Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report
(No.64) ¡V November 2018 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
13 December 2018 |
TCS00694/13/600/R1906v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
10 December 2018 |
First
Submission |
2 |
13 December 2018 |
Amended according to the IEC¡¦s comment on 11 and
13 December 2018 |
|
|
|
executive summary
ES01
This is the 64th monthly EM&A
report presenting the monitoring results and inspection findings for the reporting period from 1 to 30 November 2018 (hereinafter ¡¥the
Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project is
divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03), Contract
6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03
In the Reporting Period, the major
construction works under Liantang/Heung
Yuen Wai Boundary Control Point and Associated Works of the Project
included Contract 2, Contract 3, Contract 4, Contract
6, Contract 7 and Contract SS C505.
Environmental monitoring activities under the EM&A programme in the
Reporting Period are summarized in the following table.
Environmental Aspect |
Environmental Monitoring Parameters /
Inspection |
Reporting Period |
|
Number of Monitoring Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour
TSP |
9 |
147 |
24-hour
TSP |
9 |
45 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
45 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1
& WM1-C |
12 Scheduled & 0 extra |
WM2A(a)
& WM2A-Cx |
12 Scheduled & 5 extra |
||
WM2B
& WM2B-C |
12 Scheduled & 0 extra (*) |
||
WM3x
&WM3-C |
12 Scheduled & 3 extra |
||
WM4,
WM4-CA &WM4-CB |
12 Scheduled & 0 extra |
||
Ecology |
Woodland
compensation i)
General Health condition of planted species ii) Survival
of planted species |
9
Quadrats and transect |
1 |
Joint Site Inspection / Audit |
IEC, ET,
the Contractor and RE joint site Environmental Inspection and Auditing |
Contract
2 |
5 |
Contract
3 |
5 |
||
Contract
4 |
5 |
||
Contract
6 |
5 |
||
Contract
7 |
5 |
||
Contract
SS C505 (#) |
4 |
Remark: (#) IEC only joined one (1) event of site inspection for
Contract SS C505.
(*)
In the whole Reporting Period, water sampling was unable to carry out at WM2B and
WM2B-C due to shallow water (water depth under 150mm)
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no construction noise exceedance
and valid noise complaint was recorded. For air quality monitoring, one (1) Action
Level exceedances of 24-hour TSP was
recorded. Moreover, eleven (11) Limit Level
exceedances were recorded during water
quality monitoring. The summary of
exceedance in the Reporting Period is shown below.
Environmental Aspect |
Monitoring
Parameters |
Action Level |
Limit Level |
Event
& Action |
|||
NOE
Issued |
Investigation
Result |
Project
related exceedance |
Corrective
Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
1 |
0 |
0 |
Not project related |
0 |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
-- |
-- |
-- |
Turbidity |
0 |
5 |
5 |
Refer to ES.06 |
|
The Contractor should fully implement water quality mitigation measure. |
|
SS |
0 |
6 |
6 |
ES05
There was one (1) Action
Level exceedance of 24-hour TSP recorded at Location AM2. Investigation result revealed that the Contractor has implemented dust mitigation
measures to control the dust generated under the Project. It was concluded that the exceedance was related to other dust source such as
frequent road traffic apart from the project and work area owned by other
project without proper maintenance site exit along Lin Ma Hang Road and unlikely due to the works under Contract works.
ES06
A total of eleven
(11) Limit Level
exceedances were recorded during water
quality monitoring. Investigation for cause of water quality exceedances have conducted by
ET. Investigation report revealed that the exceedances recorded at WM2A(a) on 2 November 2018 and WM3x on 17 November 2018 was
not caused by the works under the Project. Investigation report revealed that the
exceedance recorded at WM3x on 10 November was caused to the isolated incident of burst water
pipe which related to the works under Contract 6. Furthermore, the investigation for exceedances recorded at WM2A(a) on 26, 27 and 28 November 2018 are still underway by
ET and the investigation result will be presented in next Monthly EM&A
Report.
Environmental
Complaint
ES07
In this Reporting
Period, one (1) documented environmental
complaint was received from EPD on 19 November 2018 concerning
about the dust impact generated from the demolition work for a temporary bridge
near Kau Lung Hang with insufficient dust control
measures. Remedial action was
undertaken by the Contractor immediately and satisfied by EPD. Follow up investigation
was conducted by ET and it was observed that the situation was improved. Investigation
report for the complaint is underway by ET.
Notification
of Summons and Successful Prosecutions
ES08
No environmental summons
and prosecutions were recorded in the Reporting Period.
Reporting Change
ES09
No reporting changes
were made in the Reporting Period.
ES10
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 2, 9, 16, 23 and 30
November 2018.
No non-compliance was noted during the site inspection.
ES11
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 15, 21 and 29 November
2018. No non-compliance was noted during the site
inspection.
ES12
In the Reporting Period, joint site
inspection to evaluate
the site environmental performance at Contract 4 has been
carried out by the RE, IEC, ET and
the Contractor on 2, 9, 16, 19 and 30
November 2018. No non-compliance was noted.
ES13
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 15, 22 and 29 November
2018. No non-compliance was noted during the site inspection.
ES14
In the Reporting Period, joint site
inspection for Contract 7 to
evaluate the site environmental performance has been carried out by the RE,
IEC, ET and the Contractor on 2, 9, 16, 20 and 30
November 2018. No non-compliance was noted during the site
inspection.
ES15
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, ET and the Contractor on 7, 14, 21 and 28 November
2018 in which IEC joined the site inspection on 28 November
2018. No non-compliance was noted during the site inspection.
Future Key Issues
ES16
During dry season, special attention
should be paid on the potential construction dust impact since most of the construction sites are adjacent
to villages. The Contractor should fully implement the construction dust
mitigation measures as appropriately.
ES17
Preventive measures for muddy water or other water
pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping
Yuen River, Kwan Tei River or public area should be
properly maintained. The Contractors should paid special attention on water
quality mitigation measures and fully implement according ISEMM of the EM&A
Manual, in particular for working areas near Ma Wat Channel and Ping Yuen
River.
ES18
In addition, all
effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent
Discharged into Drainage and Sewerage Systems, inland and Coastal Waters
criteria or discharge permits stipulation.
ES19
Construction noise would be a key
environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
ES20
Since most of construction sites under the
Project are located adjacent to villages, the Contractors should fully
implement air quality mitigation measures to reduce construction dust emission.