Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report (No.39)
¡V October 2016 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
11
November 2016 |
TCS00694/13/600/R0714v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
8 November 2016 |
First
Submission |
2 |
11 November 2016 |
Amended according to the IEC¡¦s comments on 10
November 2016 |
|
|
|
executive summary
ES01
This is the 39th monthly EM&A report presenting the monitoring
results and inspection findings for the reporting period from 1 to 31 October 2016
(hereinafter ¡¥the Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project is
divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (TCSS), Contract 5 (CV/2013/03), Contract 6
(CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03
In the Reporting Period, the major construction
activities under Contract 5 have been substantially completed. The construction works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project included Contract 2, Contract 3, Contract 6, Contract 7 and Contract SS
C505. Environmental monitoring activities
under the EM&A programme in the Reporting Period are summarized in the
following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
135 |
24-hour TSP |
9 |
45 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
40 |
Water Quality |
Water in-situ
measurement and/or sampling |
WM1 & WM1-C |
13 Scheduled & 0
extra |
WM2A(a) & WM2A-Cx |
13 Scheduled & 3
extra |
||
WM2B & WM2B-C |
13 Scheduled & 1
extra |
||
WM3x &WM3-C |
13 Scheduled &
2 extra |
||
WM4, WM4-CA &WM4-CB |
13 Scheduled &
3 extra |
||
Ecology |
Woodland compensation i) General Health condition of planted species ii) Survival of planted species |
9 Quadrats |
0 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and
Auditing |
Contract 2 |
3 (#) |
Contract 3 |
5 |
||
Contract 6 |
4 |
||
Contract 7 |
4 |
||
Contract SS C505 |
4 |
Note: Extra monitoring day was due to measurement
results exceedance
(#) Site inspection scheduled on 21 October 2016 was cancelled due to
typhoon signal no. 8
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no air quality
exceedance and construction noise exceedance was registered for the Project. For water quality monitoring, a total of thirty-seven
(37) Limit Level exceedances were recorded. The summary of exceedance in the
Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
|||
NOE Issued |
Investigation Result |
Project related exceedance |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
0 |
17 |
17 |
All exceedances on 4 to 18 Oct were not project
related, except for exceedances at WM2A(a) on 4 Oct were due to damage pipe
under C6 Exceedances on 19 to 31 Oct at WM2A are under
investigation. |
1 (#) |
The Contractors were reminded to implement water quality mitigation measures
in accordance with ISEMM of the EM&A Manual requirements |
|
SS |
0 |
20 |
20 |
1 (*) |
(#) 6 number of NUT exceedances at WM2A(a) are under investigated by ET.
(*) 7 number of SS exceedances at WM2A(a) are under investigated by ET.
Environmental Complaint
ES05
In
this Reporting Period, two
(2) documented environmental
complaints were received. One of the complaints was about transportation of dusty construction
waste material under Contract 6 and
another complaint was about
wastewater discharge from construction site near the works areas of Contracts 2
and 6. The summary of complaint received in the Reporting Period
is shown below.
Reporting Period |
Contract No |
Environmental Complaint |
||
Frequency |
Complaint Nature |
Project related complaint |
||
1 ¡V 31 Oct 2016 |
Contract 2 |
1 |
Wastewater
(1) |
0 |
Contract 3 |
0 |
NA |
0 |
|
Contract 6 |
2 |
Wastewater
(1) Dust (1) |
1 (Dust) |
|
Contract 7 |
0 |
NA |
0 |
|
SS C505 |
0 |
NA |
0 |
Notification of Summons and Successful Prosecutions
ES06
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
ES07
In the Reporting period, no reporting changes
were made.
ES08
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 7, 14 and 28 October 2016 in which the site inspection scheduled on 21
October 2016 was cancelled due to typhoon signal no. 8. No non-compliance was noted during the
site inspection.
ES09
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 3, 11, 19, 24 and 31 October 2016. No non-compliance was noted during the site
inspection.
ES10
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 20 and 27 October 2016. No non-compliance
was noted during the site inspection.
ES11
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, IEC, ET and the Contractor on 4, 12, 19 and 26 October 2016. No non-compliance was noted during the site
inspection.
ES12
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
7 has been carried out by the RE, IEC, ET and the Contractor on 4, 11, 18 and 25 October 2016. No non-compliance
was noted during the site inspection.
Future Key Issues
ES13
During dry season,
special attention should be paid on the potential construction dust impact
since most of the construction sites
are adjacent to villages. The Contractor should fully implement the
construction dust mitigation measures.
ES14
Preventive measures for muddy water or other water
pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma
Wat Channel, Ping Yuen River or public area should be properly maintained. The Contractors should paid special
attention on water quality
mitigation measures and fully implement according ISEMM of the EM&A Manual,
in particular for working areas near Ma Wat Channel and Ping Yuen River.
Moreover, all effluent discharge shall be ensure to fulfill Technical
Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland
and Coastal Waters criteria or discharge permits stipulation.
ES15
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using quiet
plants should be implemented in accordance with the EM&A requirement.
Table of Contents
2 Project
Organization and Construction progress
2.1 Construction
Contract Packaging
2.5 Summary of Environmental Submissions
3 Summary
of Impact Monitoring Requirements
3.4 Monitoring
Frequency and Period
3.8 Derivation
of Action/Limit (A/L) Levels
3.9 Data
Management and Data QA/QC Control
4.2 Air
Quality Monitoring Results
5 Construction
Noise Monitoring
5.2 Noise
Monitoring Results (normal daytime)
5.3 Noise
Monitoring Results (Restricted Hours)
6.2 Results
of Water Quality Monitoring
8.2 Records
of Waste Quantities
9.2 Findings
/ Deficiencies During the Reporting Month
10 Environmental
Complaint and Non-Compliance
10.1 Environmental
Complaint, Summons and Prosecution
11 Implementation
Status of Mitigation Measures
11.2 Tentative
Construction Activities in the Coming Month
11.3 Key
Issues for the Coming Month
12 Conclusions
and Recommendations
List
of TABLES
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Impact
Monitoring Stations - Air Quality
Table 3-3 Impact
Monitoring Stations - Construction Noise
Table 3-4 Impact
Monitoring Stations - Water Quality
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Construction
Noise Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action and Limit
Levels for Water Quality
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1a
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM4B
Table 4-5 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM5a
Table 4-6 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM6
Table 4-7 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM7a
Table 4-8 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM8
Table 4-9 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Table 5-1 Summary
of Construction Noise Monitoring Results
Table 5-2 Summary
of Construction Noise Monitoring Results
Table 5-3 Summary
of Construction Noise Monitoring Results (Evening Time)
Table 5-4 Summary
of Construction Noise Monitoring Results (Night Time)
Table 6-1 Summary
of Water Quality Monitoring Results for Contract 2 and 3
Table 6-2 Summary
of Water Quality Monitoring Results for Contract 5 and SS C505
Table 6-3 Summary
of Water Quality Monitoring Results for Contract 6
Table 6-4 Summary
of Water Quality Monitoring Results for Contract 2 and 6
Table 6-5 Action
and Limit (A/L) Levels Exceedance Recorded
Table 6-6 Summary
of Water Quality Exceedance in the Reporting Period
Table 8-1 Summary
of Quantities of Inert C&D Materials
Table 8-2 Summary
of Quantities of C&D Wastes
Table 9-1 Site
Observations for Contract 2
Table 9-2 Site
Observations for Contract 3
Table 9-3 Site Observations
for Contract 6
Table 9-4 Site
Observations for Contract SS C505
Table 9-5 Site
Observations for Contract 7
Table 10-1 Statistical
Summary of Environmental Complaints
Table 10-2 Statistical
Summary of Environmental Summons
Table 10-3 Statistical
Summary of Environmental Prosecution
Table 11-1 Environmental
Mitigation Measures
List of Appendices
Appendix
A Layout Plan of the
Project
Appendix
B Organization Chart
Appendix
C 3-month rolling
construction program
Appendix
D Designated
Monitoring Locations as Recommended in the Approved EM&A Manual
Appendix
E Monitoring
Locations for Impact Monitoring
Appendix
F Calibration
Certificate of Monitoring Equipment and HOKLAS-accreditation Certificate of the
Testing Laboratory
Appendix
G Event and Action
Plan
Appendix
H Impact Monitoring
Schedule
Appendix
I Database of
Monitoring Result
Appendix
J Graphical
Plots for Monitoring Result
Appendix
K Meteorological
Data
Appendix
L Waste Flow Table
Appendix
M Implementation Schedule
for Environmental Mitigation Measures
Appendix
N Investigation
Report for Exceedance
1.1.1
Civil Engineering and Development Department is the Project Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE)
Liantang / Heung Yuen Wai Boundary Control Point and Associated Works, which is
a Designated Project to be implemented under Environmental Permit number EP-404/2011/C granted on 12 March
2015.
1.1.2
The Project consists of two main components: Construction of a Boundary
Control Point (hereinafter referred as ¡§BCP¡¨); and Construction of a connecting
road alignment. Layout plan of the Project is shown in Appendix A.
1.1.3
The proposed BCP is located at the boundary with Shenzhen near the
existing Chuk Yuen Village, comprising a main passenger building with passenger
and cargo processing facilities and the associated customs, transport and
ancillary facilities. The
connecting road alignment consists of six main sections:
1)
Lin Ma Hang to Frontier Closed Area (FCA) Boundary ¡V this section
comprises at-grade and viaducts and includes the improvement works at Lin Ma
Hang Road;
2)
Ping Yeung to Wo Keng Shan ¡V this section
stretches from the Frontier Closed Area Boundary to the tunnel portal at Cheung
Shan and comprises at-grade and viaducts including an interchange at Ping
Yeung;
3)
North Tunnel ¡V this section comprises the tunnel segment at Cheung Shan
and includes a ventilation building at the portals on either end of the tunnel;
4)
Sha Tau Kok Road ¡V this section stretches from the tunnel portal at Wo Keng Shan to the tunnel portal south of Loi Tung and
comprises at-grade and viaducts including an interchange at Sha Tau Kok and an
administration building;
5)
South Tunnel ¡V this section comprises a tunnel segment that stretches from
Loi Tung to Fanling and includes a ventilation building at the portals on
either end of the tunnel as well as a ventilation building in the middle of the
tunnel near Lau Shui Heung;
6)
Fanling ¡V this section comprises the at-grade, viaducts and interchange
connection to the existing Fanling Highway.
1.1.4
Action-United
Environmental Services & Consulting has
been commissioned as an Independent ET to implement the relevant
EM&A program in accordance with the
approved EM&A Manual, as well as the associated duties. As part of the EM&A program, the
baseline monitoring has carried out between 13 June 2013 and 12 July
2013 for all parameters including air quality, noise and water quality
before construction work commencement.
The Baseline Monitoring Report summarized the key findings and the
rationale behind determining a set of Action and Limit Levels (A/L Levels) from
the baseline data. Also, the
Project baseline monitoring report which verified by the IEC has been submitted
to EPD on 16 July 2013 for endorsement. The major construction works of the
Project was commenced on 16 August 2013
in accordance with the EP Section 5.3 stipulation.
1.1.5
This is 39th
monthly EM&A report presenting the monitoring results and
inspection findings for reporting period from 1 to 31 October 2016.
1.2.1
The Monthly Environmental Monitoring and
Audit (EM&A) Report is structured into the following sections:-
Section 1 Introduction
Section 2 Project
Organization and Construction Progress
Section 3 Summary
of Impact Monitoring Requirements
Section 4 Air
Quality Monitoring
Section 5 Construction
Noise Monitoring
Section 6 Water
Quality Monitoring
Section 7 Waste
Management
Section 8 Site
Inspections
Section 9 Environmental
Complaints and Non-Compliance
Section 10 Implementation
Status of Mitigation Measures
Section 11 Conclusions
and Recommendations
2.1.1
To facilitate the project management and
implementation, the Project would be divided by the following contracts:
¡P
Contract 2 (CV/2012/08)
¡P
Contract 3 (CV/2012/09)
¡P
Contract 4 (NE/2014/02)
¡P
Contract 5 (CV/2013/03)
¡P
Contract 6 (CV/2013/08)
¡P
Contract 7 (NE/2014/03)
¡P
ArchSD Contract No. SS C505
2.1.2
The
details of each contracts is summarized below and the delineation of each contracts is shown in Appendix
A.
