Producer No.: 5213-642-L1048-07 | 16 Sep 2015 | Till the end of Contract | ||
| 3 | Water Pollution Control Ordinance - Discharge License | No.:
  WT00022774-2015 | 17 Nov 2015 | 30 Nov 2020 | ||
| 4 | Waste Disposal Regulation - Billing Account for
  Disposal of Construction Waste | Account No. 7022831 | 23 Jul 2015 | Till the end of Contract | ||
| 5 | Construction Noise Permit | PP-RN0027-15 | 5 Oct 2015 | 2 Apr 2016 | ||
| PP-RN0032-15 | 23 Nov 2015 | 22 Jan 2016 | ||||
| GW-RN0865-15 | 23 Dec 2015 | 22 Jan 2016 | ||||
| PP-RN0002-16 | 23 Jan 2016 | 22 Mar 2016 | ||||
| GW-RN0023-16 | 23 Jan 2016 | 22 Mar 2016 | ||||
| Contract
  7 | ||||||
| 1 | Air pollution Control (Construction Dust) Regulation | Application
  is processing by EPD | ||||
| 2 | Chemical Waste Producer Registration | Application
  is processing by EPD | ||||
| 3 | Water Pollution Control Ordinance - Discharge License | Application
  is processing by EPD | ||||
| 4 | Waste Disposal Regulation - Billing Account for
  Disposal of Construction Waste | Application
  is processing by EPD | ||||
3.1.1                
The Environmental Monitoring and Audit
requirements are set out in the Approved EM&A manual. Environmental issues
such as air quality, construction noise and water quality were identified as
the key issues during the construction phase of the Project.
3.1.2                
A summary of construction phase EM&A
requirements are presented in the
sub-sections below.
3.2.1                
The EM&A program of construction phase
monitoring shall cover the following environmental issues:
•                    
Air quality;
•                    
Construction noise; and
•                    
Water quality
3.2.2                
A summary of the monitoring parameters is
presented in Table 3-1.
Table 3-1         Summary
of EM&A Requirements
| Environmental Issue | Parameters | 
| Air Quality |   1-hour
  TSP by Real-Time Portable Dust Meter; and   24-hour
  TSP by High Volume Air Sampler. | 
| Noise |   Leq(30min) in
  normal working days (Monday to Saturday) 07:00-19:00 except public holiday;
  and   3 sets
  of consecutive Leq(5min) on restricted
  hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday   Supplementary
  information for data auditing, statistical results such as L10 and
  L90 shall also be obtained for reference. | 
| Water Quality | In-situ Measurements   Dissolved
  Oxygen Concentration (mg/L);   Dissolved
  Oxygen Saturation (% );   Turbidity
  (NTU);   pH unit;   Water
  depth (m); and   Temperature
  (¢J). | 
| Laboratory Analysis
     Suspended
  Solids (mg/L) | 
3.3.1                
The designated monitoring locations as
recommended in the EM&A Manual
are shown in Appendix D.  As the access to some of the designated
monitoring locations was questionable due to safety reason or denied by the
landlords, alternative locations therefore have had proposed. The proposed
alternative monitoring locations has updated in the revised EM&A Programme
which verified by IEC and certified by ET Leader prior submitted to EPD on 10
July 2013.  Table 3-2, Table
3-3 and Table 3-4 are respectively listed the air quality, construction
noise and water quality monitoring locations for the Project and a map showing
these monitoring stations is presented in Appendix E.
Table 3-2        Impact
Monitoring Stations - Air Quality
| Station ID | Description | Works Area | Related to the Work Contract | 
| AM1a* | Garden Farm,
  Tsung Yuen Ha Village | BCP | SS C505  Contract 5 Contract 7 | 
| AM2 | Village House
  near Lin Ma Hang Road | LMH to Frontier
  Closed Area | Contract 5  Contract 6 | 
| AM3 | Ta Kwu Ling
  Fire Service Station of Ta Kwu Ling Village. | LMH to Frontier
  Closed Area | Contract 5 Contract 6 | 
| AM4b^ | House no. 10B1 Nga Yiu Ha Village | LMH to Frontier
  Closed Area | Contract 6 | 
| AM5a^ | Ping Yeung
  Village House | Ping Yeung to
  Wo Keng Shan | Contract 6 | 
| AM6 | Wo Keng Shan Village House | Ping Yeung to
  Wo Keng Shan | Contract 6 | 
| AM7b@ | Loi Tung Village House | Sha Tau Kok
  Road | Contract 2 Contract 6 | 
| AM8 | Po Kat Tsai
  Village No. 4 | Po Kat Tsai | Contract 2 | 
| AM9b# | Nam Wa Po Village House No. 80 | Fanling | Contract 3 | 
# Proposal for the change of air quality monitoring location from AM9a
to AM9b was submitted to EPD on 4 Nov 2013 after verified by the IEC and it was
approved by EPD (EPD¡¦s ref.: (15) in EP 2/N7/A/52 Pt.10 dated 8 Nov 2013).
* Proposal for the change of air quality monitoring location from AM1to
AM1a was submitted to EPD on 24 March 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (6) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
@ Proposal for the change of air quality monitoring location from AM7a to
AM7b was submitted to EPD on 4 June 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (7) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
^ proposal for change of monitoring location
are subject to approve by EPD.
Table 3-3        Impact
Monitoring Stations - Construction Noise
| Station ID | Description | Works Area | Related to the Work Contract | 
| NM1 | Tsung Yuen Ha Village House No. 63 | BCP | SS C505  Contract 5 Contract 7 | 
| NM2 | Village House near Lin Ma Hang
  Road | Lin Ma Hang to Frontier Closed
  Area | Contract 5,  Contract 6 | 
| NM3 | Ping Yeung Village House (facade
  facing northeast) | Ping Yeung to Wo Keng Shan | Contract 6 | 
| NM4 | Wo Keng
  Shan Village House | Ping Yeung to Wo Keng Shan | Contract 6 | 
| NM5 | Village House, Loi Tung | Sha Tau Kok Road | Contract 2, Contract 6 | 
| NM6 | Tai Tong Wu Village House 2 | Sha Tau Kok Road | Contract 2, Contract 6 | 
| NM7 | Po Kat Tsai Village | Po Kat Tsai | Contract 2 | 
| NM8 | Village House, Tong Hang | Fanling | Contract 2 Contract 3 | 
| NM9 | Village House, Kiu Tau Village | Fanling | Contract 3 | 
| NM10 | Nam Wa
  Po Village House No. 80 | Fanling | Contract 3 | 
Table 3-4        Impact
Monitoring Stations - Water Quality
| Station ID | Description | Coordinates of Designated / Alternative Location | Nature of the location | Related to the Work Contract | |
| WM1 | Downstream of Kong Yiu Channel | 833 679 | 845 421 | Alternative location located at upstream 51m of the designated location | SS C505  Contract 5 Contract 6  | 
| WM1- Control | Upstream of Kong Yiu Channel | 834 185 | 845 917 | NA | SS C505  Contract 5 Contract 6 | 
| WM2A | Downstream of River Ganges | 834 204 | 844 471 | Alternative location located at downstream 81m of the designated
  location | Contract 6 | 
| WM2A- Control | Upstream of River Ganges | 835 270 | 844 243 | Alternative location located at upstream 78m of the designated location | Contract 6 | 
| WM2B | Downstream of River Ganges | 835 433 | 843 397 | NA | Contract 6 | 
| WM2B- Control | Upstream of River Ganges | 835 835 | 843 351 | Alternative location located at downstream 31m of the designated
  location | Contract 6 | 
| WM3 | Downstream of River Indus | 836 324 | 842 407 | NA | Contract 2 Contract 6 | 
| WM3- Control | Upstream of River Indus | 836 763 | 842 400 | Alternative location located at downstream 26m of the designated
  location | Contract 2 Contract 6 | 
| WM4 | Downstream of Ma Wat Channel | 833 850 | 838 338 | Alternative location located at upstream 11m of the designated location | Contract 2 Contract 3 | 
| WM4¡V Control A | Kau Lung Hang
  Stream | 834 028 | 837 695 | Alternative location located at downstream 28m of the designated
  location | Contract 2 Contract 3 | 
| WM4¡V Control B | Upstream of Ma Wat Channel | 833760 | 837395 | Alternative location located at upstream 15m of the designated location | Contract 2 Contract 3 | 
The requirements of impact monitoring are stipulated in Sections 2.1.6, 3.1.5 and 4.1.6 of the approved EM&A Manual and presented as
follows.
Air Quality Monitoring
3.4.1                
Frequency of impact air quality monitoring is
as follows:
|   
  1-hour TSP | 3 times every six
  days during course of works | 
|   
  24-hour TSP | Once every 6 days
  during course of works. | 
Noise Monitoring
3.4.2                
One set of Leq(30min)
as 6 consecutive Leq(5min)
between 0700-1900 hours on normal weekdays and once every week during course of
works.  If construction work
necessary to carry out at other time periods, i.e. restricted time period
(19:00 to 07:00 the next morning and whole day on public holidays) (hereinafter
referred as ¡§the restricted hours¡¨), 3 consecutive Leq(5min)
measurement will depended CNP requirements to undertake.  Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for
reference.
Water Quality Monitoring
3.4.3                
The water quality monitoring frequency shall
be 3 days per week during course of works. 
The interval between two sets of monitoring shall not be less than 36
hours.
Air Quality Monitoring
3.5.1                
The 24-hour and 1-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B.  If the ET proposes to use a direct
reading dust meter to measure 1-hour TSP levels, it shall submit sufficient
information to the IEC to approve.
3.5.2                
The filter paper of
24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.
3.5.3                
All equipment to be used for air quality
monitoring is listed in Table 3-5. 
Table 3-5         Air
Quality Monitoring Equipment
| Equipment | Model | 
| 24-Hr TSP | |
| High
  Volume Air Sampler | TISCH High Volume
  Air Sampler, HVS Model TE-5170* | 
| Calibration
  Kit | TISCH Model TE-5025A* | 
| 1-Hour TSP | |
| Portable Dust Meter | Sibata LD-3B
  Laser Dust monitor Particle Mass Profiler & Counter* | 
* Instrument was used in the Reporting
Period and the calibration certificate could be referred in Appendix F.
Wind Data Monitoring Equipment
3.5.4                
According to the approved EM&A Manual,
wind data monitoring equipment shall also be provided and set up for logging
wind speed and wind direction near the dust monitoring locations.  The equipment installation location
shall be proposed by the ET and agreed with the IEC.  For installation and operation of wind
data monitoring equipment, the following points shall be observed:
1)         
The wind sensors should be installed 10 m
above ground so that they are clear of obstructions or turbulence caused by
buildings.
2)         
The wind data should be captured by a data
logger. The data shall be downloaded for analysis at least once a month.
3)         
The wind data monitoring equipment should be
re-calibrated at least once every six months.
4)         
Wind direction should be divided into 16
sectors of 22.5 degrees each.
3.5.5                
ET has liaised with the landlords of the
successful granted HVS installation premises.  However, the owners rejected to provide
premises for wind data monitoring equipment installation.
3.5.6                
