Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
18th Quarterly Environmental Monitoring & Audit Summary Report ¡V (November
2017 to January 2018) |
|
|
||
|
|
Prepared
For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Quality Index |
|||
Date |
Reference No. |
Prepared By |
Certified By |
26 April 2018 |
TCS00694/13/600/R1510v2 |
|
|
Nicola
Hon (Environmental Consultant) |
T.W. Tam (Environmental Team Leader) |
Version |
Date |
Description |
1 |
24 April 2018 |
First
Submission |
2 |
26 April 2018 |
Amended according to the IEC¡¦s comment on 25
April 2018 |
|
|
|
This
report has been prepared by Action-United Environmental Services &
Consulting with all reasonable skill, care and diligence within the terms of
the Agreement with the client, incorporating our General Terms and Conditions
of Business and taking account of the resources devoted to it by agreement
with the client. We disclaim any responsibility to the client and others in
respect of any matters outside the scope of the above. This report is
confidential to the client and we accept no responsibility of whatsoever
nature to third parties to whom this report, or any part thereof, is made
known. Any such party relies upon the report at their own risk. |
Executive Summary
ES.01.
This is the 18th Quarterly
EM&A Summary Report for the ¡§Liantang/Heung Yuen Wai Boundary
Control Point and Associated Works¡¨ under Environmental Permit No. EP-404/2011/D (hereinafter ¡¥¡¥the EP¡¦¡¦), covering the period from 1 November
2017 to 31 January 2018 (hereinafter ¡§Reporting Period¡¨).
Environmental Monitoring and
Audit Activities
ES.02. In the
Reporting Period, the construction works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project included Contract 2, Contract 3, Contract 6, Contract 7 and Contract SS
C505. Environmental monitoring activities under
the EM&A programme in the Reporting Period are summarized in the following
table.
Environmental Aspect |
Monitoring
Parameters / Inspection |
Reporting Period |
|
Monitoring Locations
/ Contracts |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
432 |
24-hour TSP |
9 |
144 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
130 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1 & WM1-C, |
40 scheduled and 0 extra of sampling day |
WM2A & WM2A-Cx |
40 scheduled and 4 extra of sampling day |
||
WM2B & WM2B-C |
(*) 40 Scheduled |
||
WM3 &WM3-C |
40 scheduled and 2 extra of sampling day |
||
WM4, WM4-CA &WM4-CB |
40 scheduled and 6 extra of sampling day |
||
Ecology |
Woodland compensation i) General Health condition of planted species ii) Survival of planted species |
9 Quadrats |
1 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing |
Contract 2 |
13 |
Contract 3 |
13 |
||
Contract 4 |
13 |
||
Contract 6 |
13 |
||
Contract 7 |
13 |
||
Contract SS C505 (#) |
14 |
Note:
Extra monitoring day was due to measurement results exceedance
(#) IEC only joined inspection for Contract SS C505 once per month.
(*) During
the whole reporting period, water sampling was unable to carry out at WM2B and WM2B-C due to shallow
water (water depth under 150mm)
Breaches
of Action/Limit levels
ES.03. In the
Reporting Period, no noise exceedance and
valid noise complaint was registered for construction noise. For air quality, there were
6 Action Level exceedances of 24-hour TSP monitoring results recorded. For water quality monitoring, a total of 26 Action/ Limit Level exceedance were recorded. The summary of exceedance
for the Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
||
NOE Issued |
Investigation |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
24-hour TSP |
6 |
0 |
6 |
Not project related |
NA |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
-- |
-- |
Turbidity |
0 |
13 |
13 |
• 6
numbers of LL
exceedances which
recorded on 6,
11, 15 Dec 17 were related to the insufficient mitigation measures for
Contract 3. • Other
20 numbers of exceedances
were not project related. |
The Contractor
was reminded to implement water quality mitigation measures in accordance
with ISEMM of the EM&A Manual requirements |
|
SS |
1 |
12 |
13 |
ES.04. Investigation Reports for all 24-hour TSP exceedances were completed by
ET which concluded that the exceedances were not project related. According to the observation during site
audit, the Contractor had properly implemented the dust mitigation measures
such as provided water spraying on construction area and site haul road regularly. Moreover, water tanker and road sweeper
were deployed the main road on regular basis to suppress fugitive dust and
remover dirt and debris on road. It
was considered that the exceedances were likely related to the dust impact
from traffic.
ES.05. Investigation Reports for all water quality exceedances were completed by ET.
The investigation result revealed that the LL exceedances on 6, 11, 15 December
2017 were related to the insufficient water quality mitigation measures for
Contract 3 while the other exceedances was not
project-related. As remedial action,
the relevant Contractor had enhanced the water quality mitigation measures such as
covering the exposed area by tarpaulin sheet to minimize muddy runoff and no
project-related exceedance was recorded after the enhancement measures.