Contract 2 (CV/2012/08)
2.1.3
Contract 2 has awarded in December 2013 and
construction work was commenced on 19 May 2014. Major Scope of Work of the Contract 2 is
listed below:
¡P
construction of
an approximately 5.2km long dual two-lane connecting road (with about 0.4km of
at-grade road and 4.8km of tunnel) connecting the Fanling Interchange with the
proposed Sha Tau Kok Interchange;
¡P
construction of a
ventilation adit tunnel and the mid-ventilation
building;
¡P
construction of
the north and south portal buildings of the Lung Shan Tunnel and their
associated slope works;
¡P
provision and
installation of ventilation system, E&M works and building services works
for Lung Shan tunnel and Cheung Shan tunnel and their portal buildings;
¡P
construction of
Tunnel Administration Building adjacent to Wo Keng
Shan Road and the associated E&M and building services works; and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 3 (CV/2012/09)
2.1.4
Contract 3 was awarded in July 2013 and
construction work was commenced on 5 November 2013. Major Scope of Work of the Contract 3 is
listed below:
¡P
construction of
four link roads connecting the existing Fanling Highway and the south portal of
the Lung Shan Tunnel;
¡P
realignment of
the existing Tai Wo Service Road West and Tai Wo Service Road East;
¡P
widening of the
existing Fanling Highway (HyD¡¦s
entrustment works);
¡P
demolishing
existing Kiu Tau vehicular bridge and Kiu Tau footbridge and reconstruction of
the existing Kiu Tau Footbridge (HyD¡¦s entrustment
works); and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 4 (NE/2014/02)
2.1.5
Contract
4 has awarded in mid-April 2016. However, the major construction work still is not
yet commenced. The scope of work
of the Contract 4 includes:
¡P
design,
supply, delivery, installation, testing and commissioning of a traffic control
and surveillance system for the connecting road linking up the Liantang / Heung
Yuen Wai Boundary Control Point and the existing Fanling Highway.
Contract 5 (CV/2013/03)
2.1.6
Contract 5 has awarded in April 2013 and construction
work was commenced in August 2013.
Major Scope of Work of the Contract 5 is listed below:
¡P
site formation of about 23
hectares of land for the development of the BCP;
¡P
construction of an
approximately 1.6 km long perimeter road at the BCP including a 175m long
depressed road;
¡P
associated
diversion/modification works at existing local roads and junctions including
Lin Ma Hang Road;
¡P
construction of pedestrian
subway linking the BCP to Lin Ma Hang Road;
¡P
provision of resite area with supporting infrastructure for reprovisioning of the affected village houses; and
¡P
construction of associated footpath, slopes, retaining structures, drainage,
sewerage, waterworks, landscaping works and other ancillary works.
Contract 6 (CV/2013/08)
2.1.7
Contract 6 has awarded in June 2015 and
construction work was commenced on 23 October 2015. Major Scope of Work of the Contract 6 would
be included below:
construction of an approximately 4.6km long dual two-lane connecting
road (with about 0.6km of at-grade road, 3.3km of viaduct and 0.7km of tunnel)
connecting the BCP with the proposed Sha Tau Kok Road Interchange and the
associated ventilation buildings;
associated diversion/modification works at access roads to the resite of Chuk Yuen Village;
provision of sewage collection, treatment and disposal facilities for
the BCP and the resite of Chuk
Yuen Village;
construction of a pedestrian subway linking the BCP to Lin Ma Hang
Road;
provisioning of the affected facilities including Wo Keng Shan Road garden; and
construction of associated footpath, slopes, retaining
structures, drainage, sewerage, waterworks, landscaping works and other
ancillary works.
Contract 7 (NE/2014/03)
2.1.8
Contract 7 has awarded in December 2015 and
the construction works of Contract 7 was commenced on 15 February 2016. Major Scope of Work of the Contract 7 would
be included below:
construction of the Hong Kong Special
Administrative Region (HKSAR) portion of four vehicular bridge
construction of one pedestrian bridge crossing Shenzhen (SZ) River
(cross boundary bridges)
ArchSD Contract No. SS C505
2.1.9
SS C505 has awarded in July 2015 and
construction work was commenced on 1 September 2015. Major Scope of Work of the SS C505 would
be included below:
passenger-related facilities including
processing kiosks and examination facilities for private cars and coaches, passenger
clearance building and halls, the interior fitting works for the pedestrian
bridge crossing Shenzhen River, etc.;
cargo processing facilities including kiosks
for clearance of goods vehicles, customs inspection platforms, X-ray building,
etc.;
accommodation for the facilities inside of the
Government departments providing services in connection with the BCP;
transport-related facilities inside the BCP
including road networks, public transport interchange, transport drop-off and
pick-up areas, vehicle holding areas and associated road furniture etc;
a public carpark; and
other ancillary
facilities such as sewerage and drainage, building services provisions and
electronic systems, associated environmental mitigation measure and landscape
works.
2.2.1
The project organization is shown in Appendix
B. The responsibilities of
respective parties are:
Civil
Engineering and Development Department (CEDD)
2.2.2
CEDD is the Project Proponent and the Permit Holder of the EP of the development
of the Project and will assume overall responsibility for the project. An
Independent Environmental Checker (IEC) shall be employed by CEDD to audit the
results of the EM&A works carried out by the ET.
Architectural
Services Department (ArchSD)
2.2.3
ArchSD acts as the works agent for
Development Bureau (DEVB), for Contract SS C505 Liantang/ Heung Yuen Wai
Boundary Control Point (BCP) ¡V BCP Buildings and Associated Facilities.
Environmental
Protection Department (EPD)
2.2.4
EPD is the statutory enforcement body for
environmental protection matters in Hong Kong.
Ronald Lu
& Partners (Hong Kong) Ltd (The Architect)
2.2.5
Ronald Lu & Partners (Hong Kong) Ltd is
appointed by ArchSD as an Architect for Contract SS C505 Liantang/ Heung Yuen
Wai Boundary Control Point (BCP) ¡V BCP Buildings and Associated
Facilities. It responsible for
overseeing the construction works of Contract SS C505 and for ensuring that the
works are undertaken by the Contractor in accordance with the specification and
contract requirements. The duties and responsibilities of the Architect with
respect to EM&A are:
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the
environmental mitigation measures and their effectiveness
Monitor Contractors¡¦ and ET¡¦s compliance with
the requirements in the Environmental Permit (EP) and EM&A Manual
Facilitate ET¡¦s implementation of the EM&A
programme
Participate in joint site inspection by the ET
and IEC
Oversee the implementation of the agreed Event
/ Action Plan in the event of any exceedance
Adhere to the procedures for carrying out
complaint investigation
Liaison with DSD, Engineer/Engineer¡¦s
Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s
Regulation of Shenzhen River Stage 4 (RSR 4)¡¨ Project discussing regarding the
cumulative impact issues.
Engineer
or Engineers Representative (ER)
2.2.6
The ER is responsible for overseeing the
construction works and for ensuring that the works are undertaken by the
Contractor in accordance with the specification and contract requirements. The
duties and responsibilities of the ER with respect to EM&A are:
¡P
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the
environmental mitigation measures and their effectiveness
¡P
Monitor Contractors¡¦s,
ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental Permit
(EP) and EM&A Manual
¡P
Facilitate ET¡¦s implementation of the
EM&A programme
¡P
Participate in joint site inspection by the
ET and IEC
¡P
Oversee the implementation of the agreed
Event / Action Plan in the event of any exceedance
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with DSD, Engineer/Engineer¡¦s
Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s Regulaiton of Shenzhen River Stage 4 (RSR 4)¡¨ Project
discussing regarding the cumulative impact issues.
The
Contractor(s)
2.2.7
There will be one contractor for each
individual works contract. Once the contractors are appointed, EPD, ET and IEC
will be notified the details of the contractor.
2.2.8
The Contractor for Contracts under CEDD
should report to the ER. For ArchSD Contract, the Contractor should report to
the Architect or Architect¡¦s Representative (AR). The duties and
responsibilities of the Contractor are:
¡P
Comply with the relevant contract conditions
and specifications on environmental protection
¡P
Employ an Environmental Team (ET) to
undertake monitoring, laboratory analysis and reporting of EM &A Facilitate
ET¡¦s monitoring and site inspection activities
¡P
Participate in the site inspections by the ET
and IEC, and undertake any corrective actions
¡P
Provide information / advice to the ET
regarding works programme and activities which may contribute to the generation
of adverse environmental impacts
¡P
Submit proposals on mitigation measures in
case of exceedances of Action and Limit levels in accordance with the Event /
Action Plans
¡P
Implement measures to reduce impact where
Action and Limit levels are exceeded
¡P
Adhere to the procedures for carrying out
complaint investigation
Environmental Team (ET)
2.2.9
Once the ET is appointed, the EPD, CEDD, ER, Architect
and IEC will be notified the details of the ET.
2.2.10
The ET shall not be in any way an associated
body of the Contractor(s), and shall be employed by the Project
Proponent/Contractor to conduct the EM&A programme. The ET should be managed by the ET
Leader. The ET Leader shall be a person who has at least 7 years¡¦ experience in
EM&A and has relevant professional qualifications. Suitably qualified staff
should be included in the ET, and resources for the implementation of the
EM&A programme should be allocated in time under the Contract(s), to enable
fulfillment of the Project¡¦s EM&A requirements as specified in the EM&A
Manual during construction of the Project. The ET shall report to the Project
Proponent and the duties shall include:
¡P
Monitor and audit various environmental
parameters as required in this EM&A Manual
¡P
Analyse the
environmental monitoring and audit data, review the success of EM&A
programme and the adequacy of mitigation measures implemented, confirm the
validity of the EIA predictions and identify any adverse environmental impacts
arising
¡P
Carry out regular site inspection to
investigate and audit the Contractors¡¦ site practice, equipment/plant and work
methodologies with respect to pollution control and environmental mitigation,
and effect proactive action to pre-empt problems
¡P
Monitor compliance with conditions in the EP,
environmental protection, pollution prevention and control regulations and
contract specifications
¡P
Audit environmental conditions on site
¡P
Report on the environmental monitoring and
audit results to EPD, the ER, the Architect, the lEC
and Contractor or their delegated representatives
¡P
Recommend suitable mitigation measures to the
Contractor in the case of exceedance of Action and Limit levels in accordance
with the Event and Action Plans
¡P
Liaise with the IEC on all environmental
performance matters and timely submit all relevant EM&A proforma
for approval by IEC
¡P
Advise the Contractor(s) on environmental
improvement, awareness, enhancement measures etc., on site
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, ET, lEC and the
Contractor(s) of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
Independent Environmental Checker (IEC)
2.2.11
One IEC will be employed for this Project.
Once the IEC is appointed, EPD, ER, the Architect and ET will be notified the
details of the IEC.
2.2.12
The Independent Environmental Checker (IEC)
should not be in any way an associated body of the Contractor or the ET for the
Project. The IEC should be employed by the Permit Holder (i.e., CEDD) prior to
the commencement of the construction of the Project. The IEC should have at
least 10 years¡¦ experience in EM&A and have relevant professional
qualifications. The appointment of IEC should be subject to the approval of
EPD. The IEC should:
¡P
Provide proactive advice to the ER and the
Project Proponent on EM&A matters related to the project, independent from
the management of construction works, but empowered to audit the environmental
performance of construction
¡P
Review and audit all aspects of the EM&A
programme implemented by the ET
¡P
Review and verify the monitoring data and all
submissions in connection with the EP and EM&A Manual submitted by the ET
¡P
Arrange and conduct regular, at least monthly
site inspections of the works during construction phase, and ad hoc inspections
if significant environmental problems are identified
¡P
Check compliance with the agreed Event /
Action Plan in the event of any exceedance
¡P
Check compliance with the procedures for
carrying out complaint investigation
¡P
Check the effectiveness of corrective
measures
¡P
Feedback audit results to ET by signing off
relevant EM&A proforma
¡P
Check that the mitigation measures are
effectively implemented
¡P
Verify the log-book(s) mentioned in Condition
2.2 of the EP, notify the Director by fax, within one working day of receipt of
notification from the ET Leader of each and every occurrence, change of
circumstances or non-compliance with the EIA Report and/or the EP, which might
affect the monitoring or control of adverse environmental impacts from the
Project
¡P
Report the works conducted, the findings,
recommendation and improvement of the site inspections, after reviewing ET¡¦s
and Contractor¡¦s works, and advices to the ER and Project Proponent on a
monthly basis
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, the Architect, ET, lEC
and the Contractor of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
2.3.1
The concurrent construction works that may be
carried out include, but not limited to, the following:
(a)
Regulation of Shenzhen River Stage IV;
(b)
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange ¡V Contract No. HY/2012/06;
(c)
Construction of BCP
facilities in Shenzhen.
2.4.1
In the Reporting Period, the major
construction activity conducted under the Project is located in Contracts 2, 3,
6, 7 and SS C505 and they are summarized in below. Moreover, 3-month rolling construction
program for all the current contracts is enclosed in Appendix C.