Under this situation, the ET proposed
alternative methods to obtain representative wind data.  Meteorological information as extracted
from ¡§the Hong Kong Observatory Ta Kwu Ling Station¡¨ is alternative method to
obtain representative wind data. 
For Ta Kwu Ling Station, it is located nearby the Project site.  Moreover, this station is located at 15m
above mean sea level while its anemometer is located at 13m above the existing
ground which in compliance with the general setting up requirement.  Furthermore, this station also can be to
provide the humidity, rainfall, and air pressure and temperature etc.
meteorological information.  In Hong
Kong of a lot development projects, weather information extracted from Hong
Kong Observatory is common alternative method if weather station installation
not allowed.
Noise Monitoring
3.5.7                
Sound level meter in compliance with the
International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring.  The sound level meter shall be checked
using an acoustic calibrator.  The
wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
3.5.8                
Noise monitoring equipment to be used for
monitoring is listed in Table 3-6.
Table 3-6         Construction
Noise Monitoring Equipment
| Equipment | Model | 
| Integrating Sound Level Meter | B&K Type 2238* or Rion
  NL-31 or Rion NL-52* | 
| Calibrator | B&K Type 4231* or Cesva
  CB-5* or Rion NC-74* | 
| Portable Wind Speed Indicator | Testo Anemometer | 
* Instrument was used in the Reporting
Period and the calibration certificate could be referred in Appendix F.
3.5.9                
Sound level meters listed above comply with
the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications, as recommended in TM issued
under the NCO.  The acoustic
calibrator and sound level meter to be used in the impact monitoring will be
calibrated yearly.
Water Quality Monitoring
3.5.10            
DO and water temperature should be measured
in-situ by a DO/temperature meter. The instrument should be portable and
weatherproof using a DC power source. It should have a membrane electrode with
automatic temperature compensation complete with a cable. The equipment should
be capable of measuring:
•                
a DO level in the range of 0-20 mg/l and
0-200% saturation; and
•                
a
temperature of between 0 and 45 degree Celsius.
3.5.11            
A portable pH meter capable of measuring a
range between 0.0 and 14.0 should be provided to measure pH under the specified
conditions accordingly to the APHA Standard Methods.
3.5.12            
The instrument should be portable and
weatherproof using a DC power source. It should have a photoelectric sensor
capable of measuring turbidity between 0-1000 NTU.
3.5.13            
A portable, battery-operated echo sounder or
tape measure will be used for the determination of water depth at each
designated monitoring station as appropriate.
3.5.14            
A water sampler e.g. Kahlsico
Water Sampler, which is a transparent PVC cylinder with capacity not less than
2 litres, will be used for water sampling if water depth over than 0.5m.   For sampling from very shallow
water depths e.g. <0.5 m, water sample collection will be directly from
water surface below 100mm use sampling plastic bottle to avoid inclusion of bottom
sediment or humus.  Moreover,
Teflon/stainless steel bailer or self-made sampling buckets maybe used for
water sampling.  The equipment used
for sampling will be depended the sampling location and depth situations.
3.5.15            
Water samples for laboratory measurement of
SS will be collected in high density polythene bottles, packed in ice (cooled
to 4 ºC without being frozen), and delivered to the laboratory in the same day
as the samples were collected.
3.5.16            
Analysis of suspended solids should be
carried out in a HOKLAS or other accredited laboratory. Water samples of about
1L should be collected at the monitoring stations for carrying out the
laboratory suspended solids determination. 
The SS determination work should start within 24 hours after collection
of the water samples. The SS analyses should follow the APHA Standard Methods 2540D with Limit of Reporting of 2 mg/L.
3.5.17            
Water quality monitoring equipment used in
the impact monitoring is listed in Table 3-7.  Suspended solids (SS)
analysis is carried out by a local HOKLAS-accredited laboratory, namely ALS Technichem
(HK) Pty Ltd. 
Table 3-7         Water
Quality Monitoring Equipment
| Equipment | Model | 
| Water
  Depth Detector | Eagle
  Sonar or tape measures | 
| Water Sampler | A 2-litre transparent PVC cylinder with latex cups at
  both ends or teflon/stainless steel bailer or
  self-made sampling bucket  | 
| Thermometer & DO meter | YSI Professional Plus /YSI PRO20 Handheld Dissolved
  Oxygen Instrument* / YSI 550A Multifunctional Meter/ YSI Professional DSS* | 
| pH meter | YSI Professional Plus / AZ8685 pH pen-style meter*/ YSI
  6820/ 650MDS/ YSI Professional DSS* | 
| Turbidimeter | Hach 2100Q*/ YSI 6820/
  650MDS/ YSI Professional DSS* | 
| Sample Container | High density polythene bottles (provided by laboratory) | 
| Storage
  Container | ¡¥Willow¡¦
  33-liter plastic cool box with Ice pad | 
* Instrument was used in the Reporting
Period and the calibration certificate could be referred in Appendix F.
1-hour TSP
Monitoring
3.6.1                
The 1-hour TSP monitor was a brand named ¡§Sibata LD-3B Laser Dust monitor Particle Mass Profiler
& Counter¡¨ which is a portable, battery-operated laser photometer.  The 1-hour TSP meter provides a real
time 1-hour TSP measurement based on 90o light scattering.  The 1-hour TSP monitor consists of the
following:
(a.)        
A pump to draw sample aerosol through the
optic chamber where TSP is measured;
(b.)       
A sheath air system to isolate the aerosol in
the chamber to keep the optics clean for maximum reliability; and
(c.)        
A built-in data logger compatible with
Windows based program to facilitate data collection, analysis and reporting.
3.6.2                
The 1-hour TSP meter is used within the valid
period as follow manufacturer¡¦s Operation and Service Manual.
3.6.3                
The equipment used for 24-hour TSP
measurement is Tisch Environmental, Inc. Model TE-5170 TSP
high volume air sampling system, which complied with EPA Code of Federal Regulation, Appendix B to Part 50. The High
Volume Air Sampler (HVS) consists of the following:
(a.)        
An anodized aluminum shelter; 
(b.)       
A 8¡¨x10¡¨ stainless steel filter holder;
(c.)        
A blower motor assembly;     
(d.)       
A continuous flow/pressure recorder;
(e.)        
A motor speed-voltage control/elapsed time
indicator;
(f.)        
A 7-day mechanical timer, and 
(g.)        
A power supply of 220v/50 Hz
3.6.4                
The HVS is operated and calibrated on a
regular basis in accordance with the manufacturer¡¦s instruction using Tisch Calibration Kit Model TE-5025A.  Calibration would carry out in two month
interval.
3.6.5                
24-hour TSP is collected by the ET on filters
of HVS and quantified by a local HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd (ALS), upon receipt of the
samples.  The ET keep all the
sampled 24-hour TSP filters in normal air conditioned room conditions, i.e. 70%
RH (Relative Humidity) and 25oC, for six months prior to disposal.
3.6.6                
Noise measurements were taken in terms of the
A-weighted equivalent sound pressure level (Leq)
measured in decibels dB(A). Supplementary statistical
results (L10 and L90) were also obtained for reference.
3.6.7                
During the monitoring, all noise measurements
would be performed with the meter set to FAST response and on the A-weighted
equivalent continuous sound pressure level (Leq).  Leq(30min)
in six consecutive Leq(5min) measurements
will use as the monitoring parameter for the time period between 0700-1900
hours on weekdays; and also Leq(15min) in
three consecutive Leq(5min) measurements
would be used as monitoring parameter for other time periods (e.g. during
restricted hours), if necessary.
3.6.8                
Prior of noise measurement, the accuracy of
the sound level meter is checked using an acoustic calibrator generating a
known sound pressure level at a known frequency.  The checking is performed before and
after the noise measurement.
Water
Quality
3.6.9                
Water quality monitoring is conducted at the
designated locations. The sampling procedures with the in-situ monitoring are
presented as below:
Sampling Procedure
3.6.10            
A Digital Global
Positioning System (GPS) is used to identify the designated monitoring stations
prior to water sampling.  A
portable, battery-operated echo sounder or tape measurement is used for the
determination of water depth at each station.  At each station, water sample would be
collected from 0.1m below water surface or the water surface to prevent the
river bed sediment for stirring.
3.6.11            
The sample container will be rinsed with a
portion of the water sample.  The
water sample then will be transferred to the high-density polythene bottles as provided by the laboratory,
labeled with a unique sample number and sealed with a screw cap.
3.6.12            
Before sampling, general information such as
the date and time of sampling, weather condition as well as the personnel
responsible for the monitoring would be recorded on the field data sheet.
3.6.13            
A ¡¥Willow¡¦ 33-liter plastic cool box packed
with ice will be used to preserve the water samples prior to arrival at the
laboratory for chemical determination. 
The water temperature of the cool box is maintained at a temperature as
close to 40C as possible without being frozen.  Samples collected are delivered to the
laboratory upon collection.
In-situ Measurement
3.6.14            
YSI PRO20 Handheld Dissolved Oxygen
Instrument or YSI Professional DSS is
used for water in-situ measures, which automates the measurements and
data logging of temperature, dissolved oxygen and dissolved oxygen
saturation.  
3.6.15            
A portable AZ Model 8685 pH pen-style meter or YSI Professional
DSS is used for in-situ pH measurement.  The pH meter is capable of measuring pH
in the range of 0 ¡V 14 and readable to 0.1. 
3.6.16            
A portable Hach
2100Q Turbidimeter or YSI Professional DSS is used
for in-situ turbidity measurement. The turbidity meter is capable of measuring
turbidity in the range of 0 ¡V 1000 NTU.  
3.6.17            
All in-situ measurement equipment are calibrated by HOKLAS accredited laboratory of three
month interval.
Laboratory Analysis
3.6.18            
All water samples analyzed Suspended Solids
(SS) will be carried out by a local HOKLAS-accredited testing laboratory (ALS Technichem (HK) Pty Ltd HOKLAS registration no. 66).  SS determination using APHA