Environmental
Complaint
ES.06. In this Reporting Period, four (4) documented environmental complaint was received
regarding the air quality and noise issues under the EM&A Programme. Subsequent joint site inspection was carried
out for complaint investigation and investigation
reports were submitted by ET after reviewed by IEC. The IRs revealed that the Contractors
have properly implemented the mitigation measures and no breaches of EM&A programme was seen.
Further enhancement measures were included and implemented in response
to the complaint.
Notification of Summons and Successful Prosecutions
ES.07. No environmental summons or successful
prosecutions were recorded in the Reporting Period.
Reporting Changes
ES.08. No reporting
changes were made in the Reporting Period.
Future key issues
ES.09. During dry
season, special attention should be paid on the potential construction dust
impact since most of the construction sites are adjacent to villages. The
Contractor should fully implement the construction dust mitigation measures as appropriately.
ES.10. Preventive
measures for muddy water or other water pollutants from site surface flow to local
stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei River or public area should be
properly maintained. The
Contractors should paid special attention on water quality mitigation measures and
fully implement according ISEMM of the EM&A Manual, in particular for
working areas near Ma Wat Channel and Ping Yuen River.
ES.11. In
addition, all effluent discharge shall be ensure to fulfill Technical
Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland
and Coastal Waters criteria or discharge permits stipulation.
ES.12. Construction
noise would be a key environmental issue during construction work of the
Project. Noise mitigation measures
such as using quiet plants should be implemented in accordance with the
EM&A requirement.
Table of Contents
2 Project Organization and
Construction progress
2.1 Construction
Contract Packaging
2.5 Summary of Environmental Submissions
3 Project Organization and
Construction progress
3.4 Monitoring
Frequency and Period
3.8 Derivation
of Action/Limit (A/L) Levels
3.9 Data
Management and Data QA/QC Control
4.2 Summary
of Monitoring Results
5 Construction Noise
Monitoring
5.2 Summary
of Monitoring Results
6.2 Summary
of Monitoring Results
8.2 Records
of Waste Quantities
10 Non-compliance, Complaints,
Notifications of Summons and Prosecutions
10.1 Status
of Non-compliance Environmental Complaint, Summons and Prosecution
11 Implementation Status of Mitigation
Measures
12 Conclusions and Recommendations
List
of tables
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Impact
Monitoring Stations - Air Quality
Table 3-3 Impact
Monitoring Stations - Construction Noise
Table 3-4 Impact
Monitoring Stations - Water Quality
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Construction
Noise Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action
and Limit Levels for Water Quality
Table 4-1 Summary
of Air Quality Monitoring Results
Table 4-2 Summaries
of Breaches of Air Quality A/L Levels
Table 5-1 Summary
of Construction Noise Monitoring Results
Table 5-2 Summaries
of Breaches of Construction Noise A/L Levels
Table 6-1 Summary
of the Water Quality Monitoring Results ¡V Contracts SS C505 & 6
Table 6-2 Summary
of the Water Quality Monitoring Results ¡V Contracts 2 & 3
Table 6-3 Summary
of the Water Quality Monitoring Results ¡V Contract 6
Table 6-4 Summary
of the Water Quality Monitoring Results ¡V Contracts 2 & 6
Table 6-5 Summaries
of Breaches of the Existing Water Quality A/L Levels
Table 6-6 Summary
of Water Quality Exceedance in the Reporting Period
Table 8-1 Summary
of Quantities of Inert C&D Materials
Table 8-2 Summary
of Quantities of C&D Wastes
Table 9-1 Summary
of Reminders/Observations of Site Inspection ¡V Contract 2
Table 9-2 Summary
of Reminders/Observations of Site Inspection ¡V Contract 3
Table 9-3 Summary
of Reminders/Observations of Site Inspection ¡V Contract 6
Table 9-4 Summary
of Reminders/Observations of Site Inspection ¡V Contract SS C505
Table 9-5 Summary
of Reminders/Observations of Site Inspection ¡V Contract 7
Table 9-6 Summary
of Reminders/Observations of Site Inspection ¡V Contract 7
Table 10-1 Statistical
Summary of Environmental Complaints
Table 10-2 Statistical
Summary of Environmental Summons
Table 10-3 Statistical
Summary of Environmental Prosecution
Table 11-1 Environmental
Mitigation Measures
List of Annexes
Appendix A Layout plan of the Project
Appendix B Environmental Management Organization Chart
Appendix C Designated Monitoring Locations as Recommended in the Approved
EM&A Manual
Appendix D Monitoring Locations for Impact Monitoring
Appendix E Event and Action Plan
Appendix F Graphical Plots for Monitoring Result
Appendix G Weather information
Appendix H Waste Flow Table
Appendix I Implementation Schedule for
Environmental Mitigation Measures
1.1.1. Civil Engineering and Development Department is the Project Proponent and the Permit Holder