Contract 2 (CV/2012/08)
2.4.2
The
contract commenced in May 2014. In this Reporting Period, construction
activities conducted are listed below:
Mid-Vent
Portal |
Stud
tunnel and cavern excavation Adit invert slab,
waterproofing and lining Ventilation
building superstructure and backfilling |
North Portal |
Slope
stabilization and retaining wall Southbound
Tunnel Boring Machine (TBM) excavation Northbound
bench excavation Tunnel
enlargement and construction of cross passage Tunnel
internal structure and cross passage ventilation
building foundation |
South Portal |
Southbound and northbound
Drill Blast Excavation
South ventilation and building
superstructure
Tunnel invert, waterproofing
and lining |
Admin
Building |
Building
superstructure and external wall |
Contract 3 (CV/2012/09)
2.4.3
The Contract commenced in November 2013. In this Reporting Period, construction
activities conducted are listed below:
Boundary
wall for pumping station
Cable
detection and trial trenches
Construction
of remaining slab of Box Culvert ID05
Demolition
of Valve Control House
Footbridge
construction
Gabion
wall construction
Re-provisioning
of Kiu Tau Footbridge
Storm
drains laying
Noise
barrier construction
Pier /
pier table construction
Pile
cap works
Portal
beam construction
Retaining
wall construction
Road
works
Sewer
works
Slope
reinstatement works near Bridge E
Utilities
Duct Laying
Water
Main Laying
Viaduct
segment erection
Contract 4 (Contract number to be assigned)
2.4.4
The
Contract was awarded in mid-April 2016 and the major construction work has not yet
commenced.
Contract 5 (CV/2013/03)
2.4.5
As advised by the ER, the construction works
under Contract 5 was substantially completed on 31 August 2016.
Contract 6 (CV/2013/08)
2.4.6
Contract 6 has awarded in June 2015 and
construction work was commenced on 23 October 2015. In this Reporting Period, construction
activities conducted are listed below:
Slope
Works
Bored
Piling
Pile
Cap Construction
Bridge
Pier Construction
Bridge
Segment Erection
Tunnel
Excavation
Sewage
Treatment Plant Construction
Contract 7 (NE/2014/03)
2.4.7
Contract 7 has awarded in December 2015 and
construction work was commenced on 15 February 2016. In this Reporting Period, construction
activities conducted are listed below:
Piling Works at Bridges A
and E
Pile Caps Construction at
Bridges B, C and D
Column construction at
Bridge C
Contract SS C505
2.4.8
Contract SS C505 has awarded in July 2015 and
construction work was commenced on 1 September 2015. In this Reporting Period, construction
activities conducted are listed below:
General Site Set-up
Building no.4, 5, 6, 7,
9, 10, 11 and 36 construction
Excavation waterproofing
works for Building no. 4, 6 & 11
Pile cap construction for
Building no.4,6&7
Tower crane operation
Bridge construction works
including construction of bridge column, retaining wall, pile cap and pier
Underground drainage
works
Prototype ¡§A¡¨ & ¡§B¡¨
construction works
Mock up for south
entrance double curve cladding
Formwork and falsework
for PTB¡¦s slab construction
Construction PTB M/F
& 1/F flat slab
Steel beam works for
maintenance platform for PTB
Pile cap construction for
PTB, including excavation and backfilling works
Bridge deck construction
for Bridges 1 - 5
Footing construction
2.5.1
In according to the EP, the required documents
have submitted to EPD which listed in below:
Project Layout Plans of Contracts 2, 3, 5, 6, 7 and SS C505
Landscape Plan
Topsoil Management Plan
Environmental Monitoring and Audit Programme
Baseline Monitoring Report (TCS00690/13/600/R0030v3) for the Project
Waste Management Plan of the Contracts 2, 3, 5,
6, 7 and SS C505
Contamination Assessment Plan (CAP) and
Contamination Assessment Report (CAR) for Po Kat Tsai, Loi Tung and the
workshops in Fanling
Vegetation Survey Report
Woodland Compensation Plan
Habitat Creation Management Plan
Wetland Compensation Plan
2.5.2
Summary of
the relevant permits, licenses, and/or notifications on environmental
protection for the Project of each contracts are presented in Table 2-1.
Table 2-1 Status of Environmental Licenses
and Permits of the Contracts
Item |
Description |
License/Permit Status |
||||
Ref. no. |
Effective Date |
Expiry Date |
||||
Contract 2 |
||||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref No.: 368864 |
31 Dec 2013 |
Till Contract ends |
||
2 |
Chemical Waste Producer Registration |
North Portal Waste
Producers Number: No.5213-652-D2523-01 |
25 Mar 2014 |
Till Contract ends |
||
Mid-Vent Portal Waste
Producers Number: No.5213-634-D2524-01 |
25 Mar 2014 |
Till Contract ends |
||||
South Portal Waste
Producers Number: No.5213-634-D2526-01 |
9 Apr 2014 |
Till Contract ends |
||||
3 |
Water Pollution Control Ordinance - Discharge License |
No.WT00018374-2014 |
8 Oct 2014 |
30 Sep 2019 |
||
No.: W5/1I389 |
28 Mar 2014 |
31 Mar 2019 |
||||
No. WT00023063-2015 |
18 Dec 2015 |
31 Mar 2019 |
||||
No.: W5/1I392 |
28 Mar 2014 |
31 Mar 2019 |
||||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7019105 |
8 Jan 2014 |
Till Contract ends |
||
5 |
Construction
Noise Permit |
GW-RN0457-16 |
22 Jun 2016 |
14 Dec 2016 |
||
GW-RN0435-16 |
27 Jun 2016 |
26 Dec 2016 |
||||
GW-RN0519-16 |
1 Aug 2016 |
30 Oct 2016 |
||||
GW-RN0543-16 |
18 Jul 2016 |
13 Jan 2017 |
||||
GW-RN0582-16 |
09 Aug 2016 |
08 Nov 2016 |
||||
GW-RN0590-16 |
09 Aug 2016 |
08 Nov 2016 |
||||
GW-RN0579-16 |
11 Aug 2016 |
07 Jan 2017 |
||||
GW-RN0604-16 |
11 Aug 2016 |
07 Jan 2017 |
||||
GW-RN0695-16 |
18 Sep 2016 |
17 Mar 2017 |
||||
GW-RN0700-16 |
20 Sep 2016 |
19 Feb 2017 |
||||
GW-RN0759-16 |
12 Oct 2016 |
11 Apr 2017 |
||||
GW-RN0780-16 |
27 Oct 2016 |
26 Dec 2016 |
||||
GW-RN0788-16 |
27 Oct 2016 |
26 Dec 2016 |
||||
6 |
Specified Process License (Mortar
Plant Operation) |
L-3-251(1) |
12-Apr-2016 |
11-Apr-2021 |
||
Contract 3 |
||||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 362101 |
17 Jul 2013 |
Till Contract ends |
||
2 |
Chemical Waste Producer Registration |
Waste Producers Number:
No.:5113-634-C3817-01 |
7 Oct 2013 |
Till Contract ends |
||
3 |
Water Pollution Control Ordinance - Discharge License |
No.:WT00016832 ¡V 2013 |
28 Aug 13 |
31 Aug
2018 |
||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7017914 |
2 Aug 13 |
Till Contract ends |
||
5 |
Construction
Noise Permit |
GW-RN0233-16 |
11 Apr 2016 |
10 Oct 2016 |
||
GW-RN0309-16 |
30 Apr 2016 |
29 Oct 2016 |
||||
GW-RN0414-16 |
18 Jun 2016 |
17 Dec 2016 |
||||
GW-RN0434-16 |
22 Jun 2016 |
21 Dec 2016 |
||||
GW-RN0514-16 |
16 Jul 2016 |
15 Oct 2016 |
||||
GW-RN0525-16 |
20 Jul 2016 |
7 Jan 2017 |
||||
GW-RN0541-16 |
5 Aug 2016 |
4 Nov 2016 |
||||
GW-RN0549-16 |
30 Jul 2016 |
9 Jan 2017 |
||||
GW-RN0557-16 |
8
Aug 2016 |
30
Sep 2016 |
||||
GW-RN0561-16 |
16 Aug 2016 |
11 Feb 2017 |
||||
GW-RN0580-16 |
25 Aug 2016 |
24 Feb 2017 |
||||
GW-RN0581-16 |
25 Aug 2016 |
24 Feb 2017 |
||||
GW-RN0596-16 |
17 Aug 2016 |
15 Feb 2017 |
||||
GW-RN0606-16 |
27 Aug 2016 |
2 Oct 2016 |
||||
GW-RN0619-16 |
22 Aug 2016 |
14 Feb 2017 |
||||
GW-RN0646-16 |
10 Sep
2016 |
9 Mar 2017 |
||||
GW-RN0649-16 |
3 Sep 2016 |
7 Jan 2017 |
||||
GW-RN0653-16 |
11 Sep 2016 |
10 Mar 2017 |
||||
GW-RN0654-16 |
15 Sep 2016 |
14 Mar 2017 |
||||
GW-RN0708-16 |
8 Oct 2016 |
28 Jan 2017 |
||||
GW-RN0711-16 |
1 Oct 2016 |
13 Jan 2017 |
||||
GW-RN0720-16 |
4 Oct 2016 |
31 Mar 2017 |
||||
GW-RN0729-16 |
5 Oct 2016 |
31 Mar 2017 |
||||
GW-RN0756-16 |
18 Oct 2016 |
13 Apr 2017 |
||||
Contract 5 |
||||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 359338 |
13 May 2013 |
Till the end of Contract |
||
2 |
Chemical Waste Producer Registration |
Waste Producers Number No.:
5213-642-S3735-01 |
8 Jun 2013 |
Till the end of Contract |
||
3 |
Water Pollution Control Ordinance - Discharge License |
No.: W5/1G44/1 |
8 Jun 13 |
30 Jun 2018 |
||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7017351 |
29 Apr 13 |
Till the end of Contract |
||
Contract 6 |
||||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 390614 |
29 Jun 2015 |
Till the end of Contract |
||
2 |
Chemical Waste Producer Registration |
Waste Producers Number No.: 5213-652-C3969-01 |
31 Aug 2015 |
Till the end of Contract |
||
3 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7022707 |
9 Jul 2015 |
Till the end of Contract |
||
4 |
Water Pollution Control Ordinance - Discharge License |
No.:WT00024574-2016 |
31 May 2016 |
31 May 2021 |
||
No.:WT00024576-2016 |
31 May 2016 |
31 May 2021 |
||||
No.:WT00024742-2016 |
14
June 2016 |
30
June 2021 |
||||
No.:WT00024746-2016 |
14
June 2016 |
30
June 2021 |
||||
5 |
Construction
Noise Permit |
GW-RW0588-16 |
19 Oct 2016 |
18 Apr 2017 |
||
GW-RN0766-16 |
21 Oct 2016 |
20 Jan 2017 |
||||
Contract SS C505 |
||||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 390974 |
13 Jul 2015 |
Till the end of Contract |
||
2 |
Chemical Waste Producer Registration |
Waste
Producer No.: 5213-642-L1048-07 |
16 Sep 2015 |
Till the end of Contract |
||
3 |
Water Pollution Control Ordinance - Discharge License |
No.:
WT00024865-2016 |
8 Jul 2016 |
30 Nov 2020 |
||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7022831 |
23 Jul 2015 |
Till the end of Contract |
||
5 |
Construction
Noise Permit |
GW-RN0396-16 |
5 June 2016 |
4 Nov 2016 |
||
PP-RN0020-16 |
16 Jul 2016 |
14 Jan 2017 |
||||
GW-RN0520-16 |
23 Jul 2016 |
22 Jan 2017 |
||||
Contract
7 |
||||||
1 |
Air pollution Control (Construction Dust) Regulation |
Ref. No: 397015 |
21 Dec 2015 |
Till the end of Contract |
||
2 |
Chemical Waste Producer Registration |
Waste
Producer No.: 5214-641-K3202-01 |
24 Mar 2016 |
Till the end of Contract |
||
3 |
Water Pollution Control Ordinance - Discharge License |
No.: WT00024422-2016
|
10 May 2016 |
31 May 2021 |
||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7024129 |
21 Jan 2016 |
Till the end of Contract |
||
5 |
Construction
Noise Permit |
GW-RN0538-16 |
23 Jul 2016 |
4 Nov 2016 |
||
Contract 4 |
||||||
1 |
Air pollution Control (Construction Dust) Regulation |
Form of Notification of Construction work has submitted to EPD in July
2016. |
||||
2 |
Chemical Waste Producer Registration |
Application
is under preparation |
||||
3 |
Water Pollution Control Ordinance - Discharge License |
Application
is under preparation |
||||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Application
is under preparation |
||||
3.1.1
The Environmental Monitoring and Audit
requirements are set out in the Approved EM&A manual. Environmental issues
such as air quality, construction noise and water quality were identified as
the key issues during the construction phase of the Project.