Standard Methods 2540D as specified in the EM&A Manual will start within
48 hours of water sample receipt. 
3.7.1                
Calibration of the HVS is performed upon installation
and thereafter at bimonthly intervals in accordance with the manufacturer¡¦s
instruction using the certified standard calibrator (TISCH Model TE-5025A).  Moreover, the Calibration
Kit would be calibrated annually. The
calibration data are properly documented and the records are maintained by ET
for future reference.
3.7.2                
The 1-hour TSP
meter was calibrated by the supplier prior to purchase.  Zero response of the equipment would be
checked before and after each monitoring event.  Annually calibration with the High
Volume Sampler (HVS) in same condition would be undertaken by the Laboratory.
3.7.3                
The sound level
meter and calibrator are calibrated and certified by a laboratory accredited
under HOKLAS or any other international accreditation scheme at yearly basis.
3.7.4                
All water quality monitoring equipment would
be calibrated by HOKLAS accredited laboratory of three month intervals.
3.7.5                
The calibration
certificates of all monitoring equipment used for the impact monitoring program
in the Reporting Period and the HOKLAS accredited certificate of laboratory are attached in Appendix F.   
3.8.1                
The baseline results form the basis for
determining the environmental acceptance criteria for the impact
monitoring.  According to the approved
Environmental Monitoring and Audit Manual, the air quality, construction noise
and water quality criteria were set up, namely Action and Limit levels are
listed in Tables 3-8, 3-9 and 3-10.
Table 3-8        Action and Limit Levels for Air Quality
Monitoring
| Monitoring
   Station | Action Level (mg /m3) | Limit Level (mg/m3) | ||
| 1-hour TSP | 24-hour TSP | 1-hour TSP | 24-hour TSP | |
| AM1a | 265 | 143 | 500 | 260 | 
| AM2 | 268 | 149 | ||
| AM3 | 269 | 145 | ||
| AM4b | 267 | 148 | ||
| AM5a | 268 | 143 | ||
| AM6 | 269 | 148 | ||
| AM7b | 275 | 156 | ||
| AM8 | 269 | 144 | ||
| AM9b | 271 | 151 | ||
Table 3-9         Action
and Limit Levels for Construction Noise
| Monitoring Location | Action Level | Limit Level in
  dB(A) | 
| Time Period:
  0700-1900 hours on normal weekdays | ||
| NM1, NM2, NM3, NM4,
  NM5, NM6, NM7, NM8, NM9, NM10 | When one
  or more documented complaints are received | 75 dB(A)Note 1
  & Note 2 | 
Note 1:  Acceptable Noise Levels
for school should be reduced to 70 dB(A)
and65 dB(A) during examination period 
Note 2:  If works are to be
carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the NCA have to be followed.
Table 3-10       Action and
Limit Levels for Water Quality 
| Parameter | Performance
   criteria | Monitoring Location | |||||
| WM1 | WM2A | WM2B | WM3 | WM4 | |||
| DO (mg/L) | Action Level | (*)4.23 | (**)4.00 | (*)4.74  | (**)4.00 | (*)4.14 | |
| Limit Level | (#)4.19 | (**)4.00 | (#)4.60 | (**)4.00 | (#)4.08 | ||
| Turbidity (NTU) | Action Level | 51.3 | 24.9  | 11.4  | 13.4  | 35.2  | |
| AND  120% of upstream control station of
  the same day | |||||||
| Limit Level | 67.6 | 33.8  | 12.3  | 14.0  | 38.4  | ||
| AND  130% of upstream control station of the same day | |||||||
| SS (mg/L) | Action Level | 54.5 | 14.6 | 11.8 | 12.6 | 39.4 | |
| AND  120% of upstream control station of the
  same day | |||||||
| Limit Level | 64.9 | 17.3 | 12.4 | 12.9 | 45.5 | ||
| AND  130% of upstream control station of the same day | |||||||
| Remarks: (*)      The
  Proposed Action Level of Dissolved
  Oxygen is adopted to be used 5%-ile of
  baseline data (**)  The
  Proposed Action & Limit Level of Dissolved
  Oxygen is used 4mg/L (#)     The
  Proposed Limit Level of Dissolved
  Oxygen is adopted to be used 1%-ile of
  baseline data | |||||||
3.8.2                
Should non-compliance of the environmental
quality criteria occurs, remedial actions will be triggered according to the
Event and Action Plan which presented in Appendix G.
3.9.1                
All monitoring data will be handled by the ET¡¦s in-house data recording and management system.  The monitoring data
recorded in the equipment will be downloaded directly from the equipment at the
end of each monitoring day.  The
downloaded monitoring data will input into a computerized database maintained
by the ET.  The laboratory results
will be input directly into the computerized database and checked by personnel
other than those who input the data.
3.9.2                
For monitoring parameters that require
laboratory analysis, the local laboratory shall follow the QA/QC requirements
as set out under the HOKLAS scheme for the relevant laboratory tests.
4.1.1                
In the Reporting Period, construction works under the
project have been commenced in Contracts 2,
3, 5, 6 and Contract SS C505 and air quality monitoring was performed at all designated
locations.
4.1.2                
The air quality monitoring schedule is presented
in Appendix H and the monitoring
results are summarized in the following sub-sections.
4.2.1                
In the Reporting Period, a total of 135 events of 1-hour TSP and 48
events 24-hours TSP monitoring were carried out and the monitoring results are
summarized in Tables 4-1 to 4-9.   The detailed 24-hour TSP monitoring
data are presented in Appendix
I and the relevant graphical plots are shown in Appendix J.
Table 4-1         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1a
| Date | 24-hour
  TSP (mg/m3) | 1-hour
  TSP (mg/m3) | ||||
| Date | Start Time | 1st reading | 2nd reading | 3rd reading | ||
| 4-Jan-16 | 86 | 5-Jan-16 | 9:54 | 125 | 61 | 91 | 
| 9-Jan-16 | 44 | 11-Jan-16 | 10:00 | 101 | 95 | 76 | 
| 15-Jan-16 | 34 | 16-Jan-16 | 9:57 | 11 | 22 | 33 | 
| 21-Jan-16 | 29 | 22-Jan-16 | 9:43 | 77 | 93 | 80 | 
| 27-Jan-16 | 43 | 28-Jan-16 | 10:31 | 29 | 43 | 21 | 
| Average (Range) | 47  (29 ¡V 86) | Average (Range) | 91 (11 ¡V 125) | |||
Table 4-2         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
| Date | 24-hour
  TSP (mg/m3) | 1-hour
  TSP (mg/m3) | ||||
| Date | Start Time | 1st
  reading | 2nd
  reading | 3rd
  reading | ||
| 4-Jan-16 | 65
   | 5-Jan-16 | 9:37 | 93 | 62 | 80 | 
| 9-Jan-16 | 82
   | 11-Jan-16 | 10:03 | 92 | 94 | 92 | 
| 15-Jan-16 | 33
   | 16-Jan-16 | 9:59 | 54 | 47 | 45 | 
| 21-Jan-16 | 25
   | 22-Jan-16 | 9:49 | 71 | 92 | 71 | 
| 27-Jan-16 | 48 | 28-Jan-16 | 10:13 | 57 | 108 | 93 | 
| Average (Range) | 51  (25 ¡V 82) | Average (Range) | 77 (45 ¡V 108) | |||
Table 4-3         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
| Date | 24-hour
   TSP (mg/m3) | 1-hour
   TSP (mg/m3) | ||||
| Date | Start Time | 1st
   reading | 2nd
   reading | 3rd
   reading | ||
| 4-Jan-16 | 139 | 5-Jan-16 | 9:30 | 100 | 69 | 86 | 
| 9-Jan-16 | 96 | 11-Jan-16 | 10:05 | 103 | 96 | 68 | 
| 15-Jan-16 | 37 | 16-Jan-16 | 10:05 | 58 | 52 | 49 | 
| 21-Jan-16 | 46 | 22-Jan-16 | 9:57 | 71 | 89 | 79 | 
| 27-Jan-16 | 112 | 28-Jan-16 | 9:52 | 32 | 60 | 51 | 
| Average (Range) | 86 (37 ¡V 139) | Average (Range) | 71 (32 ¡V 103) | |||
Table 4-4         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM4b
| Date | 24-hour
   TSP (mg/m3) | 1-hour
   TSP (mg/m3) | ||||
| Date | Start Time | 1st
   reading | 2nd
   reading | 3rd
   reading | ||
| 2-Jan-16 | 105 | 4-Jan-16 | 14:11 | 77 | 54 | 47 | 
| 7-Jan-16 | 49 | 8-Jan-16 | 10:08 | 136 | 124 | 35 | 
| 13-Jan-16 | 46 | 14-Jan-16 | 10:03 | 177 | 184 | 169 | 
| 19-Jan-16 | 70 | 20-Jan-16 | 10:57 | 84 | 102 | 86 | 
| 25-Jan-16 | 73 | 26-Jan-16 | 9:49 | 66 | 84 | 72 | 
| 30-Jan-16 | 22 |  | ||||
| Average (Range) | 61 (22 ¡V
  105) | Average (Range) | 100 (35 ¡V 184) | |||
Table 4-5         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM5a
| Date | 24-hour
   TSP (mg/m3) | 1-hour
   TSP (mg/m3) | ||||
| Date | Start Time | 1st
   reading | 2nd
   reading | 3rd
   reading | ||
| 2-Jan-16 | 93 | 4-Jan-16 | 14;17 | 83 | 61 | 53 | 
| 7-Jan-16 | 42 | 8-Jan-16 | 10:01 | 97 | 91 | 15 | 
| 13-Jan-16 | 46 | 14-Jan-16 | 10:02 | 154 | 167 | 179 | 
| 19-Jan-16 | 64 | 20-Jan-16 | 10:49 | 77 | 99 | 79 | 
| 25-Jan-16 | 59 | 26-Jan-16 | 9:47 | 69 | 91 | 70 | 
| 30-Jan-16 | 31 |  | ||||
| Average (Range) | 56 (31 ¡V
  93) | Average (Range) | 92 (15 ¡V 179) | |||
Table 4-6         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM6
| Date | 24-hour
   TSP (mg/m3) | 1-hour
   TSP (mg/m3) | ||||
| Date | Start Time | 1st
   reading | 2nd
   reading | 3rd
   reading | ||
| 2-Jan-16 | 124 | 4-Jan-16 | 14:16 | 72 | 50 | 42 | 
| 7-Jan-16 | 134 | 8-Jan-16 | 9:57 | 127 | 121 | 134 | 
| 13-Jan-16 | 132 | 14-Jan-16 | 9:50 | 138 | 140 | 168 | 
| 19-Jan-16 | 145 | 20-Jan-16 | 10:35 | 80 | 97 | 85 | 
| 25-Jan-16 | 61 | 26-Jan-16 | 9:37 | 77 | 95 | 79 | 
| 30-Jan-16 | 48 |  | ||||
| Average (Range) | 107 (48 ¡V
  145) | Average (Range) | 100 (42 ¡V 168) | |||
Table 4-7         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM7b
| Date | 24-hour
  TSP (mg/m3) | 1-hour
  TSP (mg/m3) | ||||
| Date | Start Time | 1st
  reading | 2nd
  reading | 3rd
  reading | ||
| 4-Jan-16 | 34 | 4-Jan-16 | 9:18 | 50 | 47 | 45 | 
| 9-Jan-16 | 70 | 8-Jan-16 | 9:07 | 108 | 110 | 115 | 
| 15-Jan-16 | 41 | 14-Jan-16 | 9:15 | 79 | 110 | 117 | 
| 21-Jan-16 | 39 | 20-Jan-16 | 9:21 | 198 | 167 | 155 | 
| 27-Jan-16 | 32 | 26-Jan-16 | 9:17 | 68 | 59 | 63 | 
| Average (Range) | 43  (32 ¡V 70) | Average (Range) | 99 (45 ¡V 198) | |||
Table 4-8         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM8
| Date | 24-hour
  TSP (mg/m3) | 1-hour
  TSP (mg/m3) | ||||
| Date | Start Time | 1st
  reading | 2nd
  reading | 3rd
  reading | ||
| 4-Jan-16 | 22 | 4-Jan-16 | 13;9 | 47 | 43 | 39 | 
| 9-Jan-16 | 49 | 8-Jan-16 | 13;3 | 107 | 110 | 116 | 
| 15-Jan-16 | 23 | 14-Jan-16 | 13:09 | 78 | 111 | 115 | 
| 21-Jan-16 | 38 | 20-Jan-16 | 13:07 | 196 | 166 | 155 | 
| 27-Jan-16 | 27 | 26-Jan-16 | 13:02 | 53 | 41 | 64 | 
| Average (Range) | 32  (22 ¡V 49) | Average (Range) | 96 (39 ¡V 196) | |||
Table 4-9         Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
| Date | 24-hour
  TSP (mg/m3) | 1-hour
  TSP (mg/m3) | ||||
| Date | Start Time | 1st
  reading | 2nd
  reading | 3rd
  reading | ||
| 4-Jan-16 | 20 | 5-Jan-16 | 11:00 | 106 | 64 | 91 | 
| 9-Jan-16 | 37 | 11-Jan-16 | 9:05 | 41 | 14 | 37 | 
| 15-Jan-16 | 45 | 16-Jan-16 | 9:20 | 189 | 188 | 162 | 
| 21-Jan-16 | 41 | 22-Jan-16 | 9:09 | 55 | 52 | 57 | 
| 27-Jan-16 | 36 | 28-Jan-16 | 9:15 | 34 | 26 | 36 | 
| Average (Range) | 36 (20 ¡V 45) | Average (Range) | 77 (14 ¡V 189) | |||
4.2.2                
As shown in Tables 4-1 to 4-9, all
the 1-hour TSP and 24-hour TSP monitoring results were below the Action/Limit
Levels.  No Notification of
Exceedance (NOE) was issued in this Reporting Period.
