Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/ Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report
(No.121) ¡V August 2023 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
12 September 2023 |
TCS00694/13/600/R2847v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
11 September 2023 |
First
Submission |
2 |
12 September 2023 |
Amended
As Per IEC¡¦s comment |
|
|
|
executive summary
ES01
This is the 121st monthly Environmental Monitoring & Audit (EM&A) report
presenting the monitoring results and inspection findings for the reporting period from 1 to 31 August 2023 (hereinafter ¡¥the Reporting
Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project is divided to six CEDD
contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03), Contract
6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03
The
construction activities under Contract 5 have been completed in September 2016
and area under Contract 5 were handover to SS C505 and Contract 6 after
completion. Subsequently, substantial
completion for the Works for Contract 2, 3, 4, 6, 7 and SS C505 has been
achieved in 2019. Proposal for
partial termination of the construction phase EM&A programme
for Contracts 2, 4, 7 and SS C505 was approved by EPD on 9 July 2020 (EPD¡¦s
ref.: ( ) in Ax (3) to EP 2/N7/A/52 Pt.17). Moreover, termination proposal for
Contract 3 was approved by EPD on 4 May 2021 (EPD¡¦s ref.: () in Ax (3) to EP
2/N7/A52 Pt.18). Therefore, air quality monitoring stations AM1c, AM8 &
AM9b, noise monitoring stations NM1, NM7, NM8, NM9 & NM10 and water quality
monitoring stations WM4, WM4-CA & WM4-CB and ET¡¦s site inspection and audit
for relevant works area for Contracts 2, 3, 4, 5, 7 and SS C505 was ceased
accordingly.
ES04
In the Reporting Period, environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the
following table.
Environmental Aspect |
Environmental Monitoring Parameters /
Inspection |
Reporting Period |
|
Number of Monitoring Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour
TSP |
6 (#) |
96 |
24-hour
TSP |
6 (#) |
29 |
|
Construction Noise |
Leq(30min) Daytime |
5 (~) |
26 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1
& WM1-C |
13 Scheduled &
0 extra (*) |
WM2A(a)
& WM2A-Cx |
13 Scheduled &
0 extra (*) |
||
WM2B
& WM2B-C |
13 Scheduled &
0 extra (*) |
||
WM3x
&WM3-C |
13 Scheduled &
0 extra (*) |
||
Joint Site Inspection / Audit |
ET and
the Contractor joint site Environmental Inspection and Auditing |
Contract 6 |
5 |
ET, the
Contractor, IEC and RE joint site Environmental Inspection and Auditing |
1 |
Remark:
(*) Water
sampling was unable to carry
out at WM1-C, WM3-C, WM2B
and WM2B-C in the Reporting Period due to shallow water. Water sampling was unable to carry out at WM1-C at some
of monitoring days in the Reporting Period. WM4,
WM4-CA and WM4-CB were ceased after last monitoring carried out on 3 May 2021
according to Partial Termination Proposal for Contract 3 approved by EPD on 4
May 2021.
(#)
Number of air monitoring location changed to 6 since the partial termination proposal
approved by EPD on 9 Jul 2020 and 4 May 2021. Power supply for HVS for 24-hour TSP
monitoring at Location AM3 (Ta Kwu Ling Ambulance
Depot) was suspended from 1 February 2023 due to the renovation work of Ta Kwu Ling Ambulance Depot.
(~)
Number of noise monitoring location changed to 5 since the partial termination proposal
approved by EPD on 9 Jul 2020 and 4 May 2021.
Action and Limit (A/L) Levels exceedance
ES05
In the Reporting Period, no exceedance was recorded for construction noise, air quality and water quality monitoring. The summary of exceedance in the Reporting Period is shown below.
Environmental Aspect |
Monitoring
Parameters |
Action Level |
Limit Level |
Event
& Action |
|||
NOE
Issued |
Investigation
Result |
Project
related exceedance |
Corrective
Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
-- |
-- |
-- |
Turbidity |
0 |
0 |
0 |
-- |
-- |
||
SS |
0 |
0 |
0 |
Environmental
Complaint
ES06
No environmental complaint was recorded in the Reporting Period.
Notification
of Summons and Successful Prosecutions
ES07
No environmental summons and prosecutions were recorded in the Reporting Period.
Reporting Change
ES08
Construction works for additional works at
Kong Yiu Channel area was completed in May 2023, thus no construction work and
waste raised of the Projects was presented in the Reporting Period. Updated EM&A
termination proposal (Revision 2) addressing EPD¡¦s comment on 28 July 2023 was certified
by ET and verified by IEC in August 2023 and the proposal was submitted to EPD
by AECOM in early-August 2023.
Site Inspection
ES09
In the Reporting Period, joint site
inspection has been carried out by the ET and the Contractor on 2, 9, 16, 23 and 29 August 2023. Joint site
inspection with IEC, ET and the Contractor was carried out on 29 August 2023. No non-compliance
was noted during the site inspection.
Future Key Issues
ES10
As
construction work of the Project was completed in May 2023, thus no adverse
environmental issue arising from the Project is foreseen in the future.
ES11
The
Contractor was reminded to implement the mitigation measure for the Operation
Phase as stipulated in the EP and the approved EIA Report.