3.1.2
A summary of construction phase EM&A
requirements are presented in the
sub-sections below.
3.2.1
The EM&A program of construction phase
monitoring shall cover the following environmental issues:
•
Air quality;
•
Construction noise; and
•
Water quality
3.2.2
A summary of the monitoring parameters is
presented in Table 3-1.
Table 3-1 Summary
of EM&A Requirements
Environmental Issue |
Parameters |
Air Quality |
1-hour
TSP by Real-Time Portable Dust Meter; and 24-hour
TSP by High Volume Air Sampler. |
Noise |
Leq(30min) in
normal working days (Monday to Saturday) 07:00-19:00 except public holiday;
and 3 sets
of consecutive Leq(5min) on restricted
hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday Supplementary
information for data auditing, statistical results such as L10 and
L90 shall also be obtained for reference. |
Water Quality |
In-situ Measurements Dissolved
Oxygen Concentration (mg/L); Dissolved
Oxygen Saturation (% ); Turbidity
(NTU); pH unit; Water
depth (m); and Temperature
(¢J). |
Laboratory Analysis
Suspended
Solids (mg/L) |
3.3.1
The designated monitoring locations as
recommended in the EM&A Manual
are shown in Appendix D. As the access to some of the designated
monitoring locations was questionable due to safety reason or denied by the
landlords, alternative locations therefore have had proposed. The proposed
alternative monitoring locations has updated in the revised EM&A Programme
which verified by IEC and certified by ET Leader prior submitted to EPD on 10
July 2013. Table 3-2, Table
3-3 and Table 3-4 are respectively listed the air quality, construction
noise and water quality monitoring locations for the Project and a map showing
these monitoring stations is presented in Appendix E.
Table 3-2 Impact
Monitoring Stations - Air Quality
Station ID |
Description |
Works Area |
Related to the Work Contract |
AM1b^ |
Open area at
Tsung Yuen Ha Village |
BCP |
SS C505 Contract 7 |
AM2 |
Village House
near Lin Ma Hang Road |
LMH to Frontier
Closed Area |
Contract 6 |
AM3 |
Ta Kwu Ling
Fire Service Station of Ta Kwu Ling Village. |
LMH to Frontier
Closed Area |
Contract 6 |
AM4b^ |
House no. 10B1 Nga Yiu Ha Village |
LMH to Frontier
Closed Area |
Contract 6 |
AM5a^ |
Ping Yeung
Village House |
Ping Yeung to
Wo Keng Shan |
Contract 6 |
AM6 |
Wo Keng Shan Village House |
Ping Yeung to
Wo Keng Shan |
Contract 6 |
AM7b@ |
Loi Tung Village House |
Sha Tau Kok
Road |
Contract 2 Contract 6 |
AM8 |
Po Kat Tsai
Village No. 4 |
Po Kat Tsai |
Contract 2 |
AM9b# |
Nam Wa Po Village House No. 80 |
Fanling |
Contract 3 |
# Proposal for the change of air quality monitoring location from AM9a
to AM9b was submitted to EPD on 4 Nov 2013 after verified by the IEC and it was
approved by EPD (EPD¡¦s ref.: (15) in EP 2/N7/A/52 Pt.10 dated 8 Nov 2013).
* Proposal for the change of air quality monitoring location from AM1to
AM1a was submitted to EPD on 24 March 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (6) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
@ Proposal for the change of air quality monitoring location from AM7a to
AM7b was submitted to EPD on 4 June 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (7) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
^ Proposal for change of air quality monitoring locations was enclosed
in the updated EM&A Programme which approval by EPD on 29 Mar 2016.
Table 3-3 Impact
Monitoring Stations - Construction Noise
Station ID |
Description |
Works Area |
Related to the Work Contract |
NM1 |
Tsung Yuen Ha Village House No. 63 |
BCP |
SS C505 Contract 7 |
NM2a# |
Village House near Lin Ma Hang
Road |
Lin Ma Hang to Frontier Closed
Area |
Contract 6 |
NM3 |
Ping Yeung Village House (facade
facing northeast) |
Ping Yeung to Wo Keng Shan |
Contract 6 |
NM4 |
Wo Keng
Shan Village House |
Ping Yeung to Wo Keng Shan |
Contract 6 |
NM5 |
Village House, Loi Tung |
Sha Tau Kok Road |
Contract 2, Contract 6 |
NM6 |
Tai Tong Wu Village House 2 |
Sha Tau Kok Road |
Contract 2, Contract 6 |
NM7 |
Po Kat Tsai Village |
Po Kat Tsai |
Contract 2 |
NM8 |
Village House, Tong Hang |
Fanling |
Contract 2 Contract 3 |
NM9 |
Village House, Kiu Tau Village |
Fanling |
Contract 3 |
NM10 |
Nam Wa
Po Village House No. 80 |
Fanling |
Contract 3 |
# Proposal for the change of construction noise monitoring location from
NM2 to NM2a was verified by the IEC on 6 May 2016 and was effective on 9 May
2016.
Table 3-4 Impact
Monitoring Stations - Water Quality
Station ID |
Description |
Coordinates of Designated / Alternative Location |
Nature of the location |
Related to the Work Contract |
|
Easting |
Northing |
||||
WM1 |
Downstream of Kong Yiu Channel |
833 679 |
845 421 |
Alternative location located at upstream 51m of the designated location |
SS C505 Contract 6 |
WM1- Control |
Upstream of Kong Yiu Channel |
834 185 |
845 917 |
NA |
SS C505 Contract 6 |
WM2A |
Downstream of River Ganges |
834 204 |
844 471 |
Alternative location located at upstream 81m of the designated location |
Contract 6 |
WM2A(a)* |
Downstream of River Ganges |
834 191 |
844 474 |
Alternative location located at upstream 70m of the designated location |
Contract 6 |
WM2A- Controlx# |
Upstream of River Ganges |
835 377 |
844 188 |
Alternative location located at upstream 160m of the designated location |
Contract 6 |
WM2B |
Downstream of River Ganges |
835 433 |
843 397 |
NA |
Contract 6 |
WM2B- Control |
Upstream of River Ganges |
835 835 |
843 351 |
Alternative location located at downstream 31m of the designated
location |
Contract 6 |
WM3x# |
Downstream of River Indus |
836 206 |
842 270 |
Alternative location located at downstream 180m of the designated
location |
Contract 2 Contract 6 |
WM3- Control |
Upstream of River Indus |
836 763 |
842 400 |
Alternative location located at downstream 26m of the designated
location |
Contract 2 Contract 6 |
WM4 |
Downstream of Ma Wat Channel |
833 850 |
838 338 |
Alternative location located at upstream 11m of the designated location |
Contract 2 Contract 3 |
WM4¡V Control A |
Kau Lung Hang
Stream |
834 028 |
837 695 |
Alternative location located at downstream 28m of the designated
location |
Contract 2 Contract 3 |
WM4¡V Control B |
Upstream of Ma Wat Channel |
833760 |
837395 |
Alternative location located at upstream 15m of the designated location |
Contract 2 Contract 3 |
Note: EPD has approved the revised EM&A Programme on 29th
March 2016. If the measured water depth of the monitoring station is lower than
150 mm, alternative location (WM3x and WM2A-Controlx) based on
the criteria were selected to perform water monitoring in accordance with the
updated EM&A Programme (Rev. 05) (Section 4.1.4)
* Proposal for the change of water monitoring location from WM2A to WM2A(a) was verified by the IEC and it was approved by EPD.
(EPD¡¦s ref. (10) in EP 2/N7/A/52 Pt.19)
The requirements of impact monitoring are stipulated in Sections 2.1.6, 3.1.5 and 4.1.6 of the approved EM&A Manual and presented as
follows.
Air Quality Monitoring
3.4.1
Frequency of impact air quality monitoring is
as follows:
1-hour TSP |
3 times every six
days during course of works |
24-hour TSP |
Once every 6 days
during course of works. |
Noise Monitoring
3.4.2
One set of Leq(30min)
as 6 consecutive Leq(5min)
between 0700-1900 hours on normal weekdays and once every week during course of
works. If construction work
necessary to carry out at other time periods, i.e. restricted time period
(19:00 to 07:00 the next morning and whole day on public holidays) (hereinafter
referred as ¡§the restricted hours¡¨), additional weekly impact monitoring for Leq(5min) measurement shall be
employed during respective restricted hours periods.. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for
reference.
Water Quality Monitoring
3.4.3
The water quality monitoring frequency shall
be 3 days per week during course of works.
The interval between two sets of monitoring shall not be less than 36
hours.
Air Quality Monitoring
3.5.1
The 24-hour and 1-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B. If the ET proposes to use a direct
reading dust meter to measure 1-hour TSP levels, it shall submit sufficient
information to the IEC to approve.
3.5.2
The filter paper of
24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.
3.5.3
All equipment to be used for air quality
monitoring is listed in Table 3-5.
Table 3-5 Air
Quality Monitoring Equipment
Equipment |
Model |
24-Hr TSP |
|
High
Volume Air Sampler |
TISCH High Volume
Air Sampler, HVS Model TE-5170* |
Calibration
Kit |
TISCH Model TE-5025A* |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3B
Laser Dust monitor Particle Mass Profiler & Counter* |
* Instrument was used in the Reporting
Period and the calibration certificate could be referred in Appendix F.
Wind Data Monitoring Equipment
3.5.4
According to the approved EM&A Manual,
wind data monitoring equipment shall also be provided and set up for logging
wind speed and wind direction near the dust monitoring locations. The equipment installation location
shall be proposed by the ET and agreed with the IEC. For installation and operation of wind
data monitoring equipment, the following points shall be observed:
1)
The wind sensors should be installed 10 m
above ground so that they are clear of obstructions or turbulence caused by
buildings.
2)
The wind data should be captured by a data
logger. The data shall be downloaded for analysis at least once a month.
3)
The wind data monitoring equipment should be
re-calibrated at least once every six months.
4)
Wind direction should be divided into 16
sectors of 22.5 degrees each.
3.5.5
ET has liaised with the landlords of the
successful granted HVS installation premises. However, the owners rejected to provide
premises for wind data monitoring equipment installation.
3.5.6
Under this situation, the ET proposed
alternative methods to obtain representative wind data. Meteorological information as extracted
from ¡§the Hong Kong Observatory Ta Kwu Ling Station¡¨ is alternative method to
obtain representative wind data.
For Ta Kwu Ling Station, it is located nearby the Project site. Moreover, this station is located at 15m
above mean sea level while its anemometer is located at 13m above the existing
ground which in compliance with the general setting up requirement. Furthermore, this station also can be to
provide the humidity, rainfall, and air pressure and temperature etc.
meteorological information. In Hong
Kong of a lot development projects, weather information extracted from Hong
Kong Observatory is common alternative method if weather station installation
not allowed.
Noise Monitoring
3.5.7
Sound level meter in compliance with the
International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. The sound level meter shall be checked
using an acoustic calibrator. The
wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
3.5.8
Noise monitoring equipment to be used for
monitoring is listed in Table 3-6.
Table 3-6 Construction
Noise Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
B&K Type 2238* or Rion
NL-31 or Rion NL-52* |
Calibrator |
B&K Type 4231* or Cesva
CB-5 or Rion NC-74* |
Portable Wind Speed Indicator |
Testo Anemometer |
* Instrument was used in the Reporting
Period and the calibration certificate could be referred in Appendix F.
3.5.9
Sound level meters listed above comply with
the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications, as recommended in TM issued
under the NCO. The acoustic
calibrator and sound level meter to be used in the impact monitoring will be
calibrated yearly.
Water Quality Monitoring
3.5.10
DO and water temperature should be measured
in-situ by a DO/temperature meter. The instrument should be portable and
weatherproof using a DC power source. It should have a membrane electrode with
automatic temperature compensation complete with a cable. The equipment should
be capable of measuring:
•
a DO level in the range of 0-20 mg/l and
0-200% saturation; and
•
a temperature
of between 0 and 45 degree Celsius.
3.5.11
A portable pH meter capable of measuring a
range between 0.0 and 14.0 should be provided to measure pH under the specified
conditions accordingly to the APHA Standard Methods.
3.5.12
The instrument should be portable and
weatherproof using a DC power source. It should have a photoelectric sensor
capable of measuring turbidity between 0-1000 NTU.
3.5.13
A portable, battery-operated echo sounder or
tape measure will be used for the determination of water depth at each designated
monitoring station as appropriate.