4.2.3                
The meteorological data during the impact
monitoring days are summarized in Appendix
K.
5.1.1                
In the Reporting Period, construction works under the
project have been commenced in Contracts 2,
3, 5, 6 and Contract SS C505 and noise monitoring was performed at all
designated locations.
5.1.2                
The noise monitoring schedule is presented in
Appendix H and the monitoring
results are summarized in the following sub-sections.
5.2.1                
In the Reporting Period, a total of 50 event noise measurements were
carried out at the designated locations. 
The sound level meter was set in 1m from the exterior of the building
façade including noise monitoring locations NM1, NM2, NM3, NM4, NM5, NM6, NM7,
NM8 and NM9.  Therefore, no façade
correction (+3 dB(A)) is added according to acoustical
principles and EPD guidelines.  However,
free-field status was performed at NM10 and façade correction (+3 dB(A)) has added according to the requirement in this
month.  The noise monitoring results
at the designated locations are summarized in Tables 5-1 and 5-2.  The detailed noise monitoring
data are presented in Appendix
I and the relevant graphical plots are shown in Appendix J. 
Table 5-1         Summary of Construction Noise Monitoring Results
| Construction Noise Level (Leq30min), dB(A)  | |||||
| Date | NM1 | NM2 | NM8 | NM9 | NM10(*) | 
| 5-Jan-16 | 60 | 66 | 63 | 62 | 67 | 
| 11-Jan-16 | 53 | 68 | 59 | 66 | 62 | 
| 16-Jan-16 | 61 | 65 | 59 | 59 | 68 | 
| 22-Jan-16 | 71 | 71 | 59 | 59 | 65 | 
| 28-Jan-16 | 58 | 62 | 63 | 62 | 63 | 
| Limit Level | 75 dB(A) | ||||
Remarks
(*)   façade correction (+3 dB(A)
is added according to acoustical principles and EPD guidelines
i      bold and
underlined indicated Limit Level exceedance.
Table 5-2         Summary of Construction Noise Monitoring Results
| Construction Noise Level (Leq30min), dB(A)  | |||||
| Date | NM3 | NM4 | NM5 | NM6 | NM7 | 
| 4-Jan-16 | 70 | 75 | 55 | 56 | 58 | 
| 8-Jan-16 | 62 | 67 | 55 | 54 | 63 | 
| 14-Jan-16 | 67 | 64 | 56 | 63 | 63 | 
| 20-Jan-16 | 66 | 67 | 59 | 55 | 67 | 
| 26-Jan-16 | 58 | 66 | 62 | 62 | 67 | 
| Limit Level | 75 dB(A) | ||||
5.2.1                
As shown in Tables
5-1 and 5-2, the noise level measured at all designated monitoring
locations were below 75dB(A). 
Furthermore, there was no noise complaints (Action Level
exceedance) received by the RE, CEDD, Architect/AR/ and the Contractors in the
Reporting Period.  Therefore, no
Action or Limit Level exceedance was triggered and no corrective action was
required.
i.                                
6.1.1                
In the Reporting Period, construction works under the
project has been commenced in Contracts 2,
3, 5, 6 and Contract SS C505 and water quality monitoring was performed at all
designated locations.  The water
quality monitoring schedule is presented in Appendix H.  The
monitoring results are summarized in the following sub-sections.
6.2.1                
In the Reporting Period, a total of thirteen (13)
sampling days water quality was scheduled to carry out
for all designated locations with their control stations.  Since water quality exceedance were recorded
at WM2A and WM2B, one (1) and seven (7) extra days water quality monitoring were
conducted at WM2A and WM2B respectively in accordance with ¡§Event and Action Plan¡¨. 
6.2.2                
The key monitoring parameters including Dissolved Oxygen, Turbidity and Suspended
Solids are summarized in Tables 6-1 and 6-5.  Breaches of water quality monitoring
criteria are shown in Table 6-6.  Detailed monitoring database including
in-situ measurements and laboratory analysis data are shown in Appendix I and the relevant
graphical plot are shown in Appendix
J.
Table 6-1         Water
Quality Monitoring Results Associated of Contracts 2 and 3
| Date | Dissolved Oxygen (mg/L) | Turbidity (NTU) | Suspended Solids (mg/L) | ||||||
| WM4 | WM4-CA | WM4-CB | WM4 | WM4-CA | WM4-CB | WM4 | WM4-CA | WM4-CB | |
| 2-Jan-16 | 8.2 | 8.9 | 6.7 | 10.1 | 3.8 | 6.8 | 10.5 | 2.0 | 8.5 | 
| 5-Jan-16 | 7.4 | 8.5 | 7.6 | 23.8 | 11.7 | 46.4 | 26.5 | 19.0 | 76.0 | 
| 7-Jan-16 | 10.0 | 9.6 | 8.3 | 31.8 | 9.8 | 24.2 | 34.0 | 12.5 | 29.0 | 
| 9-Jan-16 | 8.0 | 7.7 | 6.7 | 17.1 | 6.4 | 23.6 | 17.0 | 4.0 | 27.0 | 
| 11-Jan-16 | 10.0 | 10.2 | 8.8 | 19.8 | 13.0 | 13.6 | 16.5 | 8.0 | 13.5 | 
| 13-Jan-16 | 10.6 | 11.8 | 11.1 | 15.9 | 5.6 | 10.3 | 8.0 | 3.0 | 18.5 | 
| 15-Jan-16 | 10.0 | 10.5 | 9.1 | 40.6 | 22.1 | 30.0 | 33.5 | 13.0 | 25.0 | 
| 19-Jan-16 | 10.8 | 11.4 | 9.5 | 29.4 | 5.0 | 8.8 | 22.5 | 2.0 | 14.5 | 
| 21-Jan-16 | 9.5 | 9.4 | 7.3 | 32.9 | 16.6 | 19.4 | 34.5 | 12.0 | 23.5 | 
| 23-Jan-16 | 13.7 | 13.2 | 11.4 | 25.9 | 6.5 | 9.0 | 20.5 | 2.0 | 4.5 | 
| 25-Jan-16 | 11.6 | 12.2 | 10.2 | 8.0 | 4.1 | 11.2 | 4.0 | 2.0 | 8.5 | 
| 27-Jan-16 | 13.3 | 10.8 | 10.3 | 31.9 | 49.3 | 27.1 | 15.0 | 27.5 | 13.5 | 
| 29-Jan-16 | 10.4 | 10.7 | 10.1 | 28.4 | 21.7 | 24.5 | 19.5 | 18.0 | 15.5 | 
Remark: 
bold and underlined indicated Limit Level exceedance.
Table 6-2         Water
Quality Monitoring Results Associated of Contracts 5, 6 and SS C505
| Date | Dissolved Oxygen (mg/L) | Turbidity (NTU) | Suspended Solids (mg/L) | |||
| WM1 | WM1- Control | WM1 | WM1- Control | WM1 | WM1- Control | |
| 2-Jan-16 | 8.6 | 8.5 | 37.7 | 11.3 | 34.0 | 4.5 | 
| 5-Jan-16 | 6.3 | 8.6 | 22.5 | 5.4 | 21.0 | 4.0 | 
| 7-Jan-16 | 6.9 | 10.6 | 41.2 | 22.9 | 30.5 | 19.0 | 
| 9-Jan-16 | 9.1 | 7.8 | 30.7 | 7.6 | 28.5 | 5.0 | 
| 11-Jan-16 | 10.4 | 10.3 | 424.0 | 407.0 | 184.0 | 161.5 | 
| 13-Jan-16 | 10.5 | 9.3 | 49.0 | 12.4 | 51.0 | 5.5 | 
| 15-Jan-16 | 10.6 | 10.7 | 182.5 | 170.5 | 109.0 | 98.0 | 
| 19-Jan-16 | 11.9 | 11.6 | 43.0 | 13.8 | 49.0 | 8.0 | 
| 21-Jan-16 | 9.3 | 10.0 | 41.6 | 31.5 | 40.5 | 19.5 | 
| 23-Jan-16 | 14.7 | 15.8 | 48.6 | 34.2 | 51.5 | 14.5 | 
| 25-Jan-16 | 13.6 | 14.6 | 45.6 | 7.7 | 31.5 | 3.5 | 
| 27-Jan-16 | 14.7 | 25.7 | 155.5 | 135.0 | 86.0 | 89.5 | 
| 29-Jan-16 | 10.4 | 10.3 | 853.5 | 765.0 | 479.5 | 414.0 | 
Table 6-3         Water
Quality Monitoring Results Associated only Contract 6
| Date | Dissolved Oxygen (mg/L) | Turbidity (NTU) | Suspended Solids (mg/L) | |||||||||
| WM2A | WM2A- C | WM2B | WM2B- C | WM2A | WM2A- C | WM2B | WM2B- C | WM2A | WM2A- C | WM2B | WM2B- C | |
| 2-Jan-16 | 9.1 | 8.6 | 9.8 | 7.9 | 6.3 | 9.0 | 23.9 | 5.9 | 3.0 | 3.0 | 19.0 | 2.0 | 
| 4-Jan-16 | 8.5 | 7.7 | 8.7 | 7.3 | 7.2 | 34.0 | 8.8 | 8.6 | 6.0 | 20.0 | 5.5 | 11.0 | 
| 5-Jan-16# |  |  |  |  |  |  | 10.5 |  |  |  | 4.0 |  | 
| 6-Jan-16 | 9.7 | 7.9 | 8.2 | 8.3 | 13.6 | 19.7 | 199.0 | 6.4 | 7.0 | 7.5 | 134.0 | 2.0 | 
| 7-Jan-16# |  |  |  |  |  |  | 21.3 |  |  |  | 10.0 |  | 
| 8-Jan-16 | 9.0 | 9.4 | 8.3 | 7.3 | 11.0 | 11.9 | 12.2 | 6.0 | 5.5 | 4.5 | 20.0 | 2.0 | 
| 9-Jan-16# |  |  |  |  |  |  | 10.9 |  |  |  | 4.0 |  | 
| 11-Jan-16# |  |  |  |  |  |  | 26.2 |  |  |  | 9.0 |  | 
| 12-Jan-16 | 10.3 | 9.4 | 11.1 | 10.6 | 30.2 | 34.9 | 95.2 | 7.5 | 5.0 | 6.0 | 54.0 | 2.0 | 
| 13-Jan-16# |  |  |  |  |  |  | 10.4 |  |  |  | 5.0 |  | 
| 14-Jan-16 | 10.3 | 9.5 | 9.9 | 8.6 | 8.8 | 23.0 | 10.7 | 5.9 | 7.0 | 14.0 | 10.0 | 6.0 | 
| 16-Jan-16 | 10.6 | 10.5 | 10.3 | 11.0 | 40.6 | 10.7 | 143.5 | 8.8 | 17.0 | 4.0 | 89.0 | 3.0 | 
| 18-Jan-16 | 9.1 | 9.5 | 10.7 | 10.6 | 570.0 | 8.2 | 23.9 | 5.7 | 227.5 | 3.5 | 24.5 | 5.0 | 
| 19-Jan-16# |  |  |  |  | 22.2 |  | 8.8 |  |  |  | 6.0 |  | 
| 20-Jan-16 | 11.1 | 10.4 | 11.2 | 11.5 | 17.3 | 16.7 | 141.0 | 278.0 | 6.0 | 9.0 | 78.0 | 149.5 | 
| 22-Jan-16 | 11.9 | 11.1 | 11.6 | 10.2 | 9.6 | 71.8 | 9.8 | 5.3 | 6.0 | 30.5 | 4.5 | 2.0 | 
| 26-Jan-16 | 13.3 | 12.2 | 13.2 | 10.7 | 14.3 | 13.4 | 10.8 | 7.2 | 5.0 | 9.0 | 7.0 | 4.0 | 
| 28-Jan-16 | 12.8 | 13.5 | 9.7 | 12.1 | 200.5 | 190.5 | 502.5 | 164.0 | 146.5 | 145.5 | 289.0 | 184.0 | 
| 29-Jan-16# |  |  |  |  |  |  | 366.0 | 11.1 |  |  | 375.0 | 7.0 | 
| 30-Jan-16 | 11.0 | 9.2 | 10.3 | 8.7 | 22.1 | 4.4 | 10.7 | 6.5 | 12.0 | 2.5 | 7.5 | 4.5 | 
| Remarks: | (i)           
  bold with underline indicated Limit Level exceedance (ii)         
  bold and italic indicated Action Level exceedance #         Additional
  water quality monitoring at the exceeded location(s) due to two consecutive monitoring days indicated Limit Level exceedance. | 
Table 6-4         Water
Quality Monitoring Results Associated Contracts 2 and 6
| Date | Dissolved Oxygen (mg/L) | Turbidity (NTU) | Suspended Solids (mg/L) | |||
| WM3 | WM3- Control | WM3 | WM3- Control | WM3 | WM3- Control | |
| 2-Jan-16 | 8.9 | 9.1 | 9.6 | 18.8 | 10.0 | 21.0 | 
| 4-Jan-16 | 8.2 | 8.6 | 20.7 | 25.5 | 14.5 | 25.0 | 
| 6-Jan-16 | 9.4 | 8.0 | 13.4 | 10.8 | 11.5 | 20.5 | 
| 8-Jan-16 | 10.6 | 10.2 | 9.2 | 8.0 | 12.5 | 25.5 | 
| 12-Jan-16 | 10.2 | 8.7 | 6.9 | 72.3 | 6.5 | 102.0 | 
| 14-Jan-16 | 9.7 | 9.9 | 9.8 | 8.1 | 4.0 | 13.0 | 
| 16-Jan-16 | 10.1 | 10.5 | 57.9 | 49.2 | 45.5 | 321.0 | 
| 18-Jan-16 | 10.0 | 10.8 | 12.7 | 9.7 | 7.5 | 51.0 | 
| 20-Jan-16 | 12.3 | 11.4 | 22.1 | 19.4 | 23.5 | 55.0 | 
| 22-Jan-16 | 10.1 | 9.7 | 13.0 | 22.5 | 9.0 | 26.5 | 
| 26-Jan-16 | 10.9 | 12.4 | 10.4 | 21.6 | 11.5 | 32.0 | 
| 28-Jan-16 | 11.0 | 11.7 | 275.5 | 260.0 | 229.5 | 396.5 | 
| 30-Jan-16 | 10.3 | 10.6 | 11.6 | 14.8 | 7.5 | 9.0 | 
Table 6-5      Breaches
of Water Quality Monitoring Criteria in Reporting Period
| Location | Dissolved Oxygen | Turbidity | Suspended Solids | Total Exceedance | ||||
| Action | Limit | Action | Limit | Action | Limit | Action | Limit | |
| WM1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 
| WM2A | 0 | 0 | 0 | 2 | 1 | 1 | 1 | 3 | 
| WM2B | 0 | 0 | 1 | 9 | 0 | 8 | 1 | 15 | 
| WM3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 
| WM4 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 1 | 
| No of Exceedance | 0 | 0 | 1 | 12 | 1 | 9 | 2 | 21 | 
6.2.3                
In this Reporting Period, a total of
twenty-three (23) Limit/Action Levels exceedances were recorded, namely one (1)
AL and twelve (12) LL exceedance of turbidity and one (1) AL and nine (9) LL exceedance
of Suspended Solids for the Project.  There were two (2) LL of Turbidity and
one (1) AL & one (1) LL Level of Suspended Solids recorded at WM2A, one (1)
AL and nine (9) LL of Turbidity and eight LL of Suspended Solids recorded at WM2B
and one LL of Turbidity recorded at WM4.
6.2.4                
NOE was issued to relevant parties upon
confirmation of the monitoring result.  The cause of exceedance is summarized in Table
6-6 accordance to investigation findings and the detailed investigation
reports for the exceedances are attached in Appendix N.
Table 6-6      Summary of Water
Quality Exceedance in the Reporting Period
| Exceedance Day | Location | Exceeded Parameter | Cause of Water Quality Exceedance | 
| 2-Jan-16 | WM2B | NTU & SS | The exceedances should be related to Contract 6
  when the Contractor conducted channel cleaning for sediment and muddy water removal
