Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report
(No.61) ¡V August 2018 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
13 September 2018 |
TCS00694/13/600/R1780v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
10 September 2018 |
First Submission |
2 |
13 September 2018 |
Amended against IEC¡¦s comment on 11 and 13 September
2018 |
|
|
|
executive summary
ES01
This is the 61st monthly EM&A
report presenting the monitoring results and inspection findings for the reporting period from 1 to 31 August 2018 (hereinafter ¡¥the
Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project is divided
to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03),
Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD contract
(Contract SS C505).
ES03
In the Reporting Period, the major
construction works under Liantang/Heung
Yuen Wai Boundary Control Point and Associated Works of the Project
included Contract 2, Contract 3, Contract 4, Contract
6, Contract 7 and Contract SS C505.
Environmental monitoring activities under the EM&A programme in the
Reporting Period are summarized in the following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
147 |
24-hour TSP |
9 |
45 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
45 |
Water Quality |
Water in-situ
measurement and/or sampling |
WM1 & WM1-C |
13 Scheduled & 2 extra |
WM2A(a) & WM2A-Cx |
13 Scheduled & 5 extra |
||
WM2B & WM2B-C |
13 Scheduled & 0 extra (*) |
||
WM3x &WM3-C |
13 Scheduled & 3 extra |
||
WM4, WM4-CA &WM4-CB |
13 Scheduled & 2 extra |
||
Ecology |
Woodland compensation i) General Health condition of planted species ii) Survival of planted species |
9 Quadrats and transect |
1 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site
Environmental Inspection and Auditing |
Contract 2 |
5 |
Contract 3 |
5 |
||
Contract 4 |
5 |
||
Contract 6 |
5 |
||
Contract 7 |
5 |
||
Contract SS C505 (#) |
5 |
Remark: (#) IEC only joined one (1) event of site inspection for
Contract SS C505.
(*)
In the whole Reporting Period, water sampling was unable to carry out at WM2B and
WM2B-C due to shallow water (water depth under 150mm)
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no air quality and construction noise exceedance and valid noise
complaint was
recorded. For water quality
monitoring, a total of thirty (30)
Action/ Limit Level exceedances were
recorded under the Project. The
summary of exceedance in the Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
|||
NOE Issued |
Investigation Result |
Project related exceedance |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
0 |
16 |
16 |
Refer to ES.05 |
The Contractor should fully implement water quality mitigation measure. |
||
SS |
1 |
13 |
14 |
ES05
Investigation
Reports for water quality exceedances have been conducted by ET
accordingly. Investigation results
revealed that the Contractor had properly implemented water quality mitigation
measures such as well-maintained the wastewater treatment facility and covered
the expose area with impervious sheet.
It was concluded that all exceedances recorded at WM3x and the
exceedances recorded at WM1 on 10 August 2018 were not caused by the works
under the Project. However, there
were 5 AL/ LL exceedances recorded at WM4 concluded as partially related to the
work under Contract 2 while the Contractor has promptly rectified the
deficiency. Furthermore, the
investigation for exceedances recorded at WM2A(a) during 22 to 31 August 2018
and recorded at WM1 on 30 August 2018 are still underway by ET and the investigation
result will be presented in next Monthly EM&A Report.
Environmental
Complaint
ES06
In this Reporting Period, one
environmental complaint was recorded related to works under contract 6. The IR revealed that some deficiencies
at site exit was observed, however, the Contractor has promptly rectified the deficiencies and
provided remedial action to response the complaint. Besides, no environmental summons and prosecution were
received under the EM&A programme.
Notification of
Summons and Successful Prosecutions
ES07
No environmental
summons and prosecutions were recorded in the Reporting Period.
Reporting Change
ES08
No reporting
changes were made in the Reporting Period.
ES09
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 3, 10, 17, 24 and
31 August 2018.
No non-compliance was noted during the site inspection.
ES10
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 2, 9, 15, 23 and 30 August 2018. No non-compliance was noted during the site
inspection.
ES11
In the Reporting Period, joint site
inspection to evaluate
the site environmental performance at Contract 4 has been
carried out by the RE, IEC, ET and
the Contractor on 3, 10, 17, 20 and
31 August 2018. No non-compliance was noted.
ES12
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 2, 9, 16, 23 and 30 August 2018. No non-compliance was noted during the site inspection.
ES13
In the Reporting Period, joint site
inspection for Contract 7 to
evaluate the site environmental performance has been carried out by the RE,
IEC, ET and the Contractor on 3, 10, 17, 21 and
31 August 2018. No non-compliance was noted during the site
inspection.
ES14
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, ET and the Contractor on 1, 8, 15, 22 and
29 August 2018 in which IEC joined the site inspection on 22 August
2018. No non-compliance was noted during the site
inspection.
Future Key Issues
ES15
During rainy season, preventive measures for muddy
water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma
Wat Channel, Ping Yuen River, Kwan Tei River or public area should
be properly maintained. The
Contractors should paid special attention
on water quality mitigation measures and fully implement according ISEMM of the
EM&A Manual, in particular for working areas near Ma Wat Channel and Ping
Yuen River.
ES16
In addition, all effluent
discharge shall be ensure to fulfill Technical Memorandum of Effluent
Discharged into Drainage and Sewerage Systems, inland and Coastal Waters
criteria or discharge permits stipulation.
ES17
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using quiet plants should be implemented in
accordance with the EM&A requirement.