3.5.14
A water sampler e.g. Kahlsico
Water Sampler, which is a transparent PVC cylinder with capacity not less than
2 litres, will be used for water sampling if water depth over than 0.5m. For sampling from very shallow water
depths e.g. <0.5 m, water sample collection will be directly from water
surface below 100mm use sampling plastic bottle to avoid inclusion of bottom
sediment or humus. Moreover,
Teflon/stainless steel bailer or self-made sampling buckets maybe used for
water sampling. The equipment used
for sampling will be depended the sampling location and depth situations.
3.5.15
Water samples for laboratory measurement of
SS will be collected in high density polythene bottles, packed in ice (cooled
to 4 ºC without being frozen), and delivered to the laboratory in the same day
as the samples were collected.
3.5.16
Analysis of suspended solids should be
carried out in a HOKLAS or other accredited laboratory. Water samples of about
1L should be collected at the monitoring stations for carrying out the
laboratory suspended solids determination.
The SS determination work should start within 24 hours after collection
of the water samples. The SS analyses should follow the APHA Standard Methods 2540D with Limit of Reporting of 2 mg/L.
3.5.17
Water quality monitoring equipment used in
the impact monitoring is listed in Table 3-7. Suspended solids (SS)
analysis is carried out by a local HOKLAS-accredited laboratory, namely ALS Technichem
(HK) Pty Ltd.
Table 3-7 Water
Quality Monitoring Equipment
Equipment |
Model |
Water
Depth Detector |
Eagle
Sonar or tape measures |
Water Sampler |
A 2-litre transparent PVC cylinder with latex cups at
both ends or teflon/stainless steel bailer or
self-made sampling bucket |
Thermometer & DO meter |
YSI Professional Plus /YSI PRO20 Handheld Dissolved
Oxygen Instrument / YSI 550A Multifunctional Meter*/ YSI Professional DSS |
pH meter |
YSI Professional Plus / AZ8685 pH pen-style meter*/ YSI
6820/ 650MDS/ YSI Professional DSS |
Turbidimeter |
Hach 2100Q*/ YSI 6820/
650MDS/ YSI Professional DSS* |
Sample Container |
High density polythene bottles (provided by laboratory) |
Storage
Container |
¡¥Willow¡¦
33-liter plastic cool box with Ice pad |
* Instrument was used in the Reporting
Period and the calibration certificate could be referred in Appendix F.
1-hour TSP
Monitoring
3.6.1
The 1-hour TSP monitor was a brand named ¡§Sibata LD-3B Laser Dust monitor Particle Mass Profiler
& Counter¡¨ which is a portable, battery-operated laser photometer. The 1-hour TSP meter provides a real
time 1-hour TSP measurement based on 90o light scattering. The 1-hour TSP monitor consists of the
following:
(a.)
A pump to draw sample aerosol through the
optic chamber where TSP is measured;
(b.)
A sheath air system to isolate the aerosol in
the chamber to keep the optics clean for maximum reliability; and
(c.)
A built-in data logger compatible with
Windows based program to facilitate data collection, analysis and reporting.
3.6.2
The 1-hour TSP meter is used within the valid
period as follow manufacturer¡¦s Operation and Service Manual.
3.6.3
The equipment used for 24-hour TSP
measurement is Tisch Environmental, Inc. Model TE-5170 TSP
high volume air sampling system, which complied with EPA Code of Federal Regulation, Appendix B to Part 50. The High
Volume Air Sampler (HVS) consists of the following:
(a.)
An anodized aluminum shelter;
(b.)
A 8¡¨x10¡¨ stainless steel filter holder;
(c.)
A blower motor assembly;
(d.)
A continuous flow/pressure recorder;
(e.)
A motor speed-voltage control/elapsed time
indicator;
(f.)
A 7-day mechanical timer, and
(g.)
A power supply of 220v/50 Hz
3.6.4
The HVS is operated and calibrated on a
regular basis in accordance with the manufacturer¡¦s instruction using Tisch Calibration Kit Model TE-5025A. Calibration would carry out in two month
interval.
3.6.5
24-hour TSP is collected by the ET on filters
of HVS and quantified by a local HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd (ALS), upon receipt of the
samples. The ET keep all the
sampled 24-hour TSP filters in normal air conditioned room conditions, i.e. 70%
RH (Relative Humidity) and 25oC, for six months prior to disposal.
3.6.6
Noise measurements were taken in terms of the
A-weighted equivalent sound pressure level (Leq)
measured in decibels dB(A). Supplementary statistical
results (L10 and L90) were also obtained for reference.
3.6.7
During the monitoring, all noise measurements
would be performed with the meter set to FAST response and on the A-weighted
equivalent continuous sound pressure level (Leq). Leq(30min)
in six consecutive Leq(5min) measurements
will use as the monitoring parameter for the time period between 0700-1900
hours on weekdays; Leq(5min) measurements
would be used as monitoring parameter for other time periods (e.g. during
restricted hours), if necessary.
3.6.8
Prior of noise measurement, the accuracy of
the sound level meter is checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. The checking is performed before and
after the noise measurement.
Water
Quality
3.6.9
Water quality monitoring is conducted at the
designated or alternative locations. The sampling procedures with the in-situ
monitoring are presented as below:
Sampling Procedure
3.6.10
A Digital Global
Positioning System (GPS) is used to identify the designated monitoring stations
prior to water sampling. A
portable, battery-operated echo sounder or tape measurement is used for the
determination of water depth at each station. At each station, water sample would be
collected from 0.1m below water surface or the water surface to prevent the
river bed sediment for stirring.
3.6.11
The sample container will be rinsed with a
portion of the water sample. The
water sample then will be transferred to the high-density polythene bottles as provided by the laboratory,
labeled with a unique sample number and sealed with a screw cap.
3.6.12
Before sampling, general information such as
the date and time of sampling, weather condition as well as the personnel
responsible for the monitoring would be recorded on the field data sheet.
3.6.13
A ¡¥Willow¡¦ 33-liter plastic cool box packed
with ice will be used to preserve the water samples prior to arrival at the
laboratory for chemical determination.
The water temperature of the cool box is maintained at a temperature as
close to 40C as possible without being frozen. Samples collected are delivered to the
laboratory upon collection.
In-situ Measurement
3.6.14
YSI 550A Handheld Dissolved Oxygen Instrument is used for water in-situ measures,
which automates the measurements and data logging of temperature, dissolved
oxygen and dissolved oxygen saturation.
3.6.15
A portable AZ Model 8685 is used for in-situ
pH measurement. The pH meter is
capable of measuring pH in the range of 0 ¡V 14 and readable to 0.1.
3.6.16
A portable Hach
2100Q Turbidimeter or YSI Professional DSS is used
for in-situ turbidity measurement. The turbidity meter is capable of measuring
turbidity in the range of 0 ¡V 1000 NTU.
3.6.17
All in-situ measurement equipment are calibrated by HOKLAS accredited laboratory of three
month interval.
Laboratory Analysis
3.6.18
All water samples analyzed Suspended Solids
(SS) will be carried out by a local HOKLAS-accredited testing laboratory (ALS Technichem (HK) Pty Ltd HOKLAS registration no. 66). SS determination using APHA
Standard Methods 2540D as specified in the EM&A Manual will start within
48 hours of water sample receipt.
3.7.1
Calibration of the HVS is performed upon
installation and thereafter at bimonthly intervals in accordance with the
manufacturer¡¦s instruction using the certified standard calibrator (TISCH Model
TE-5025A).
Moreover, the Calibration Kit would be calibrated annually. The calibration data are properly
documented and the records are maintained by ET for future reference.
3.7.2
The 1-hour TSP
meter was calibrated by the supplier prior to purchase. Zero response of the equipment would be
checked before and after each monitoring event. Annually calibration with the High
Volume Sampler (HVS) in same condition would be undertaken by the Laboratory.
3.7.3
The sound level
meter and calibrator are calibrated and certified by a laboratory accredited
under HOKLAS or any other international accreditation scheme at yearly basis.
3.7.4
All water quality monitoring equipment would
be calibrated by HOKLAS accredited laboratory of three month intervals.
3.7.5
The calibration
certificates of all monitoring equipment used for the impact monitoring program
in the Reporting Period and the HOKLAS accredited certificate of laboratory are attached in Appendix F.
3.8.1
The baseline results form the basis for
determining the environmental acceptance criteria for the impact
monitoring. According to the
approved Environmental Monitoring and Audit Manual, the air quality,
construction noise and water quality criteria were set up, namely Action and
Limit levels are listed in Tables 3-8, 3-9 and 3-10.
Table 3-8 Action and
Limit Levels for Air Quality Monitoring
Monitoring
Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
AM1b |
265 |
143 |
500 |
260 |
AM2 |
268 |
149 |
||
AM3 |
269 |
145 |
||
AM4b |
267 |
148 |
||
AM5a |
268 |
143 |
||
AM6 |
269 |
148 |
||
AM7b |
275 |
156 |
||
AM8 |
269 |
144 |
||
AM9b |
271 |
151 |
Table 3-9 Action
and Limit Levels for Construction Noise
Monitoring Location |
Action Level |
Limit Level in
dB(A) |
Time Period:
0700-1900 hours on normal weekdays |
||
NM1, NM2a, NM3,
NM4, NM5, NM6, NM7, NM8, NM9, NM10 |
When one
or more documented complaints are received |
75 dB(A)Note 1
& Note 2 |
Note 1: Acceptable Noise Levels
for school should be reduced to 70 dB(A)
and65 dB(A) during examination period
Note 2: If works are to be
carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the NCA have to be followed.
Table 3-10 Action and
Limit Levels for Water Quality
Parameter |
Performance
criteria |
Monitoring Location |
|||||
WM1 |
WM2A(a) |
WM2B |
WM3x |
WM4 |
|||
DO (mg/L) |
Action Level |
(*)4.23 |
(**)4.00 |
(*)4.74 |
(**)4.00 |
(*)4.14 |
|
Limit Level |
(#)4.19 |
(**)4.00 |
(#)4.60 |
(**)4.00 |
(#)4.08 |
||
Turbidity (NTU) |
Action Level |
51.3 |
24.9 |
11.4 |
13.4 |
35.2 |
|
AND 120% of upstream control station of
the same day |
|||||||
Limit Level |
67.6 |
33.8 |
12.3 |
14.0 |
38.4 |
||
AND 130% of upstream control station of the same day |
|||||||
SS (mg/L) |
Action Level |
54.5 |
14.6 |
11.8 |
12.6 |
39.4 |
|
AND 120% of upstream control station of the
same day |
|||||||
Limit Level |
64.9 |
17.3 |
12.4 |
12.9 |
45.5 |
||
AND 130% of upstream control station of the same day |
|||||||
Remarks: (*) The
Proposed Action Level of Dissolved
Oxygen is adopted to be used 5%-ile of
baseline data (**) The
Proposed Action & Limit Level of Dissolved
Oxygen is used 4mg/L (#) The
Proposed Limit Level of Dissolved
Oxygen is adopted to be used 1%-ile of
baseline data |
|||||||
3.8.2
Should non-compliance of the environmental
quality criteria occurs, remedial actions will be triggered according to the
Event and Action Plan which presented in Appendix G.
3.9.1
All monitoring data will be handled by the ET¡¦s in-house data recording and management system. The monitoring data
recorded in the equipment will be downloaded directly from the equipment at the
end of each monitoring day. The
downloaded monitoring data will input into a computerized database maintained
by the ET. The laboratory results
will be input directly into the computerized database and checked by personnel
other than those who input the data.
3.9.2
For monitoring parameters that require
laboratory analysis, the local laboratory shall follow the QA/QC requirements
as set out under the HOKLAS scheme for the relevant laboratory tests.
4.1.1
In the Reporting Period, construction works under the
project have been commenced in Contracts 2,
3, 6, 7 and Contract SS C505. Hence, air quality monitoring was performed at all
designated locations.
4.1.2
The air quality monitoring schedule is presented
in Appendix H and the monitoring
results are summarized in the following sub-sections.
4.2.1
In the Reporting Period, a total of 135 events of 1-hour TSP and 45
events 24-hours TSP monitoring were carried out and the monitoring results are
summarized in Tables 4-1 to 4-9. The detailed 24-hour TSP monitoring
data are presented in Appendix
I and the relevant graphical plots are shown in Appendix J.