  after rainfall.  Mitigation
  measures such as sump pit with temporary channel were constructed under the
  slope to divert the muddy runoff. 
  Enhance work such as hydro-seeding was applied at the stabilized slope
  in late January 2016.  | 
| 6-Jan-16 | WM2B | NTU & SS | The implemented mitigation measures and capacity of sump pits by Contract
  6 were not sufficient to cater the muddy runoff from site uphill.  Mitigation measures such as sump pit
  with temporary channel were constructed under the slope to divert the muddy
  runoff.  Enhance work such as
  hydro-seeding was applied at the stabilized slope in late January 2016.   | 
| 7-Jan-16 | WM2B | NTU | The exceedances were due to the shallow water and the disturbance of
  sediment at river bed and it unlikely related to the works under
  Contract 6.  | 
| 8-Jan-16 | WM2B | NTU & SS | The exceedances were due to the shallow water and the disturbance of
  sediment at river bed and it unlikely related to the works under the
  Contract 6.  | 
| 11-Jan-16 | WM2B | NTU | The exceedances were due to the shallow water and the disturbance of
  sediment at river bed and it unlikely related to the works under
  Contract 6.  | 
| 12-Jan-16 | WM2B | NTU & SS | The implemented mitigation measures and capacity of sump pits by Contract
  6 were not sufficient to cater the muddy runoff from site uphill.  Mitigation measures such as sump pit
  with temporary channel were constructed under the slope to divert the muddy
  runoff.  Enhance work such as
  hydro-seeding was applied at the stabilized slope in late January 2016.   | 
| 15-Jan-16 | WM4 | NTU | The exceedance was a single incident due to rainstorm and unlikely
  related to the works under the Contracts 2 and 3. | 
| 16-Jan-16 | WM2A | NTU & SS | Current mitigation measures provided by Contract 6 such covering the
  opened slope are not sufficient to cope with site runoff especially when
  raining.  Construction of bund along
  the riverside has been undertaking since 3 February 2016 at the
  works area of Bridge D.   | 
| WM2B | NTU & SS | The exceedances were likely related to contribution of muddy runoff
  from the public road surface and unlikely related to the works under
  Contract 6. | |
| 18-Jan-16 | WM2A | NTU & SS | Current mitigation measures provided by Contract 6 such covering the
  opened slope are not sufficient to cope with site runoff especially when
  raining.  Construction of bund
  along the riverside has been undertaking since 3 February 2016 at the
  works area of Bridge D.   | 
| WM2B | NTU & SS | The exceedances were likely related to contribution of muddy runoff
  from the public road surface and unlikely related to the works under
  Contract 6. | |
| 28-Jan-16 | WM2B | NTU & SS | Current
  mitigation measures provided by Contract 6 were not adequate to cater the
  large amount of storm runoff during rainstorm.  The Contractor has newly constructed a sump pit to collect the muddy runoff on 4 February 2016.   | 
| 29-Jan-16 | WM2B | NTU & SS | Current
  mitigation measures provided by Contract 6 were not adequate to cater the
  large amount of storm runoff during rainstorm.  The Contractor has newly constructed a sump pit to collect the muddy runoff on 4 February 2016.   | 
7.1.1                
Waste management was carried out by an
on-site Environmental Officer or an Environmental Supervisor from time to time.
7.2.1                
All types of waste arising from the
construction work are classified into the following:
l Construction
& Demolition (C&D) Material;
l Chemical
Waste;
l General
Refuse; and
l Excavated
Soil.
7.2.2                
The quantities of waste for disposal in this
Reporting Period are summarized in Tables 7-1 and 7-2 and the Monthly
Summary Waste Flow Table is shown in Appendix L.  Whenever possible, materials were reused
on-site as far as practicable.
Table 7-1         Summary
of Quantities of Inert C&D Materials for the Project
| Type of Waste | Contract 2 | Contract 3 | Contract 5 | Contract 6 | Contract SS C505 | Total Quantity  | |||||
| Qty. | Disposal location | Qty. | Disposal location | Qty. | Disposal location | Qty. | Disposal location | Qty. | Disposal location | ||
| C&D Materials (Inert) (in '000m3) | 74.4242 | -- | 2.430 | -- | 0 | -- | 58.943 | -- | 0.8 | -- | 136.5972 | 
| Reused in this Contract (Inert)  (in '000 m3) | 0.6482 | -- | 0.030 | -- | 0 | -- | 3.811 | -- | 0 | -- | 4.4893 | 
| Reused in other Contracts/ Projects (Inert)  (in '000 m3) | 32.5036 | C6/ NENT# &
  other projects approved by the ER | 0 | -- | 0 | -- | 12.131 | C5 &
  other projects approved by the ER | 0 | -- | 44.6346 | 
| Disposal as Public Fill (Inert)  (in '000 m3) | 41.2724 | Tuen Mun 38 | 2.40 | Tuen Mun 38 | 0 | -- | 43.001 | Tuen Mun 38 | 0.8 | TKO 137 | 87.4734 | 
Remark #: The
C&D materials were delivered to NENT for reuse by laying cover of the
landfilling area.
Table 7-2        Summary
of Quantities of C&D Wastes for the Project
| Type of Waste | Contract 2 | Contract 3 | Contract 5 | Contract 6 | Contract SS C505 | Total  Quantity | |||||
| Qty. | Disposal location | Qty. | Disposal location | Qty. | Disposal location | Qty. | Disposal location | Qty. | Disposal location | ||
| Recycled Metal (¡¥000kg) # | 0 | - | 0.001 | Licensed collector | 0 | -- | 0 | -- | 4.73 | Licensed collector | 0.001*+4.73 | 
| Recycled
  Paper / Cardboard Packing (¡¥000kg) # | 0 | - | 0 | - | 0 | -- | 0 | -- | 0 | -- | 0 | 
| Recycled Plastic (¡¥000kg) # | 0 | -- | 0 | - | 0 | -- | 0 | -- | 0 | -- | 0 | 
| Chemical Wastes (¡¥000kg) # | 0.8800 | Licensed collector | 0 | - | 0 | -- | 0 | -- | 0 | -- | 0.88 | 
| General Refuses (¡¥000m3)  | 0.1247 | NENT | 0.115 | NENT | 0.06 | NENT | 0.695 | NENT | 0.072 | NENT | 1.0667 | 
Remark #: Unit
of recycled metal, recycled paper/ cardboard packing, recycled plastic and
chemical waste for Contractor 3 was in (¡¥000m3).
8.1.1                
According to the approved EM&A Manual, the
environmental site inspection shall be formulation by ET Leader.  Weekly environmental site inspections should
carry out to confirm the environmental performance.
Contract 2
8.2.1                
In the Reporting Period, joint site
inspection for Contract 2 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on
8, 15, 22 and 29 January 2016. 
No non-compliance was noted.
8.2.2                
The findings / deficiencies of Contract
2 that observed during the weekly site inspection are listed in Table
8-1.
Table 8-1           Site
Observations for Contract 2
| Date | Findings / Deficiencies | Follow-Up Status | 
| 8 January 2016 |   Stockpile
  of bag cement more than 20 bages should be covered with tarpaulin sheet.
  (Admin Buidling) |   Cement
  bags were covered by tarpaulin. | 
|   Turbid
  water cumulated at the final gully was observed. The Contractor should review
  the treatment facilities and make sure all discharge water should comply with
  discharge license requirement. (Admin Buidling) |    The gully was cleaned and no muddy
  discharge was observed. | |
| 15 January 2016 |   Turbidity
  wheel washing water cumulated at the site exit was observed. The contractor
  should keep the site exit clean and tidy. (Mid-Vent)   White
  bubble cumulated at the discharge water treatment system was observed. The
  contractor should review the treatment system and make sure all discharge
  water should comply with discharge license requirement. (North Portal) |   Regular
  cleaning provided and no turbid water found at the site entrance.   The
  treatment system was fixed immediately and no foam was observed afterwards. | 
| 22 January 2016 |   The
  contractor was reminded to closely monitor the de-silting system and make
  sure all the discharge water should comply with license requirement. |   Not
  required for reminder. | 
| 29 January 2016 |   It
  was reminded that stagnant water cumulated inside the waste skip should be
  cleaned after the rainstorm to prevent mosquito breeding.   It
  was reminded that lifting eye of the concrete block should filled with sand
  to prevent stagnant water accmulation. |   Not
  required for reminder.   Not
  required for reminder. | 
Contract 3
8.2.3                
In the Reporting Period, joint site
inspection for Contract 3 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 4, 11, 20 and 25 January 2016.  No non-compliance was noted.
8.2.4                
The findings / deficiencies of Contract
3 that observed during the weekly site inspection are listed in Table
8-2.
Table 8-2           Site
Observations for Contract 3
| Date | Findings / Deficiencies | Follow-Up Status | 
| 4 January 2016 |   A
  diversion flow with sufficient protection was observed, the Contractor should
  provide proper measures to ensure the diversion flow would not be polluted by
  construction activities (SA12) |   A
  new pipe connected from the WetSep was provided to ensure diversion flow
  would not be polluted by construction activities. | 
|   The
  Contractor was reminded to maintain the cleanliness of the site exit. |   Not
  required for reminder. | |
| 11 January 2016 |   No
  adverse environmental were observed. |   NA | 
| 20 January 2016 |   Mud
  trace at site exit was observed. The contractor should clean up the trace and
  maintain the site exit clean and tidy. (SA18) |   The
  site exit was cleaned. | 
|   As
  a reminder, the contractor should closely monitor all discharge point to make
  sure all discharge water should comply with discharge license requirement. |   Not
  required for reminder. | |
| 25 January 2016 |   No
  adverse environmental were observed. |   NA | 
Contract 5
8.2.5                
In the Reporting Period, joint site
inspection for Contract 5 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 7, 12, 19 and 26 January 2016.  No non-compliance was noted. 
8.2.6                
The findings / deficiencies of Contract
5 that observed during the weekly site inspection are listed in Table
8-3.
Table 8-3           Site
Observations for Contract 5
| Date | ||
| 7 January 2016 |   No
  adverse environmental were observed. |   NA | 
| 12 January 2016 |   A
  tree without proper protection was observed at the working area in LMH road,
  the Contractor should fence off the tree to provide tree protection zone. |   The
  tree is isolated by fences. | 
| 19 January 2016 |   No
  adverse environmental were observed. |   NA | 
| 26 January 2016 |   To
  prevent storm water run-off from the site area, the Contractor should provide
  mitigation measures for the exposed surface adjacent to the public road. ((Location:
  LMH Road) |   The
  soil was dug out to lower the ground level along the concrete bund. | 
|   The
  Contractor was reminded to provide and maintain the mitigation measures for
  dusty stockpiles the stockpile for long time storage. (Location: BCP) |   Not
