|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/ Heung Yuen Wai
Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report
(No.94) ¡VMay 2021 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
15 June 2021 |
TCS00694/13/600/R2648v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
9 June 2021 |
First
Submission |
2 |
15 June 2021 |
Amended
as Per IEC¡¦s comment |
|
|
|
executive summary
ES01
This is the 94th monthly Environmental Monitoring & Audit (EM&A) report
presenting the monitoring results and inspection findings for the reporting period from 1 to 31 May 2021 (hereinafter ¡¥the
Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project is divided to six CEDD
contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03), Contract
6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03
In the Reporting Period, environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the
following table.
Environmental Aspect |
Environmental Monitoring Parameters /
Inspection |
Reporting Period |
|
Number of Monitoring Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour
TSP |
6 (#) |
90 |
24-hour
TSP |
6 (#) |
31 |
|
Construction Noise |
Leq(30min) Daytime |
5 (~) |
20 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1
& WM1-C |
13 Scheduled &
0 extra |
WM2A(a)
& WM2A-Cx |
13 Scheduled &
0 extra |
||
WM2B
& WM2B-C |
13 Scheduled &
0 extra (*) |
||
WM3x
&WM3-C |
13 Scheduled &
0 extra (*) |
||
WM4,
WM4-CA &WM4-CB |
1 Scheduled & 0 extra (*) |
||
Ecology |
Woodland
compensation i)
General Health condition of planted species ii) Survival
of planted species |
9
Quadrats and transect |
1 |
Wetland compensation i)
Site inspection |
Contract
6 |
4 |
|
Joint Site Inspection / Audit |
IEC, ET,
the Contractor and RE joint site Environmental Inspection and Auditing |
Contract 3 |
1 |
Contract
6 |
4 |
Remark:
(*) Water
sampling was unable to carry
out at WM2B and WM2B-C in the Reporting Period due to shallow water. Besides, WM3-C
was also unable to carry out in the Reporting Period due to shallow water. (Water depth under
150mm). WM4, WM4-CA and WM4-CB were ceased after last monitoring carried
out on 3 May 2021 according to Partial Termination Proposal for Contract 3
approved by EPD on 4 May 2021.
(#)
Number of air monitoring location changed to 6 since the partial termination proposal
approved by EPD on 9 Jul 2020 and 4 May 2021.
(~)
Number of noise monitoring location changed to 5 since the partial termination proposal
approved by EPD on 9 Jul 2020 and 4 May 2021.
ES04
Revised termination proposal for Contract 3
was submitted to EPD on 9 April 2021 for approval. The termination proposal
covers air quality monitoring station AM9b, noise monitoring stations NM8, NM9
and NM10, Water Quality monitoring stations WM4, WM4-CA and WM4-CB and ET¡¦s
site inspection and audit for relevant works area for Contract 3. The proposal
was approved by EPD on 4 May 2021 (EPD¡¦s ref.: () in Ax (3) to EP 2/N7/A52
Pt.18). The revised termination proposal for Contract 6 was still under revised
by ETL.
Action and Limit (A/L) Levels exceedance
ES05
In the Reporting Period, no exceedance was recorded for construction noise, air quality and water quality monitoring. The summary of
exceedance in the Reporting Period is shown below.
Environmental Aspect |
Monitoring
Parameters |
Action Level |
Limit Level |
Event
& Action |
|||
NOE
Issued |
Investigation
Result |
Project
related exceedance |
Corrective
Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
-- |
-- |
-- |
Turbidity |
0 |
0 |
0 |
-- |
-- |
||
SS |
0 |
0 |
0 |
Environmental
Complaint
ES06
No environmental
complaint was recorded in the Reporting Period.
Notification
of Summons and Successful Prosecutions
ES07
No environmental summons
and prosecutions were recorded in the Reporting Period.
Reporting Change
ES08
No reporting
change was recorded in the Reporting period.
Site Inspection
ES09
The Partial termination proposal for Contract
3 was approved by EPD on 4 May 2021. The site inspection and audit carried out
by the RE, ET and IEC and the Contractor for Contract 3 was ceased after last
site inspection undertaken on 5 May 2021. No non-compliance
was noted during the site inspection.
ES10
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, ET, IEC and the Contractor on 5, 12, 20 and 27 May 2021. No non-compliance was noted during the site inspection.
Future Key Issues
ES11
As wet season is approaching, preventive
measures for muddy water or other water pollutants from site surface flow to local
stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei River or
public area should be properly maintained.
The Contractors should paid special attention on water quality mitigation measures and fully
implement according ISEMM of the EM&A Manual.
ES12
In addition, all
effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent
Discharged into Drainage and Sewerage Systems, inland and Coastal Waters
criteria or discharge permits stipulation.
ES13
Construction noise would be a key
environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.