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1b
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
3-Oct-16 |
40
|
5-Oct-16 |
9:10 |
80 |
83 |
73 |
8-Oct-16 |
78
|
11-Oct-16 |
9:20 |
73 |
64 |
59 |
14-Oct-16 |
60
|
17-Oct-16 |
9:40 |
140 |
108 |
103 |
20-Oct-16 |
70
|
22-Oct-16 |
13:01 |
39 |
39 |
39 |
26-Oct-16 |
43
|
28-Oct-16 |
9:40 |
26 |
25 |
32 |
Average (Range) |
58 (40 ¡V 78) |
Average (Range) |
66 (25 ¡V 140) |
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
3-Oct-16 |
104
|
5-Oct-16 |
9:05 |
87 |
85 |
87 |
8-Oct-16 |
144
|
11-Oct-16 |
9:25 |
84 |
74 |
62 |
14-Oct-16 |
120
|
17-Oct-16 |
9:29 |
170 |
135 |
119 |
20-Oct-16 |
60
|
22-Oct-16 |
13:03 |
43 |
44 |
46 |
26-Oct-16 |
106 |
28-Oct-16 |
9:46 |
57 |
60 |
55 |
Average (Range) |
107 (60 ¡V 144) |
Average (Range) |
81 (43 ¡V 170) |
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
3-Oct-16 |
108
|
5-Oct-16 |
9:00 |
89 |
88 |
91 |
8-Oct-16 |
137
|
11-Oct-16 |
9:29 |
93 |
91 |
70 |
14-Oct-16 |
104
|
17-Oct-16 |
8:56 |
178 |
153 |
119 |
20-Oct-16 |
49
|
22-Oct-16 |
13:07 |
45 |
46 |
44 |
26-Oct-16 |
101 |
28-Oct-16 |
9:52 |
65 |
65 |
54 |
Average (Range) |
100 (49 ¡V 137) |
Average (Range) |
86 (44 ¡V 178) |
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM4b
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
5-Oct-16 |
42
|
6-Oct-16 |
9:42 |
67 |
74 |
75 |
11-Oct-16 |
30
|
12-Oct-16 |
9:45 |
85 |
86 |
82 |
17-Oct-16 |
59
|
18-Oct-16 |
13:03 |
31 |
24 |
28 |
22-Oct-16 |
35
|
24-Oct-16 |
9:47 |
61 |
62 |
60 |
28-Oct-16 |
54 |
29-Oct-16 |
9:11 |
74 |
73 |
68 |
Average (Range) |
44 (30 ¡V 59) |
Average (Range) |
63 (24 ¡V 86) |
Table 4-5 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM5a
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
5-Oct-16 |
80
|
6-Oct-16 |
9:51 |
77 |
73 |
81 |
11-Oct-16 |
51
|
12-Oct-16 |
9:40 |
89 |
87 |
84 |
17-Oct-16 |
35
|
18-Oct-16 |
13:14 |
33 |
26 |
26 |
22-Oct-16 |
35
|
24-Oct-16 |
9:51 |
58 |
66 |
64 |
28-Oct-16 |
27
|
29-Oct-16 |
9:17 |
69 |
68 |
64 |
Average (Range) |
46 (27 ¡V 80) |
Average (Range) |
64 (26 ¡V 89) |
Table 4-6 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM6
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
5-Oct-16 |
138
|
6-Oct-16 |
9:30 |
87 |
79 |
82 |
11-Oct-16 |
97
|
12-Oct-16 |
9:30 |
95 |
98 |
93 |
17-Oct-16 |
60
|
18-Oct-16 |
12:50 |
35 |
33 |
27 |
22-Oct-16 |
63
|
24-Oct-16 |
9:37 |
56 |
64 |
62 |
28-Oct-16 |
97 |
29-Oct-16 |
9:19 |
76 |
77 |
75 |
Average (Range) |
91 (60 ¡V 138) |
Average (Range) |
69 (27 ¡V 98) |
Table 4-7 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM7b
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
5-Oct-16 |
86
|
6-Oct-16 |
13:03 |
68 |
73 |
71 |
11-Oct-16 |
39
|
12-Oct-16 |
9:12 |
72 |
68 |
68 |
17-Oct-16 |
75
|
18-Oct-16 |
9:41 |
25 |
27 |
26 |
22-Oct-16 |
54
|
24-Oct-16 |
9:19 |
81 |
88 |
67 |
28-Oct-16 |
64 |
29-Oct-16 |
9:29 |
142 |
184 |
200 |
Average (Range) |
63 (39 ¡V 86) |
Average (Range) |
84 (25 ¡V 200) |
Table 4-8 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM8
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
5-Oct-16 |
59
|
6-Oct-16 |
13:11 |
84 |
74 |
75 |
11-Oct-16 |
49
|
12-Oct-16 |
13:09 |
59 |
61 |
52 |
17-Oct-16 |
47
|
18-Oct-16 |
9:35 |
31 |
29 |
31 |
22-Oct-16 |
37
|
24-Oct-16 |
13:02 |
64 |
77 |
53 |
28-Oct-16 |
36 |
29-Oct-16 |
13:10 |
128 |
95 |
93 |
Average (Range) |
46 (36 ¡V 59) |
Average (Range) |
67 (29 -128) |
Table 4-9 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
3-Oct-16 |
34
|
5-Oct-16 |
12:52 |
106 |
117 |
111 |
8-Oct-16 |
57
|
11-Oct-16 |
13:05 |
59 |
60 |
56 |
14-Oct-16 |
43
|
17-Oct-16 |
13:08 |
100 |
69 |
54 |
20-Oct-16 |
31
|
22-Oct-16 |
13:21 |
47 |
49 |
46 |
26-Oct-16 |
27
|
28-Oct-16 |
12:52 |
38 |
32 |
35 |
Average (Range) |
38 (27 ¡V 57) |
Average (Range) |
65 (32 ¡V 117) |
4.2.1
As shown in Tables 4-1 to 4-9, all
the 1-hour TSP and 24-hour TSP monitoring results were below the Action/Limit
Levels. No Notification of
Exceedance (NOE) was issued in this Reporting Period.
4.2.2
The meteorological data during the impact
monitoring days are summarized in Appendix
K.
4.2.3
For the outstanding investigation result for
24-hour TSP exceedances at AM2 and AM3 on 27 September 2016, the investigation
report (IR) conducted by the ET was completed and submitted to relevant
parties. The IR revealed that the
exceedances were not project related and therefore no remedial measures were
proposed. The detail IR is
presented Appendix N.
5.1.1
In the Reporting Period, construction works under the
project have been commenced in Contracts 2,
3, 6, 7 and Contract SS C505 and noise monitoring was performed at all
designated locations.
5.1.2
The noise monitoring schedule is presented in
Appendix H and the monitoring
results are summarized in the following sub-sections.
5.2.1
In the Reporting Period, a total of 40 event noise measurements were
carried out at the designated locations.
The sound level meter was set in 1m from the exterior of the building
façade including noise monitoring locations NM1, NM3, NM4, NM5, NM6, NM7, NM8
and NM9. Therefore, no façade
correction (+3 dB(A)) is added according to acoustical
principles and EPD guidelines. However,
free-field status were performed at NM2a and NM10 and façade correction (+3 dB(A)) has added according to the requirement in this
month. The noise monitoring results
at the designated locations are summarized in Tables 5-1 and 5-2. The detailed noise monitoring
data are presented in Appendix
I and the relevant graphical plots are shown in Appendix J.
Table 5-1 Summary of Construction Noise Monitoring Results
Construction Noise Level (Leq30min), dB(A) |
|||||
Date |
NM1 |
NM2a(*) |
NM8 |
NM9 |
NM10(*) |
5-Oct-16 |
52
|
75
|
56 |
64 |
67 |
11-Oct-16 |
62
|
73
|
59 |
63 |
67 |
17-Oct-16 |
52
|
63
|
59 |
62 |
65 |
28-Oct-16 |
58
|
64
|
56 |
62 |
65 |
Limit Level |
75 dB(A) |
Remarks
(*) façade
correction (+3 dB(A) is added according to acoustical
principles and EPD guidelines
Table 5-2 Summary of Construction Noise Monitoring Results
Construction Noise Level (Leq30min), dB(A) |
|
|||||||
Date |
NM3 |
NM4 |
NM5 |
NM6 |
NM7 |
|
||
6-Oct-16 |
66
|
59
|
60
|
56
|
60
|
|
||
12-Oct-16 |
60
|
68
|
56
|
58
|
69
|
|
||
18-Oct-16 |
64
|
74
|
62
|
63
|
63
|
|
||
24-Oct-16 |
59
|
62
|
56
|
57
|
69
|
|
||
Limit Level |
75 dB(A) |
|
|
54 |
5.2.2
As shown in Tables
5-1 and 5-2, the noise level measured at all designated monitoring locations
were below 75dB(A). Furthermore, there was no noise complaints (Action Level
exceedance) received by the RE, CEDD, Architect/AR/ and the Contractors in the
Reporting Period. Therefore, no
Action or Limit Level exceedance was triggered and no corrective action was
required.
5.3.1
In
the Reporting Period, CNPs were granted by Contracts 2, 3, 6 and 7 for
use of Powered Mechanical Equipment (PME) during restricted hour. As confirmed by both Contractors with their
works schedules, construction works would be conducted at Contract 6 and 7 during
restricted hours with the granted CNP.
Noise monitoring was therefore conducted at the relevant noise
monitoring locations during respective restricted hour periods.
5.3.2
Based on the works schedule by the Contractor of Contracts 2, 3, 6
and 7, the involved noise monitoring locations included NM5, NM7, NM8, NM9 and
NM10 and the noise
monitoring results are summarized in Tables 5-3 and 5-4.
Table 5-3 Summary of Construction Noise Monitoring Results (Evening Time)
Construction Noise Level (Leq5min), dB(A) |
||||||||||
Date |
NM5 |
NM7 |
NM8 |
NM9 |
NM10(*) |
|||||
Start
Time |
Leq5min |
Start
Time |
Leq5min |
Start
Time |
Leq5min |
Start
Time |
Leq5min |
Start
Time |
Leq5min |
|
13-Oct-16 |
22:47 |
46.9
|
22:31 |
48.5
|
21:57 |
58.8
|
-- |
-- |
-- |
-- |
23-Oct-16 |
22:47 |
47.8
|
22:16 |
47.2
|
20:57 |
58.4
|
21:25 |
66.3 |
21:36 |
59.0 |
28-Oct-16 |
22:09 |
44.9 |
21:55 |
52.0
|
21:26 |
62.8
|
-- |
-- |
-- |
-- |
Observation/ other noise source |
NA |
NA |
Traffic noise from trains as NM8 close to
train tracks |
Traffic noise from trains as NM9 close to
train tracks |
Very serious dog barking in the village |
Remarks: If works are to be carried out during restricted hours, the conditions
stipulated in the construction
noise permit issued by the NCA have to be followed.
(*) façade
correction (+3 dB(A) is added according to acoustical
principles and EPD guidelines
Table 5-4 Summary of Construction Noise Monitoring Results (Night Time)
Construction Noise Level (Leq5min), dB(A) |
||||||||||
Date (#) |
NM5 |
NM7 |
NM8 |
NM9 |
NM10(*) |
|||||
Start
Time |
Leq5min |
Start
Time |
Leq5min |
Start
Time |
Leq5min |
Start
Time |
Leq5min |
Start
Time |
Leq5min |
|
13-Oct-16 |
23:00 |
46.8
|
23:15 |
49.1
|
23:40 |
56.0
|
0:00 |
63.8
|
0:11 |
58.3
|
23-Oct-16 |
23:01 |
46.1
|
23:27 |
49.6
|
23:49 |
59.6
|
0:06 |
61.6 |
0:19 |
59.3 |
28-Oct-16 |
23:00 |
45.7
|
23:14 |
50.8
|
23:34 |
64.2
|
0:00 |
59.7 |
0:09 |
56.0 |
Observation/ other noise source |
NA |
NA |
Traffic noise from trains as NM8 close to
train tracks |
Traffic noise from trains as NM9 close to
train tracks |
Very serious dogs barking in the village |
Remarks: If works are to be carried out during restricted hours, the conditions
stipulated in the construction
noise permit issued by the NCA have to be followed.
(#) the
monitoring date for NM9 and NM10 shall be the next day of the ¡§Date¡¨
(*) façade
correction (+3 dB(A) is added according to acoustical
principles and EPD guidelines
5.3.3
According to the site
records by the monitoring team, no construction noise from the construction was
noted during the course of monitoring at all locations. On the other hand, traffic noise was
dominated at NM8 and NM9 since the monitoring locations were closed to the
train tracks and very serious dogs barking were recorded at NM10. Therefore, it is considered that the
measurement results were likely to be the background noise.
6.1.1
In the Reporting Period, construction works under the
project has been commenced in Contracts 2,
3, 6, 7 and Contract SS C505 and water quality monitoring was performed at all
designated locations. The water
quality monitoring schedule is presented in Appendix H. The
monitoring results are summarized in the following sub-sections.