  required for reminder. | 
Contract 6
8.2.7                
In the Reporting Period, joint site
inspection for Contract 6 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 7, 14, 21 and 28 January 2016.  No non-compliance was noted. 
8.2.8                
The findings / deficiencies of Contract
6 that observed during the weekly site inspection are listed in Table
8-4.
Table 8-4           Site
Observations for Contract 5
| Date | Findings / Deficiencies | Follow-Up Status | 
| 7 January 2016 |   Smoke
  exhausted from generators were observed, the Contractor should provide
  maintenance to prevent smoke emission. (Location: BCP) |   The generator has
  been sent back for maintenance. And no smoke is observed from the other
  generator on site. | 
|   the
  Contractor should cover the exposed slope to minimize the dust generation. (North
  Portal) |   The
  Exposed slope surface not under constant work activities has been paved. | |
|   The
  Contractor was reminded to provide mitigation measures such as site hoarding
  for construction activity to avoid muddy water runoff to public area. |   Not
  required for reminder. | |
| 14 January 2016 |   Trees
  without proper fencing for protection were observed, the Contractor should
  fence off the retained trees and ensure no construction materials are placed near
  the trees. (Bridge D and Wo Keng Shan Road and Ng Chow Road) |   The trees are
  fenced off to prevent damage from construction activities. | 
| 21 January 2016 |   To
  prevent storm water run-off entering the water body, the Contractor should
  provide sand bags or relevant measures along the iron railings adjacent to
  the river. (Location: Ng Chow Road) |   Sand bags have
  been provided along the iron railings adjacent to the channel. | 
|   The
  Contractor should provide maintenance on the newly provided U-channel and
  improve it to redirect the run-off water from the site and to prevent from
  entering public area. (Location: Ng Chow Road) |   Tarpaulin sheets
  have been used to cover exposed surface. | |
|   Exposed
  road surface adjacent to a river was observed at Bridge C, the Contractor should
  provide mitigation measures to prevent water accumulation and water run-off
  from the site area entering the water body. Mitigation measures such as
  increase the gradient of land surface near the river side or rock fill at the
  low point with bund near the boundary side. |   Ground level has
  been elevated by rock filling and concrete bund has been set up along the
  site boundary | |
|   The
  Contractor should provide and maintain the tree protection measures for all
  the retained trees at Bridge C. |   Tree protection has
  been enhanced by barrier fencing | |
|   The
  Contractor was reminded to review the tree protection measures for the
  retained tree on Ng Chow Road and to remove the branch clipping from the
  tree. |   Not
  required for reminder. | |
|   28
  January 2016 |   To
  prevent wheel washing water entering the river, the Contractor should seal
  all the gaps along the temporary bridge at BCP. |   The
  gap of the temporary bridge has been sealed up with concrete. | 
|   It
  was observed that muddy water from C6 south portal directing to wastewater treatment
  facility (ID: SH-6 & SH-7) lead to overflow, and muddy water discharge
  through the facilities was occurred. The Contractor should modify the
  facilities and to ensure the water quality is comply with the discharge
  license requirement. |   The
  diameter of the influent pipe of the wastewater treatment facility (SH-7) was
  enlarge from 3 inches to 4 inches and the 3 inches of submersible pump was
  replaced by 4 inches one. Moreover, the frequency for desludging of
  wastewater treatment facility (SH-6) was increased from one per week to 3
  times per week.  Discharge of
  treated water from the wastewater treatment facility was visually clear after
  the above mentioned arrangement. | |
|  
  The
  Contractor was reminded to provide notice ¡§°±¨®¬~ñF¡¨ at each site exits. |   Not
  required for reminder. | 
Contract SS C505
8.2.9                
In the Reporting Period, joint site
inspection for Contract SS C505 to evaluate the site environmental performance
has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 20 and 27 January 2016.  No non-compliance was noted. 
8.2.10            
The findings / deficiencies of Contract
SS C505 that observed during the weekly site inspection are listed in Table
8-5.
Table 8-5           Site
Observations for Contract SS C505
| Date | Findings / Deficiencies | Follow-Up Status | 
| 6 January 2016 |   The
  Contractor should cover the stockpile well with impervious sheet to reduce
  dust generation in Portion 2.   The
  Contractor was reminded to remove stagnant water on site after rainy days |   The
  stockpile was covered well with tarpaulin sheet. | 
| 13 January 2016 |   Stagnant
  water was observed at the lifting eye of concrete block at Portion 1. The
  Contractor should take measures to avoid stagnant water being stored by the
  concrete blocks |   The
  lifting eye of the concrete blocks were filled with sand to avoid stagnant
  water being stored. | 
| 20 January 2016 |   The
  Contractor should cover the stockpile properly at Portion 2 to reduce dust
  generation and avoid being washed away by rain. |   The Contractor was reminded to
  clear the sediment at the drainage channel on site regularly. | 
|   The
  Contractor was reminded to clear the sediment at the drainage channel on site
  regularly. |   Not
  required for reminder. | |
| 27 January 2016 |   As
  a reminder, stagnant water cumulated inside the drip tray should be cleaned
  after the rainstorm.   As
  a reminder, dust mitigation measures should be provided for stockpile which
  storage on site. |   Not
  required for reminder.   Not
  required for reminder. | 
Contract 7
8.2.11            
Although
construction activities under Contract 7 have not yet commenced, site
preparation work was conducted in the Reporting Period.  In the Reporting Period, two occasions
of joint site inspection to evaluate the site environmental performance were
carried out on 5 and 26 January 2016.  No non-compliance was noted. 
8.2.12            
The findings / deficiencies of Contract
7 that observed during the weekly site inspection are listed in Table
8-6.
Table 8-6           Site
Observations for Contract 7
| Date | Findings / Deficiencies | Follow-Up Status | 
| 5 January 2016 |   As
  a reminder, all NRMM using on site should be granted with NRMM label or  under application under the NRMM
  Regulation. |   Not
  required for reminder. | 
| 26 January 2016 |   No
  adverse environmental were observed. |   NA | 
8.2.13            
Overall, general housekeeping such as daily
site tidiness and cleaniness should be
maintained for all Contracts.  Furthermore, the Contractors were
reminded to implement Waste Management Plan of the Project.
Other Contracts
8.2.14            
Since Contract 4 has not yet commenced, no
site inspection were performed.
9.1.1                
In the Reporting Period, no summons and
prosecution under the EM&A Programme was lodged for Contracts 2, 3, 5, 6
and Contract SS C505.  However, one (1)
verbal and two (2) documented environmental complaints regarding
wastewater / muddy water were received and lodged for Contracts 6. 
9.1.2                
Upon
receipt of the complaint, follow up action has been undertaken by both
Contractor promptly to resolve the complaints and deficiencies.  During the complaint investigation work,
the Contractor was co-operated with the ET in providing all the necessary
information and assistance for completion of the investigation.  Follow up actions have been undertaking
by the Contractor to resolve the deficiencies The details of complaint are
listed below:-
Investigation
Result for the Verbal Complaint received by the Contractor on 4
January 2016
9.1.3                
On 4 January 2016, a land user of the farm
located at junction of Ng Chow Road and Wo Keng Shan
Road notified the Contractor of C6 (CCKJV) that muddy water was observed in the
his land area.  It was suspected
that the muddy water was discharged from the construction site of C6. 
9.1.4                
According to the information provided by the
CCKJV, pump pipe burst from the bored piling work at Bridge B was occurred at
around 6pm on 4 January 2015.  The
muddy water from the burst pump pipe was accidentally leaked to the adjacent
river channel and the concerned farm which next to the bored piling area.  Immediate action has undertaken by CCKJV
as follows:-
(a)     
The muddy water in the affected channel was trapped by
the Contractor to stop
further spreading
(b)     
The
muddy water in the affected channel was pumped to the wastewater treatment
facilities for proper treatment and then recirculated for the bored piling work
(c)     
The
worker of CCKJV was sent to the affected farm to clean up part of the muddy
water
9.1.5                
On 5 January 2016 morning, representatives
of CCKJV, AECOM and the land user were carried out joint inspection at the
affected farm to investigate the source of muddy water and negotiate the
remediate works.  Under their
investigation, it was considered that the muddy water in the farm was come from
the leakage of burst pump pipe from bored piling work at Bridge B.  Some of the
muddy water on the affected farm has been cleaned up by the workers
of CCKJV.  However, the land user of
the farm expressed that they will carry out intense remediate work on the farm
as the cumulated mud may affect the crops on his farm.
9.1.6                
A joint site inspection by the RE, IEC, Contractor
and ET was carried out on 7 January 2016 at Bridge B and the adjacent channel
follow up the status of the complaint and remediate action.  During site inspection, it was observed
that the affected channel was kept clear of muddy water and it is believe that
the Contractor has completed the clearing works.  To avoid reoccurrence of similar
incident, the Contractor has constructed site hoarding for surrounding the site
area and it was completed on 21 January 2016.
Investigation
Result for the Documented Complaints received by EPD on 14 January 2016
9.1.7                
On 14 January 2016, a complaint was
received by EPD regarding the soil/ muddy water brought by the vehicle when
leaving the construction site.  The
soil/ muddy water were cumulated at the road and this situation has been
observed for a long period of time. 
It was suspected that the wheel washing facilities of the construction
site was not in proper function and follow up action is required. 
9.1.8                
A joint site inspection among
EPD/AECOM/CCKJV/DHK was conducted on 21 January 2016 morning for the complaint
