Job No.: TCS00694/13

 

 

 

 

 

 

 

 

 

Agreement No. CE 45/2008 (CE)

Liantang/ Heung Yuen Wai

Boundary Control Point and Associated Works

 

 

 

 

 

 

 

 

 

Monthly Environmental Monitoring and Audit Report (No.70) ¡V May 2019

 

 

 

 

 

 

 

 

Prepared For

 

 

 

 

Civil Engineering and Development Department (CEDD)

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

17 June 2019

TCS00694/13/600/R2083v2

Nicola Hon

 (Environmental Consultant)

Tam Tak Wing

(Environmental Team Leader)

 

Version

Date

Remarks

1

12 June 2019

First Submission

2

17 June 2019

According to the IEC¡¦s comments on 12 and 14 June 2019

 

 

 

 

 

 


 

 

 

 

 

executive summary

ES01            This is the 70th monthly EM&A report presenting the monitoring results and inspection findings for the reporting period from 1 to 31 May 2019 (hereinafter ¡¥the Reporting Period¡¦).

Environmental Monitoring and Audit Activities

ES02            To facilitate the project management and implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD contract (Contract SS C505).

ES03            In the Reporting Period, the major construction works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project included Contract 2, Contract 3, Contract 4, Contract 6, Contract 7 and Contract SS C505.  Environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the following table.

Environmental Aspect

Environmental Monitoring Parameters / Inspection

Reporting Period

Number of Monitoring Locations to undertake

Total Occasions 

Air Quality

1-hour TSP

9

135

24-hour TSP

9

49

Construction Noise

Leq(30min) Daytime

10

40

Water Quality

Water in-situ measurement and/or sampling

WM1 & WM1-C

14 Scheduled & 0 extra

WM2A(a) & WM2A-Cx

14 Scheduled & 0 extra

WM2B & WM2B-C

14 Scheduled & 0 extra (*)

WM3x &WM3-C

14 Scheduled & 0 extra

WM4, WM4-CA &WM4-CB

14 Scheduled & 0 extra

Ecology

Woodland compensation

i)      General Health condition of planted species

ii)     Survival of planted species

9 Quadrats and transect

0

Joint Site Inspection / Audit

IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing

Contract 2

5

Contract 3

5

Contract 4

5

Contract 6

5

Contract 7

5

Contract SS C505 (#)

4

Remark: (#) IEC only joined one (1) event of site inspection for Contract SS C505.

             (*) In whole Reporting Period, water sampling was unable to carry out at WM2B and WM2B-C due to shallow water (water depth under 150mm)  

 

Action and Limit (A/L) Levels exceedance

ES04            In the Reporting Period, no construction noise exceedance and valid noise complaint was recorded. For air quality monitoring, no exceedance of 1-hour and 24-hour TSP was recorded. Furthermore, no exceedance was recorded during water quality monitoring.  The summary of exceedance in the Reporting Period is shown below.

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation Result

Project related exceedance

Corrective Actions

Air Quality

1-hour TSP

0

0

0

--

--

--

24-hour TSP

0

0

0

--

--

--

Construction Noise

Leq(30min) Daytime

0

0

0

--

--

--

Water Quality

DO

0

0

0

--

--

--

Turbidity

0

0

0

Refer to ES.05

The Contractor should fully implement water quality mitigation measure.

SS

0

2

2

ES05            A total of two (2) Limit Level exceedances were recorded during water quality monitoring. The investigation report for exceedance recorded at WM2A on 29&31 May 2019 is still underway by ET and the investigation result will be presented in next Monthly EM&A Report.

Environmental Complaint

ES06            In this Reporting Period, no environmental complaint was received.

Notification of Summons and Successful Prosecutions

ES07            No environmental summons and prosecutions were recorded in the Reporting Period. 

Reporting Change

ES08            The project (except for the BCP building complex) was commenced on 26 May 2019.  In view of the partial commencement of operation to be considered as the same as the commencement of operation for the entire project, all relevant requirements as stipulated in the EP and the approved EIA report (including the EM&A Manual) for the commencement of operation of the Project shall be strictly complied with.  The implementation status of mitigation measures for operation phase in the Reporting Period will be presented in the Report. 

Site Inspection

ES09            In this Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 2 has been carried out by the RE, IEC, ET and the Contractor on 3, 10, 17, 23 and 31 May 2019.  No non-compliance was noted during the site inspection. 

ES10            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 3 has been carried out by the RE, IEC, ET and the Contractor on 2, 9, 16, 22 and 30 May 2019.  No non-compliance was noted during the site inspection. 

ES11            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 4 has been carried out by the RE, IEC, ET and the Contractor on 3, 10, 14, 24 and 31 May 2019.  No non-compliance was noted.  

ES12            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 6 has been carried out by the RE, IEC, ET and the Contractor on 2, 9, 16, 23 and 30 May 2019.  No non-compliance was noted during the site inspection. 

ES13            In the Reporting Period, joint site inspection for Contract 7 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 3, 10, 17, 21 and 31 May 2019.  No non-compliance was noted during the site inspection. 

ES14            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract SS C505 has been carried out by the RE, ET and the Contractor on 8, 15, 22 and 29 May 2019 in which IEC joined the site inspection on 22 May 2019.  No non-compliance was noted during the site inspection.

Future Key Issues

ES15            During wet season, preventive measures for muddy water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei River or public area should be properly maintained.  The Contractors should paid special attention on water quality mitigation measures and fully implement according ISEMM of the EM&A Manual.

ES16            In addition, all effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland and Coastal Waters criteria or discharge permits stipulation.

ES17            Construction noise would be a key environmental issue during construction work of the Project.  Noise mitigation measures such as using quiet plants should be implemented in accordance with the EM&A requirement.

ES18            Since most of construction sites under the Project are located adjacent to villages, the Contractors should fully implement air quality mitigation measures to reduce construction dust emission.

 

 

 

 

 


Table of Contents

1     Introduction   1

1.1            Project Background   1

1.2            Report Structure  1

2     Project Organization and Construction progress  3

2.1            Construction Contract Packaging   3

2.2            Project Organization   5

2.3            Concurrent Projects  7

2.4            Construction Progress  7

2.5            Summary of Environmental Submissions  9

3     Summary of Impact Monitoring Requirements  13

3.1            General  13

3.2            Monitoring Parameters  13

3.3            Monitoring Locations  13

3.4            Monitoring Frequency and Period   15

3.5            Monitoring Equipment  16

3.6            Monitoring Methodology   18

3.7            Equipment Calibration   20

3.8            Derivation of Action/Limit (A/L) Levels  20

3.9            Data Management and Data QA/QC Control  21

4     Air Quality Monitoring   22

4.1            General  22

4.2