6.2.1
In the Reporting Period, a total of thirteen
(13) sampling days was scheduled to carry out for all designated locations with
their control stations. Since
exceedances were recorded at WM2A(a), WM2B, WM3x and
WM4, according to ¡§Event and Action Plan¡¨
stipulation, three (3) additional water quality monitoring day was conducted for
WM2A(a) and WM4 and its control stations. Also, one (1) and two (2) additional
water quality monitoring days were conducted for WM2B and WM3x respectively and
its control stations in the reporting period.
6.2.2
The key monitoring parameters including Dissolved Oxygen, Turbidity and Suspended
Solids are summarized in Tables 6-1 to 6-5. Breaches of water quality monitoring
criteria are shown in Table 6-6. Detailed monitoring database including
in-situ measurements and laboratory analysis data are shown in Appendix I and the relevant
graphical plot are shown in Appendix
J.
Table 6-1 Water
Quality Monitoring Results Associated of Contracts 2 and 3
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
||||||
WM4 |
WM4-CA |
WM4-CB |
WM4 |
WM4-CA |
WM4-CB |
WM4 |
WM4-CA |
WM4-CB |
|
4-Oct-16 |
6.7 |
7.2 |
7.0 |
15.1 |
7.7 |
7.5 |
13.0 |
7.5 |
8.0 |
6-Oct-16 |
6.7 |
7.0 |
7.0 |
15.7 |
4.9 |
9.6 |
13.5 |
4.0 |
13.0 |
8-Oct-16 |
6.3 |
6.8 |
5.8 |
34.9 |
11.7 |
11.2 |
13.5 |
7.5 |
9.5 |
11-Oct-16 |
6.8 |
7.6 |
6.9 |
250.0 |
12.2 |
21.4 |
153.5 |
6.0 |
34.5 |
12-Oct-16 |
0.0 |
0.0 |
0.0 |
179.0 |
6.4 |
4.8 |
122.0 |
5.0 |
28.0 |
13-Oct-16 |
6.2 |
7.2 |
5.4 |
369.5 |
5.7 |
11.8 |
240.5 |
9.0 |
22.5 |
14-Oct-16# |
-- |
-- |
-- |
13.3 |
3.3 |
4.7 |
15.0 |
6.0 |
17.0 |
15-Oct-16 |
6.2 |
6.9 |
6.0 |
16.6 |
29.3 |
11.4 |
11.0 |
20.5 |
10.0 |
18-Oct-16 |
7.0 |
7.3 |
6.8 |
156.0 |
95.7 |
94.3 |
108.0 |
69.0 |
59.0 |
19-Oct-16# |
-- |
-- |
-- |
561.5 |
522.5 |
281.0 |
536.0 |
539.0 |
220.0 |
20-Oct-16 |
6.4 |
6.0 |
5.0 |
162.5 |
19.1 |
47.3 |
118.5 |
5.0 |
27.5 |
22-Oct-16 |
6.8 |
6.3 |
5.7 |
25.8 |
11.6 |
11.8 |
19.0 |
6.5 |
7.5 |
24-Oct-16 |
6.6 |
6.1 |
6.0 |
33.7 |
8.2 |
26.9 |
25.5 |
3.5 |
19.5 |
26-Oct-16 |
6.2 |
6.5 |
5.6 |
30.1 |
19.6 |
16.8 |
34.0 |
<2 |
8.5 |
28-Oct-16 |
7.3 |
7.7 |
6.4 |
25.5 |
11.1 |
15.6 |
27.5 |
3.0 |
6.0 |
31-Oct-16 |
6.9 |
7.0 |
6.7 |
19.7 |
5.6 |
9.9 |
19.0 |
3.0 |
11.5 |
Remarks: |
bold with underline indicated Limit Level exceedance |
# Additional water quality monitoring at the exceeded
location(s) due to two consecutive monitoring days indicated Limit Level exceedance. |
Table 6-2 Water
Quality Monitoring Results Associated of Contracts 5, 6 and SS C505
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
|||
WM1 |
WM1-C |
WM1 |
WM1-C |
WM1 |
WM1-C |
|
4-Oct-16 |
6.5 |
6.6 |
23.8 |
12.4 |
17.5 |
5.5 |
6-Oct-16 |
7.2 |
7.3 |
46.3 |
12.0 |
47.0 |
6.5 |
8-Oct-16 |
7.3 |
6.5 |
49.7 |
9.6 |
36.5 |
5.0 |
11-Oct-16 |
7.7 |
7.5 |
11.3 |
8.5 |
9.5 |
5.0 |
13-Oct-16 |
6.8 |
6.8 |
15.6 |
7.4 |
18.0 |
6.5 |
15-Oct-16 |
6.8 |
6.1 |
10.3 |
8.1 |
10.0 |
4.0 |
18-Oct-16 |
7.3 |
7.2 |
Over range |
Over range |
1055.0 |
919.5 |
20-Oct-16 |
6.1 |
6.0 |
99.3 |
87.5 |
75.5 |
98.0 |
22-Oct-16 |
5.4 |
5.6 |
21.8 |
32.9 |
10.0 |
21.5 |
24-Oct-16 |
6.0 |
6.2 |
16.2 |
26.3 |
12.5 |
8.0 |
26-Oct-16 |
6.6 |
6.7 |
15.6 |
15.9 |
15.5 |
10.0 |
28-Oct-16 |
7.4 |
7.5 |
49.5 |
16.4 |
48.5 |
7.5 |
31-Oct-16 |
6.7 |
7.0 |
44.9 |
11.8 |
51.0 |
3.0 |
Table 6-3 Water
Quality Monitoring Results Associated only Contract 6
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
|||||||||
WM2A(a) |
WM2A- Cx |
WM2B |
WM2B- C |
WM2A(a) |
WM2A- Cx |
WM2B |
WM2B- C |
WM2A(a) |
WM2A- Cx |
WM2B |
WM2B- C |
|
4-Oct-16 |
5.8 |
5.6 |
6.9 |
4.6 |
124.5 |
7.6 |
-- |
-- |
102.0 |
4.0 |
-- |
-- |
5-Oct-16# |
-- |
-- |
-- |
-- |
24.1 |
4.6 |
-- |
-- |
19.0 |
<2 |
-- |
-- |
6-Oct-16 |
7.2 |
7.1 |
6.8 |
4.9 |
18.6 |
8.8 |
2.9 |
1.8 |
12.5 |
6.0 |
4.5 |
4.5 |
8-Oct-16 |
6.9 |
6.1 |
7.6 |
5.5 |
23.7 |
9.7 |
4.7 |
2.1 |
14.5 |
2.5 |
7.0 |
2.0 |
11-Oct-16 |
7.7 |
7.3 |
6.5 |
7.5 |
24.4 |
9.9 |
4.8 |
3.1 |
19.0 |
2.0 |
<2 |
5.5 |
13-Oct-16 |
6.6 |
6.1 |
7.2 |
5.0 |
14.5 |
10.6 |
2.8 |
1.6 |
11.5 |
<2 |
6.5 |
3.5 |
15-Oct-16 |
6.8 |
6.9 |
8.2 |
5.8 |
23.4 |
7.8 |
3.7 |
1.8 |
14.0 |
<2 |
6.5 |
<2 |
18-Oct-16 |
7.8 |
7.5 |
7.5 |
6.2 |
389.5 |
351.0 |
641.0 |
40.6 |
317.0 |
330.5 |
669.0 |
26.0 |
19-Oct-16# |
-- |
-- |
-- |
-- |
-- |
-- |
240.5 |
91.2 |
-- |
-- |
261.0 |
96.0 |
20-Oct-16 |
6.3 |
6.7 |
6.7 |
5.1 |
329.5 |
32.1 |
26.8 |
4.8 |
156.0 |
5.0 |
24.0 |
<2 |
22-Oct-16 |
6.6 |
6.3 |
6.4 |
5.0 |
261.0 |
6.3 |
9.2 |
4.5 |
183.0 |
4.0 |
7.5 |
<2 |
24-Oct-16 |
6.2 |
6.6 |
6.3 |
5.0 |
128.0 |
8.8 |
9.8 |
3.7 |
120.0 |
4.0 |
11.0 |
<2 |
25-Oct-16# |
-- |
-- |
-- |
-- |
24.5 |
10.5 |
-- |
-- |
18.0 |
7.0 |
-- |
-- |
26-Oct-16 |
7.0 |
7.1 |
6.9 |
4.5 |
22.4 |
8.6 |
10.1 |
3.4 |
14.5 |
6.5 |
10.5 |
<2 |
28-Oct-16 |
7.1 |
7.6 |
7.7 |
6.4 |
53.0 |
8.6 |
4.4 |
3.0 |
48.0 |
5.0 |
5.5 |
<2 |
29-Oct-16# |
-- |
-- |
-- |
-- |
45.4 |
9.1 |
-- |
-- |
88.0 |
8.0 |
-- |
-- |
31-Oct-16 |
7.4 |
7.6 |
6.8 |
6.2 |
69.3 |
23.5 |
10.9 |
3.9 |
111.5 |
7.5 |
5.5 |
<2 |
Remarks: |
bold with underline indicated Limit Level exceedance bold with italic indicated Action Level exceedance |
# Additional water quality monitoring at the exceeded
location(s) due to two consecutive monitoring days indicated Limit Level exceedance. |
Table 6-4 Water
Quality Monitoring Results Associated Contracts 2 and 6
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
|||
WM3x |
WM3-C |
WM3x |
WM3-C |
WM3x |
WM3-C |
|
4-Oct-16 |
6.6 |
6.4 |
12.3 |
9.1 |
12.0 |
5.0 |
6-Oct-16 |
6.4 |
6.8 |
12.9 |
8.4 |
10.5 |
6.0 |
8-Oct-16 |
6.3 |
7.3 |
89.3 |
3.0 |
77.0 |
4.5 |
11-Oct-16 |
6.5 |
6.5 |
9.9 |
5.2 |
8.5 |
3.0 |
12-Oct-16# |
-- |
-- |
7.0 |
3.1 |
9.0 |
3.0 |
13-Oct-16 |
6.4 |
5.4 |
13.2 |
1.8 |
12.0 |
6.0 |
15-Oct-16 |
5.5 |
5.8 |
13.1 |
2.2 |
12.5 |
<2 |
18-Oct-16 |
6.9 |
6.6 |
267.0 |
129.5 |
395.0 |
87.0 |
19-Oct-16# |
-- |
-- |
318.5 |
723.5 |
445.0 |
635.0 |
20-Oct-16 |
5.9 |
6.5 |
12.9 |
7.0 |
12.0 |
4.0 |
22-Oct-16 |
6.5 |
5.9 |
12.8 |
8.2 |
9.5 |
4.0 |
24-Oct-16 |
6.2 |
5.9 |
8.6 |
9.2 |
6.5 |
4.0 |
26-Oct-16 |
6.1 |
5.1 |
12.2 |
5.1 |
12.0 |
<2 |
28-Oct-16 |
6.9 |
6.7 |
12.7 |
5.0 |
10.5 |
4.0 |
31-Oct-16 |
6.6 |
7.3 |
7.1 |
4.7 |
10.5 |
7.5 |
Remarks: |
bold with underline indicated Limit
Level exceedance |
# Additional water quality monitoring at the exceeded
location(s) due to two consecutive monitoring days indicated Limit Level exceedance. |
Table 6-5 Action
and Limit (A/L) Levels Exceedance Recorded
Location |
Dissolved Oxygen |
Turbidity |
Suspended Solids |
Total Exceedance |
Project Related
exceedance |
|||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
|
WM1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
WM2A(a) |
0 |
0 |
0 |
7 |
0 |
10 |
0 |
17 |
0 |
2 (#) |
WM2B |
0 |
0 |
0 |
3 |
0 |
3 |
0 |
6 |
0 |
0 |
WM3x |
0 |
0 |
0 |
2 |
0 |
2 |
0 |
4 |
0 |
0 |
WM4 |
0 |
0 |
0 |
5 |
0 |
5 |
0 |
10 |
0 |
0 |
No of Exceedance |
0 |
0 |
0 |
17 |
0 |
20 |
0 |
37 |
1 |
1 |
(#)
13 number of exceedances at WM2A(a) are under
investigated by ET.
6.2.3
In this Reporting Period, a total of thirty-seven
(37) Limit Level (LL) exceedances, namely seventeen (17) LL exceedance of
turbidity and twenty (20) LL exceedances of Suspended Solids were recorded for
the Project and they are summarized in Table 6-5.