investigation.  It was noted that
the complaint location is the site exit of North Portal adjacent to Sha Tau Kok
Road.  The concerned site exit was
previously maintained by Contractor of Contractor 2 (DHK) provided with
automatic wheel washing facility. 
Since the concerned area had been handed over to Contractor of Contract
6 (CCKJV), DHK has relocated the wheel washing facility within the boundary of
Contract 2. The current exit of North Portal is being shared by Contract 2 and
Contract 6 but maintained by CCKJV. 
9.1.9                
Joint site inspection among RE, IEC, CCKJV
and ET was conducted on 21 January 2016 afternoon at the complaint location for
investigation.  It was observed that
muddy water was cumulated at the roadside of Sha Tau Kok Road.  Manual wheel washing was provided before
the site exit and there was cut-off ditch to intercept any storm water or
residual water from manual wheel washing, however, the ditch was damaged due to
frequent passage of truck and the muddy water generated by manual wheel washing
was getting into the adjacent Sha Tau Kok Road. 
9.1.10            
CCKJV was advised to immediately provide
protection for the road gully outside the site exit to avoid muddy water
directly getting into the communal drainage.  Moreover, the Contractor should repair
the damage road surface and reinstate the cut-off ditch in proper
function.  The remedial works were
completed on 5 February 2016 afternoon as following:-
(a)          
A new cut-off ditch was constructed in
order to divert the wastewater generated from wheel washing activity to the
sump pit.  Manual wheel washing
would only conduct behind the new cut-off ditch to ensure all wastewater from
wheel washing being intercepted. 
(b)         
The damaged cut-off ditch was repaired in
order to prevent wastewater being overflow to public road. 
(c)          
Water pump was provided at the sump pit to
pump the wastewater to the sedimentation tanks to undergo treatment  
(d)         
Sedimentation tank and sand bag bund was
installed and removal of silt in the sedimentation tank would be carried out
once per week.
9.1.11            
During site inspection on 12 February 2016, it was
observed that the remedial works by CCKJV was properly
in place and no cumulated muddy water was observed at the concerned site
exit.  However, CCKJV was advised to
closely monitor the condition of the site exit and further improve the wheel
washing facilities if necessary. 
Investigation
Result for the Documented Complaints received by EPD on 20 January 2016
9.1.12            
A complaint was received from EPD on 20
January 2016 regarding soil/ muddy water gushed out from the construction site
and getting into his village house area. In view of the complaint location and
confirmed with the Contractor, this complaint is related to the accident of
burst pump pipe from a recirculation tank during the bored piling work at
Bridge B happened on 4 January 2016, which causing muddy water leaked from the
works area to the nearby village house area.  The investigation report for the
accident was conducted by ET and submitted to the RE on 12 January 2016.
9.1.13            
Joint site inspection among EPD, RE and
Contractor was carried on 21 January 2016 morning for the complaint
investigation.  During the
inspection, the Contractor has explained to EPD that the complaint is related
to the accident of burst pump pipe from a recirculation tank causing leakage of
muddy water at Bridge B on 4 January 2016. 
After the burst pump pipe accident, the Contractor had taken remedial
action such as immediately cleaned up the muddy water at the affected area and
constructed site hoarding and provided sand bag barrier as a temporary berm to isolate
the bored piling area to avoid reoccurrence of leakage cases.  
9.1.14            
During the EPD¡¦s inspection on 21 January
2016, the bored piling area and the remediated works conducted by the
Contractor were inspected.  The
findings during the site inspection are summarized below:-
(a)   
No leakage of soil/ muddy water was observed from
concerned recirculation tanks and the bored piling area.
(b)     
After the burst pump pipe incident, site hoarding had
been constructed to isolate the bored piling area and the adjacent village
houses which prevent muddy water flowing from the works area of C6 to other
non-C6 works areas. 
(c)     
Sand bags barriers and drains as a temporary berm were
erected at the isolate of the bored piling area which construction of hoarding
is not practicable. 
9.1.15            
There was no muddy water leakage from the
bored piling works area after the remedial action taken by the Contractor.  It is considered that the remediate measures
provided by the Contractor are effectively preventing muddy water leaked from
the works area.  However, the
Contractor was reminded to regularly check and maintain the condition of the
pump pipe and related machinery to minimize the chance of similar accident. 
EPD
has no further comment on the remediate works
conducted by the Contractor during the site inspection on 21 January 2016.
9.1.16            
The statistical summary table of
environmental complaint is presented in Tables
9-1, 9-2 and 9-3.
Table 9-1           Statistical
Summary of Environmental Complaints
| Reporting Period | Contract No | Environmental
   Complaint Statistics | ||
| Frequency | Cumulative | Complaint Nature | ||
| 19 May 2014 ¡V  31 Dec 2015 | Contract 2 | 0 | 13 |  (6) Water Quality  (5) Construction Dust  (2) Noise | 
| 06 Nov 2013 ¡V 31 Dec 2015 | Contract 3 | 0 | 3 |  (1) Construction Dust  (2) Water quality | 
| 16 Aug 2013 ¡V 31 Dec 2015 | Contract 5 | 0 | 2 |  (2) Construction Dust | 
| 16 Aug 2013 ¡V 31 Dec 2015 | Contract 6 | 0 | 3 |  (2) Water Quality  (1) Construction Dust | 
| 16 Aug 2013 ¡V 31 Dec 2015 | SS C505 | 0 | 0 | N/A | 
| 1 ¡V 31 January 2016 | Contract 2 | 0 | 13 |  (6) Water Quality  (5) Construction Dust  (2) Noise | 
| Contract 3 | 0 | 3 |  (1) Construction Dust  (2) Water quality | |
| Contract 5 | 0 | 2 |  (2) Construction Dust | |
| Contract 6 | 2 | 5 |  (4) Water Quality  (1) construction Dust | |
| SS C505 | 0 | 0 | N/A | |
Table 9-2           Statistical
Summary of Environmental Summons
| Reporting Period | Contract No | Environmental
  Summons Statistics | ||
| Frequency | Cumulative | Complaint Nature | ||
| 19 May 2014 ¡V  31 Dec 2015 | Contract 2 | 0 | 0 | NA | 
| 06 Nov 2013 ¡V 31 Dec 2015 | Contract 3 | 0 | 0 | NA | 
| 16 Aug 2013 ¡V 31 Dec 2015 | Contract 5 | 0 | 0 | NA | 
| 16 Aug 2013 ¡V 31 Dec 2015 | Contract 6 | 0 | 0 | NA | 
| 1 ¡V 31 January 2016 | SS C505 | 0 | 0 | NA | 
| Contract 2 | 0 | 0 | NA | |
| Contract 3 | 0 | 0 | NA | |
| Contract 5 | 0 | 0 | NA | |
| Contract 6 | 0 | 0 | NA | |
Table 9-3           Statistical
Summary of Environmental Prosecution
| Reporting Period | Contract No | Environmental
  Prosecution Statistics | ||
| Frequency | Cumulative | Complaint Nature | ||
| 19 May 2014 ¡V  31 Dec 2015 | Contract 2 | 0 | 0 | NA | 
| 06 Nov 2013 ¡V 31 Dec 2015 | Contract 3 | 0 | 0 | NA | 
| 16 Aug 2013 ¡V 31 Dec 2015 | Contract 5 | 0 | 0 | NA | 
| 16 Aug 2013 ¡V 31 Dec 2015 | Contract 6 | 0 | 0 | NA | 
| 1 ¡V 31 January 2016 | SS C505 | 0 | 0 | NA | 
| Contract 2 | 0 | 0 | NA | |
| Contract 3 | 0 | 0 | NA | |
| Contract 5 | 0 | 0 | NA | |
| Contract 6 | 0 | 0 | NA | |
The Other Contracts
9.1.17            
Since the construction works at the Contract
4 and Contact 7 have not yet commenced, no environmental complaint, summons
and prosecution under the EM&A Programme are registered in the Reporting
Period. 
Warning Letter
9.1.18            
A warning letter from EPD was issued to Contract
6 on 1 February 2016 regarding Non Compliance (NC) with APCO for the
non-covered dump trucks travelling to Fill Bank at TM Area 38 on 14 and 18
January 2016 respectively.  The
Contractor has explained to the EPD that all dump trucks under the Contract
were well covered before leaving the site, however, some drivers of the dump
trucks immediately opened the cover when they just get into Fill Bank at TM
Area 38 and captured by the CCTV.  A
briefing and warning letter has given to the relevant drivers to prevent
reoccurrence of similar case. 
10.1.1            
The environmental mitigation measures that
recommended in the Implementation Schedule for Environmental Mitigation
Measures (ISEMM) in the approved EM&A Manual covered the issues of dust,
noise, water and waste and they are summarized presented in Appendix
M. 
10.1.2            
All contracts under the Project shall be
implementing the required environmental mitigation measures according to the approved
EM&A Manual as subject to the site condition.  Environmental mitigation measures
generally implemented by Contracts 2, 3, 5, 6 and Contract SS C505 in this
Reporting Period are summarized in Table 10-1.  
Table 10-1         Environmental
Mitigation Measures
| Issues | Environmental Mitigation
   Measures | 
| Water Quality | ¡P       Wastewater to be treated by the
  wastewater treatment facilities i.e. sedimentation tank or AquaSed before
  discharge. | 
| Air Quality | ¡P       Maintain damp / wet surface
  on access road ¡P       Keep slow speed in the sites ¡P       All vehicles must use wheel
  washing facility before off site ¡P       Sprayed water during
  breaking works ¡P       A
  cleaning truck was regularly performed on the public road to prevent fugitive dust emission | 
| Noise | ¡P       Restrain operation time of
  plants from 07:00 to 19:00 on any working day except for Public Holiday and
  Sunday. ¡P       Keep good maintenance of
  plants ¡P       Place noisy plants away from
  residence or school ¡P       Provide noise barriers or
  hoarding to enclose the noisy plants or works ¡P       Shut down the plants when
  not in used. | 
| Waste and Chemical Management | ¡P       On-site sorting prior to
  disposal ¡P       Follow requirements and
  procedures of the ¡§Trip-ticket System¡¨ ¡P       Predict required quantity of
  concrete accurately ¡P       Collect the unused fresh
  concrete at designated locations in the sites for subsequent disposal | 
| General | ¡P       The site was generally kept
  tidy and clean. | 
10.2.1            
Construction activities as undertaken in the
coming month for the Project lists below:
Contract 2
| Mid-Vent Portal |     Tube
  excavation (NB+SB)      Adit invert
  slab     Building
  works foundation | 
| North Portal |    
  Retaining walls and slope stabilization     
  Northbound top heading excavation and
  tunnel enlargement    
  Southbound tunnel internal works and
  finishes    
  TBM excavation | 
| South Portal |    
  Southbound and
  Northbound D&B excavation    
  Building works superstructure | 
| Admin Building |    
  Building
  works foundation | 
Contract 3
  
