|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
16th Quarterly Environmental Monitoring & Audit Summary Report ¡V (May
to July 2017) |
|
|
||
|
|
Prepared
For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Quality Index |
|||
Date |
Reference No. |
Prepared By |
Certified By |
27 November 2017 |
TCS00694/13/600/R1315v2 |
|
|
Nicola
Hon (Environmental Consultant) |
T.W. Tam (Environmental Team Leader) |
Version |
Date |
Description |
1 |
21 November 2017 |
First
Submission |
2 |
27 November 2017 |
Amended according to the IEC¡¦s comments on 24
November 2017 |
|
|
|
This
report has been prepared by Action-United Environmental Services &
Consulting with all reasonable skill, care and diligence within the terms of
the Agreement with the client, incorporating our General Terms and Conditions
of Business and taking account of the resources devoted to it by agreement
with the client. We disclaim any responsibility to the client and others in
respect of any matters outside the scope of the above. This report is
confidential to the client and we accept no responsibility of whatsoever
nature to third parties to whom this report, or any part thereof, is made
known. Any such party relies upon the report at their own risk. |
Executive Summary
ES.01.
This is the 16th Quarterly
EM&A Summary Report for the ¡§Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works¡¨ under Environmental Permit No. EP-404/2011/D (hereinafter ¡¥¡¥the EP¡¦¡¦), covering the period from 1 May to 31 July 2017 (hereinafter ¡§Reporting
Period¡¨).
Environmental Monitoring and
Audit Activities
ES.02. In the
Reporting Period, the construction works under Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project
included Contract 2, Contract 3, Contract 6, Contract 7 and Contract SS C505. Environmental monitoring
activities under the EM&A programme in the Reporting Period are summarized
in the following table.
Environmental Aspect |
Monitoring Parameters
/ Inspection |
Reporting Period |
|
Monitoring Locations
/ Contracts |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
417 |
24-hour TSP |
9 |
144 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
130 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1 & WM1-C, |
40 scheduled and 8 extra of sampling day |
WM2A & WM2A-Cx |
40 scheduled and 16 extra of sampling day |
||
WM2B & WM2B-C |
(*) 40 Scheduled |
||
WM3 &WM3-C |
40 scheduled and 7 extra of sampling day |
||
WM4, WM4-CA &WM4-CB |
40 scheduled and 6 extra of sampling day |
||
Ecology |
Woodland compensation i) General Health condition of planted species ii) Survival of planted species |
9 Quadrats |
1 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing |
Contract 2 |
13 |
Contract 3 |
13 |
||
Contract 4 (#) |
12 |
||
Contract 6 |
13 |
||
Contract 7 |
13 |
||
Contract SS C505 (#) |
13 |
Note:
Extra monitoring day was due to measurement results exceedance
(#) IEC only joined one (1) event of site inspection for Contracts 4 and
SS C505.
(*)
Water sampling was unable to
carry out at WM2B and WM2B-C due to shallow water (water depth under 150mm)
Breaches
of Action/Limit levels
ES.03. In the
Reporting Period, no noise complaint which triggered Action Level and Limit Level exceedance was registered for construction
noise.
For air quality, there were 1 Action Level exceedances recorded. For water quality
monitoring, a total of 90 Action/ Limit
Level exceedance were recorded. The summary of exceedance for the
Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
||
NOE Issued |
Investigation |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
24-hour TSP |
1 |
0 |
1 |
Not project related |
NA |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
-- |
-- |
Turbidity |
0 |
43 |
43 |
Investigation results revealed that all exceedances were not
related to the works under the project. |
The Contractor
was reminded to implement water quality mitigation measures in accordance
with ISEMM of the EM&A Manual requirements |
|
SS |
2 |
45 |
47 |
Environmental
Complaint
ES.04. In this
Reporting Period, no environmental complaints were received under the EM&A program.
Notification of Summons and Successful Prosecutions
ES.05. As notified
by the RE in the Reporting Period, a summons (ref. no. FLS7210/2017 dated 20
June 2017) was issued to the Contractor of Contract 2 (Dragages Hong Kong
Limited) for contravening the Water Pollution Control (General) Regulations. During hearing on 25 July 2017, DHK
pleaded guilty to the EPD summons ¡V failing to report discharge within 24 hours
of its occurrence. Therefore, a
summons and prosecutions was registered for Contract 2 under the EM&A programme
in the Reporting Period.
Reporting Changes
ES.06. No reporting
changes were made in the Reporting Period.
Future key issues
ES.07. During wet
season, preventive measures for muddy water or other water pollutants from site
surface flow to local stream such as Kong Yiu
Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei
River or public area should be properly maintained. The Contractors should paid special
attention on water quality mitigation measures and fully implement according
ISEMM of the EM&A Manual, in particular for working areas near Ma Wat
Channel and Ping Yuen River.
