Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report
(No.62) ¡V September 2018 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
12 October 2018 |
TCS00694/13/600/R1810v3 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
8 October 2018 |
First
Submission |
2 |
11 October 2018 |
Amended according to the IEC¡¦s comments on 8
October 2018 |
3 |
12 October 2018 |
Amended according to the IEC¡¦s comments on 11
October 2018 |
executive summary
ES01
This is the 62nd monthly EM&A
report presenting the monitoring results and inspection findings for the reporting period from 1 to 30 September 2018 (hereinafter
¡¥the Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project is
divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03), Contract
6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03
In the Reporting Period, the major
construction works under Liantang/Heung
Yuen Wai Boundary Control Point and Associated Works of the Project
included Contract 2, Contract 3, Contract 4, Contract
6, Contract 7 and Contract SS C505.
Environmental monitoring activities under the EM&A programme in the
Reporting Period are summarized in the following table.
Environmental Aspect |
Environmental Monitoring Parameters /
Inspection |
Reporting Period |
|
Number of Monitoring Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour
TSP |
9 |
135 |
24-hour
TSP |
9 |
50 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
40 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1
& WM1-C |
13 Scheduled & 0 extra |
WM2A(a)
& WM2A-Cx |
13 Scheduled & 4 extra |
||
WM2B
& WM2B-C |
13 Scheduled & 0 extra (*) |
||
WM3x
&WM3-C |
13 Scheduled & 0 extra |
||
WM4,
WM4-CA &WM4-CB |
13 Scheduled & 0 extra |
||
Ecology |
Woodland
compensation i)
General Health condition of planted species ii) Survival
of planted species |
9
Quadrats and transect |
0 |
Joint Site Inspection / Audit |
IEC, ET,
the Contractor and RE joint site Environmental Inspection and Auditing |
Contract
2 |
4 |
Contract
3 |
4 |
||
Contract
4 |
4 |
||
Contract
6 |
4 |
||
Contract
7 |
4 |
||
Contract
SS C505 (#) |
4 |
Remark: (#) IEC only joined one (1) event of site inspection for
Contract SS C505.
(*)
In the whole Reporting Period, water sampling was unable to carry out at WM2B and
WM2B-C due to shallow water (water depth under 150mm)
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no air quality and construction noise exceedance and valid noise
complaint was
recorded. For water quality
monitoring, a total of ten (10) Action/ Limit Level exceedances were recorded under the Project. The summary of exceedance in the
Reporting Period is shown below.
Environmental Aspect |
Monitoring
Parameters |
Action Level |
Limit Level |
Event
& Action |
|||
NOE
Issued |
Investigation
Result |
Project
related exceedance |
Corrective
Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
1 |
3 |
4 |
Refer to ES.05 |
The Contractor should fully implement water quality mitigation measure. |
||
SS |
1 |
5 |
6 |
ES05
Investigation
Reports for water quality exceedances have been conducted by ET accordingly.
Investigation report revealed the Contractor had implemented water quality mitigation
measures such as providing tarpaulin sheet for open slope and surface to minimize muddy runoff. It was concluded that the
exceedance recorded at WM2A(a) on 3, 5, 7 and 18
September 2018 were not caused by the works under the Project. Furthermore, the investigation for
exceedances recorded at WM2A(a) on 24 and 27 September
2018 are still underway by ET and the investigation result will be presented in
next Monthly EM&A Report.
Environmental
Complaint
ES06
No environmental complaint
was recorded in the Reporting Period.
Notification of
Summons and Successful Prosecutions
ES07
No environmental summons
and prosecutions were recorded in the Reporting Period.
Reporting Change
ES08
No reporting changes
were made in the Reporting Period.
ES09
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 7, 14, 21 and 28 September
2018.
No non-compliance was noted during the site inspection.
ES10
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 19 and 27 September 2018. No non-compliance was noted during the site
inspection.
ES11
In the Reporting Period, joint site
inspection to evaluate
the site environmental performance at Contract 4 has been
carried out by the RE, IEC, ET and
the Contractor on 7, 14, 21 and 24 September
2018. No non-compliance was noted.
ES12
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 20 and 27 September 2018. No non-compliance was noted during the site inspection.
ES13
In the Reporting Period, joint site
inspection for Contract 7 to
evaluate the site environmental performance has been carried out by the RE,
IEC, ET and the Contractor on 7, 14, 18 and 28 September
2018. No non-compliance was noted during the site
inspection.
ES14
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, ET and the Contractor on 5, 12, 19 and 27 September
2018 in which IEC joined the site inspection on 27 September
2018. No non-compliance was noted during the site
inspection.
Future Key Issues
ES15
During rainy season, preventive measures for muddy
water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei River or public area should be properly maintained. The Contractors should paid special attention on water
quality mitigation measures and fully implement according ISEMM of the EM&A
Manual, in particular for working areas near Ma Wat Channel and Ping Yuen
River.
ES16
In addition, all effluent
discharge shall be ensure to fulfill Technical Memorandum of Effluent
Discharged into Drainage and Sewerage Systems, inland and Coastal Waters
criteria or discharge permits stipulation.
ES17
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using quiet plants should be implemented in
accordance with the EM&A requirement.
ES18
Since most of construction sites under the Project are
located adjacent to villages, the Contractors should fully
implement air quality mitigation measures to reduce construction dust emission.