Cable detection and trial trenches
  
Decking construction for Bridge E
  
Filling works at Tong Hang East
  
Storm Drains Laying
  
Noise barrier construction
  
Pier / Pier Table construction
  
Pile cap works
  
Portal beam erection
  
Pre-drilling works and piling works for
viaduct
  
Retaining Wall construction
  
Road works at Fanling Highway
  
Slope works 
  
Socket H-pile installation
  
Tree felling works
  
Utilities duct laying
  
Viaduct segment erection 
  
Water works
  
Sewer works
Contract 5
  
Laying of additional rising main at LMH road
  
Bituminous laying at
L15 road and existing LMH road.
  
Brick laying at footpath of proposed LMH road
  
Road works (kerb and
bituminous laying) at existing LMH road
  
Drainage works at Depressed Road at BCP3
  
Irrigation system at existing LMH Road
  
Installation of underground utilities at
existing LMH Road 
  
Construction of Pavilion at Chung Yuen Ha
Village
Contract 6
  
Site Clearance
  
Slope Works
  
Site Accesses Construction
  
Ground Investigation Works
  
Soil Nail
  
Bored Piling
  
Pile cap construction
Contract
SS C505
  
Excavation & fill works
  
Predrilling
  
Percussive piling
  
Pre-boring
  
Bored piling
  
Pile caps
  
Training centre
set-up
  
Structural works
  
Assembly of crawler crane
  
Weighbridge works
  
Construction of Prototype A & C
10.3.1            
Key issues to be considered in the coming
month for Contracts 2, 3, 5,6 and SS C505 include:
   
Implementation of
control measures for rainstorm;
   
Regular clearance of stagnant
water during wet season;
   
Implementation of dust
suppression measures at all times;
   
Potential wastewater
quality impact due to surface runoff;
   
Potential fugitive
dust quality impact due from the dry/loose/exposure soil surface/dusty
material;
   
Disposal of empty
engine oil containers within site area;
   
Ensure dust suppression measures are
implemented properly;
   
Sediment catch-pits and silt removal
facilities should be regularly maintained;
   
Management of chemical wastes;
   
Discharge of site effluent to the nearby
wetland, stockpiling or disposal of materials, and any dredging or construction
area at this area are prohibited;
   
Follow-up of improvement on general waste
management issues; and
   
Implementation of construction noise
preventative control measures
10.3.2            
Contract 4 and Contact 7 have not yet
commenced and no environmental issue is presented. 
11.1.1            
This is the 30th monthly EM&A report presenting the monitoring
results and inspection findings for the Reporting Period from 1 to 31 January 2016.
11.1.2            
For air quality monitoring, no 1-hour and
24-hour TSP monitoring results triggered the Action or Limit Levels were
recorded. No NOEs or the associated corrective actions
were therefore issued.
11.1.3            
No noise complaint (which is an Action Level
exceedance) was received and no construction noise measurement results that
exceeded the Limit Level were recorded in the Reporting Period. No NOEs or the associated corrective actions were therefore
issued.
11.1.4            
For water quality monitoring, a total of
twenty-three (23) Limit/Action Levels exceedances were recorded, namely one (1)
AL and twelve (12) LL exceedance of turbidity and one (1) AL and nine (9) LL exceedance
of Suspended Solids for the Project. The investigations for the cause of
exceedances have been conducted by the ET and the associated investigation
reports were submitted to relevant parties
11.1.5            
No environmental summons or successful
prosecutions were recorded in the Reporting Period.  However, a warning letter from EPD was
issued to Contract 6 on 1 February 2016 regarding Non Compliance (NC) with APCO
for the non-covered dump trucks travelling to Fill Bank at TM Area 38 on 14 and
18 January 2016 respectively.  The
Contractor has explained to the EPD that all dump trucks under the Contract
were well covered before leaving the site, however, some drivers of the dump
trucks immediately opened the cover when they just get into Fill Bank at TM
Area 38 and captured by the CCTV.  A
briefing and warning letter has given to the relevant drivers to prevent
reoccurrence of similar case. 
11.1.6            
In this Reporting Period, one (1) verbal
complaint received by the Contractor and two (2) documented environmental
complaints regarding wastewater / muddy water related to Contracts 6 were received and
lodged by EPD on 14 and 20 January 2016 respectively.  Follow up actions have been undertaking
by the Contractor to resolve the deficiencies and investigation report
conducted by ET had submitted to all relevant parties.  
11.1.7            
During the Reporting Period, weekly joint
site inspection by the RE, IEC, ET with the relevant Main-contractor were
carried out for Contracts 2, 3, 5, 6 and SS C505 in accordance with the
EM&A Manual stipulation.  No
non-compliance observed during the site inspection.  
11.2.1            
During dry season, special attention should
be paid on the potential construction dust impact since most of the
construction sites are adjacent to villages. The Contractor should fully implement
the construction dust mitigation measures properly.
11.2.2            
The Contractor was reminded to prevent muddy
water or other water pollutants from site surface flow to local stream such as Kong
Yiu Channel, Ma Wat Channel, Ping Yuen River or public area.  For all Contracts, water quality
mitigation measures to prevent muddy runoff into nearby water bodies or public
areas should paid attention and fully implemented in particular for Contract 6.
11.2.3            
Construction noise would be a key
environmental issue during construction work of the Project.  Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
11.2.4            
Furthermore, daily cleaning and weekly tidiness shall be properly performed
and maintained. In addition, mosquito
control should be kept to prevent mosquito breeding on site.