ES.08. In
addition, all effluent discharge shall be ensure to fulfill Technical
Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland
and Coastal Waters criteria or discharge permits stipulation.
ES.09. Construction
noise would be a key environmental issue during construction work of the
Project. Noise mitigation measures
such as using quiet plants should be implemented in accordance with the
EM&A requirement.
ES.10. Since most
of construction sites under the Project are located adjacent to villages, the
Contractors should fully implement air quality mitigation measures to reduce
construction dust emission.
Table of Contents
2 Project Organization and
Construction progress
2.1 Construction
Contract Packaging
2.5 Summary of Environmental Submissions
3 Project Organization and
Construction progress
3.4 Monitoring
Frequency and Period
3.8 Derivation
of Action/Limit (A/L) Levels
3.9 Data
Management and Data QA/QC Control
4.2 Summary
of Monitoring Results
5 Construction Noise
Monitoring
5.2 Summary
of Monitoring Results
6.2 Summary
of Monitoring Results
8.2 Records
of Waste Quantities
10 Non-compliance, Complaints,
Notifications of Summons and Prosecutions
10.1 Status
of Non-compliance Environmental Complaint, Summons and Prosecution
11 Implementation Status of Mitigation
Measures
12 Conclusions and Recommendations
List
of tables
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Impact
Monitoring Stations - Air Quality
Table 3-3 Impact
Monitoring Stations - Construction Noise
Table 3-4 Impact
Monitoring Stations - Water Quality
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Construction
Noise Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action
and Limit Levels for Water Quality
Table 4-1 Summary
of Air Quality Monitoring Results
Table 4-2 Summaries
of Breaches of Air Quality A/L Levels
Table 5-1 Summary
of Construction Noise Monitoring Results
Table 5-2 Summaries
of Breaches of Construction Noise A/L Levels
Table 6-1 Summary
of the Water Quality Monitoring Results ¡V Contracts SS C505 & 6
Table 6-2 Summary
of the Water Quality Monitoring Results ¡V Contracts 2 & 3
Table 6-3 Summary
of the Water Quality Monitoring Results ¡V Contract 6
Table 6-4 Summary
of the Water Quality Monitoring Results ¡V Contracts 2 & 6
Table 6-5 Summaries
of Breaches of the Existing Water Quality A/L Levels
Table 6-6 Summary
of Water Quality Exceedance in the Reporting Period
Table 8-1 Summary
of Quantities of Inert C&D Materials
Table 8-2 Summary
of Quantities of C&D Wastes
Table 9-1 Summary
of Reminders/Observations of Site Inspection ¡V Contract 2
Table 9-2 Summary
of Reminders/Observations of Site Inspection ¡V Contract 3
Table 9-3 Summary
of Reminders/Observations of Site Inspection ¡V Contract 6
Table 9-4 Summary
of Reminders/Observations of Site Inspection ¡V Contract SS C505
Table 9-5 Summary
of Reminders/Observations of Site Inspection ¡V Contract 7
Table 10-1 Statistical
Summary of Environmental Complaints
Table 10-2 Statistical
Summary of Environmental Summons
Table 10-3 Statistical
Summary of Environmental Prosecution
Table 11-1 Environmental
Mitigation Measures
List of Annexes
Appendix A Layout plan of the Project
Appendix B Environmental Management Organization Chart
Appendix C Designated Monitoring Locations as Recommended in the Approved
EM&A Manual
Appendix D Monitoring Locations for Impact Monitoring
Appendix E Event and Action Plan
Appendix F Graphical Plots for Monitoring
Result
Appendix G Weather information
Appendix H Waste Flow Table
Appendix I Implementation Schedule for
Environmental Mitigation Measures
1.1.1. Civil Engineering and
Development Department is the Project
Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE) Liantang / Heung Yuen Wai Boundary
Control Point and Associated Works, which is a Designated Project to be
implemented under Environmental Permit number EP-404/2011/C granted on 12 March
2015 and the latest Environmental Permit
number EP-404/2011/D granted on 20 January 2017.
1.1.2. The Project consists of two main
components: Construction of a Boundary Control Point (hereinafter referred as
¡§BCP¡¨); and Construction of a connecting road alignment. Layout plan of the Project is shown in Appendix A.
1.1.3. The proposed BCP is located at the
boundary with Shenzhen near the existing Chuk Yuen
Village, comprising a main passenger building with passenger and cargo
processing facilities and the associated customs, transport and ancillary
facilities. The connecting road
alignment consists of six main sections:
1)
Lin Ma Hang to Frontier Closed Area (FCA) Boundary ¡V this section
comprises at-grade and viaducts and includes the improvement works at Lin Ma
Hang Road;
2)
Ping Yeung to Wo Keng Shan ¡V this section
stretches from the Frontier Closed Area Boundary to the tunnel portal at Cheung
Shan and comprises at-grade and viaducts including an interchange at Ping
Yeung;