6.2.4
NOE was issued to relevant parties upon
confirmation of the monitoring result. The investigation results and summary of exceedances
are summarized in Table 6-6. The
details of the completed investigation reports for the exceedances are attached
in Appendix
N.
Table 6-6 Summary
of Water Quality Exceedance in the Reporting Period
Date of Exceedance |
Location |
Exceeded Parameter |
Cause of Water Quality Exceedance In Brief
|
28 and 30 Sep 2016 (last reporting month) |
WM2A(a) (C6) |
SS |
Inspection
was carried out align the existing river course of upstream of WM3x and it
was observed that the river water adjacent the construction site was clear
and no muddy discharge from the site was observed. The
monitored drainage channel also collected the rain water from the Sha Tau Kok
road surface via open drain and communal channel and it is believed that the
water quality at monitored channel was affected by rain. In our investigation, it is considered
that the exceedances were unlikely caused by the works under the
Project. |
4, 5 and 11 Oct 2016 |
WM2A(a) (C6) |
NTU &SS |
As reported by CCKJV, a
fresh water pipe at Ping Yeung Interchange was damaged in the morning of 4 October
2016. CCKJV was promptly repaired the pipe which completed by noon of 4
October 2016. However, some muddy runoff was
generated due to the damaged pipe and it was accidentally got into the
adjacent Ping Yuen River. It is considered that the exceedances on 4 October
2016 were related to the pipe damage incident. During weekly site
inspection, water quality mitigation measures implemented on site was in
order and no adverse water impact was identified. It is considered the exceedances were due to natural variation and unlikely
caused by the works under the project. |
8 Oct 2016 |
WM3x (C2 and C6) |
NTU &SS |
Inspection
was carried out align the existing river course of upstream of WM3x and it
was observed that the river water adjacent the construction site was clear
and no muddy discharge from the site was observed. Since
there were no source of muddy water found from construction site and the
wastewater treatment facilities and mitigation measures were properly
maintained as observed during regularly site inspection. It is considered that
the exceedances were due to natural variation and unlikely caused by the
works under the Project. |
11, 12, 13, 18 and 20 Oct 2016 |
WM4 (C2 and C3) |
NTU &SS |
Inspection was
carried out at upstream area of impact station WM4 to investigate the source of
muddy water. Muddy water was
found flowing from the river branch near Kiu Tau Road. There was active
construction site of other Contractor near Kiu Tak Road and muddy water was
observed outside their site area and the underpass drain near that
construction site. During
weekly site inspection, the condition was generally in order and no adverse
water quality impacts under the Contract were identified. In our investigation, it is considered
that exceedances were due to the muddy water from the outside of site
boundary and not likely related to the works under the Project. |
18 Oct 2016 |
WM3x (C2 and C6) |
NTU &SS |
In our
investigation, it is considered that the water quality in the channel on 18 October 2016 was
deteriorated by heavy rain due to vigorous water flow and stir up
sediment. Moreover, the
monitored drainage channel near WM3x would be collected the rain water from
the Sha Tau Kok road surface via open drain and communal channel. It is concluded that the
exceedances were likely due to rain and not caused by the works under the
Project. |
20, 22 and 24 Oct 2016 |
WM2A(a) (C6) |
NTU &SS |
To be
reported in next reporting period. |
18, 19 and 20 Oct 2016 |
WM2B (C6) |
NTU &SS |
On 18 and
19 October 2016, the water flow in the channel was very vigorous due to heavy
rain and turbid water was observed throughout the channel. Moreover, there were trails of muddy
runoff getting into the existing river channel from the adjacent public road
due to rainstorm. On 20
October 2016, there were no muddy water discharged from the site, it is
considered that the exceedances were due to the disturbance of silt and
sediment at the channel bed during sampling at shallow water. It is
considered that the exceedances were not likely caused by
the Project. |
25, 28, 29 and 31 Oct 2016 |
WM2A(a) (C6) |
NTU &SS |
To be
reported in next reporting period. |
7.1.1
In the Reporting Period, no ecology
monitoring for woodland compensation was conducted.
8.1.1
Waste management was carried out in
accordance with the Waste Management Plan (WMP) for each contract.
8.2.1
All types of waste arising from the
construction work are classified into the following:
l Construction
& Demolition (C&D) Material;
l Chemical
Waste;
l General
Refuse; and
l Excavated
Soil.
8.2.2
The quantities of waste for disposal in this
Reporting Period are summarized in Tables 8-1 and 8-2 and the Monthly
Summary Waste Flow Table is shown in Appendix L. Whenever possible, materials were reused
on-site as far as practicable.
Table 8-1 Summary
of Quantities of Inert C&D Materials for the Project
Type of Waste |
Contract 2 |
Contract 3 |
Contract 6 |
Contract 7 |
Contract SS C505 |
Total Quantity |
|||||
Qty. |
Disposal location |
Qty. |
Disposal location |
Qty. |
Disposal location |
Qty. |
Disposal location |
Qty. |
Disposal location |
||
C&D Materials (Inert) (in '000m3) |
92.8467 |
-- |
1.115 |
-- |
36.479 |
-- |
0 |
-- |
1.164 |
-- |
131.6047 |
Reused in this Contract (Inert) (in '000 m3) |
0.8666 |
-- |
0.177 |
-- |
5.359 |
-- |
0 |
-- |
0 |
-- |
6.4026 |
Reused in other Contracts/ Projects (Inert) (in '000 m3) |
39.8733 |
C6/ NENT# &
other projects approved by the ER |
0 |
-- |
9.743 |
C5 &
other projects approved by the ER |
0 |
-- |
0 |
-- |
49.6163 |
Disposal as Public Fill (Inert) (in '000 m3) |
52.1068 |
Tuen Mun 38 |
0.453 |
Tuen Mun 38 |
21.377 |
Tuen Mun 38 |
0 |
Tuen Mun 38 |
1.164 |
TKO 137 |
75.1008 |
Remark #:
The C&D materials were delivered to NENT for reuse by laying cover of the
landfilling area.
Table 8-2 Summary
of Quantities of C&D Wastes for the Project
Type of Waste |
Contract 2 |
Contract 3 |
Contract 6 |
Contract 7 |
Contract SS C505 |
Total Quantity |
|||||
Qty. |
Disposal location |
Qty. |
Disposal location |
Qty. |
Disposal location |
Qty. |
Disposal location |
Qty. |
Disposal location |
||
Recycled Metal (¡¥000kg) # |
0 |
- |
0 |
- |
0 |
-- |
0.2 |
Licensed collector |
988.585 |
Licensed collector |
988.785 |
Recycled
Paper / Cardboard Packing (¡¥000kg) # |
0 |
- |
0 |
- |
0 |
-- |
0.04 |
Licensed collector |
0.36 |
Licensed collector |
0.4 |
Recycled Plastic (¡¥000kg) # |
0 |
-- |
0.002 |
Licensed collector |
0 |
-- |
0.001 |
Licensed collector |
0.098 |
Licensed collector |
0.002#+0.099 |
Chemical Wastes (¡¥000kg) # |
0 |
-- |
0.800 |
Licensed collector |
1.475 |
Licensed collector |
0 |
-- |
0 |
-- |
0.8#+1.475 |
General Refuses (¡¥000m3) |
0.1852 |
NENT |
0.120 |
NENT |
0.075 |
NENT |
0 |
-- |
0.189 |
NENT |
0.5692 |
Remark #: Unit of recycled metal, recycled paper/ cardboard packing,
recycled plastic and chemical waste for Contract 3 was in (¡¥000m3).
9.1.1
According to the approved EM&A Manual, the
environmental site inspection shall be formulation by ET Leader. Weekly environmental site inspections should
carry out to confirm the environmental performance.
Contract 2
9.2.1
In the Reporting Period, joint site
inspection for Contract 2 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on
7, 14 and 28
October 2016 in which the site inspection scheduled on 21 October 2016 was cancelled
due to typhoon signal no. 8. No non-compliance was noted.
9.2.2
The findings / deficiencies of Contract
2 that observed during the weekly site inspection are listed in Table
9-1.
Table 9-1 Site
Observations for Contract 2
Date |
Findings / Deficiencies |
Follow-Up Status |
30 September 2016 (last reporting period) |
Free standing oil drums without drip tray storage on site was observed.
Drip tray should be provided for
all chemical storage on site. (North Portal) |
Oil drums were removed. |
7 October 2016 |
Truck without NRMM label was observed. Proper NRMM label should be
displayed. (South Portal) |
NRMM label attached. |
Oil drums without drip tray and waste oil spillage on ground was
observed. Drip tray should be
provided for all chemical storage on site and the spillage oil should be
cleaned ASAP. (North Portal) |
Oil drums were removed and the spillage oil was cleaned. |
|
Stagnant water cumulated inside the drip tray should be cleaned after
the rainstorm. (South Portal) |
Not required for reminder. |
|
14 October 2016 |
Proper maintanence should be provided for the broken water barriers to
prevent stagnant water accmulation. (South Portal) |
All openings of water barriers have been sealed to avoid mosquito
breeding. |
21 October 2016 |
Joint site inspection was cancelled due to typhoon signal no. 8 |
|
28 October 2016 |
As a reminder, waste oil cumulated inside the drip tray should be
cleaned. Also, waste oil spillage at workshop area should be cleaned up
regularly. (South Portal) |
Not required for reminder. |
Contract 3
9.2.3
In the Reporting Period, joint site
inspection for Contract 3 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 3, 11, 19, 24 and 31 October 2016. No non-compliance was noted.
9.2.4
The findings / deficiencies of Contract
3 that observed during the weekly site inspection are listed in Table
9-2.
Table 9-2 Site
Observations for Contract 3
Date |
Findings / Deficiencies |
Follow-Up Status |
3 October 2016 |
Stagnant water was observed at the lifting eyes of concrete block at
AC1. The Contractor should remove the stagnant water and fill sand to the
lifting eyes to avoid accumulation of stagnant water. |
The stagnant water has been removed from the lifting eyes and the
lifting eyes were sealed up. |
11 October 2016 |
No adverse environmental issue was observed. |
NA |
19 October 2016 |
The Contractor was reminded to dispose of the general refuse on regular
basis and maintain the site tidiness. |
Not required for reminder. |
The Contractor was reminded to remove the stagnant water after rain. |
Not required for reminder. |
|
24 October 2016 |
The Contractor was reminded to remove the stagnant water within the site
to prevent mosquito breeding. |
Not required for reminder. |
31 October 2016 |
No adverse environmental issue was observed. |
NA |
Contract 6
9.2.5
In the Reporting Period, joint site
inspection for Contract 6 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 6, 13, 20 and 27 October 2016. No non-compliance was noted.
9.2.6
The findings / deficiencies of Contract
6 that observed during the weekly site inspection are listed in Table
9-3.
Table 9-3 Site
Observations for Contract 6
Date |
Findings / Deficiencies |
Follow-Up Status |
6 October 2016 |
It was
reminded that the mosquito control measures should be maintained. |
Not required for reminder. |
13 October 2016 |
It was
reminded that the earth bund should be maintained to avoid surface run-off
for the construction area where is near Nylon Dam |
Not required for reminder. |
20 October 2016 |
No adverse environmental issue was observed. |
NA |
27 October 2016 |
Stagnant
water was observed at the roof of the subway in BCP, the Contractor should
provide mitigation measures to prevent mosquito breeding. |
To be followed |
Contract SS C505
9.2.7
In the Reporting Period, joint site
inspection for Contract SS C505 to evaluate the site environmental performance
has been carried out by the RE, IEC, ET and the Contractor on 4, 12, 19 and 26 October 2016. No non-compliance was noted.
9.2.8
The findings / deficiencies of Contract
SS C505 that observed during the weekly site inspection are listed in Table
9-4.
Table 9-4 Site
Observations for Contract SS C505
Date |
Findings / Deficiencies |
Follow-Up Status |
4 October 2016 |
Stagnant water was observed at drainage channel
near training center. The Contractor should remove the stagnant water to
prevent mosquito breeding. |
Water pump was used to remove the stagnant water. |
The Contractor was reminded to ensure the caps of
the water-filled road barriers on site were provided. |
Not required for reminder. |
|
12 October 2016 |
Obstacles were observed at drainage channel near
PTB. The Contractor should remove the obstacles and ensure the drainage
channel function properly. |
No obstacles was observed
at the drainage channel near PTB. |
Stagnant water was observed at drainage channel
near Building 1-3. The Contractor should ensure the channel function properly
to avoid accumulation of stagnant water. |
No stagnant water was observed at the drainage
channel near Building 1-3. |
|
19 October 2016 |
No adverse environmental issue was observed. |
NA |
26 October 2016 |
Temporary drainage blocked by mud and silt was
observed. Mud and silt cumulated inside the drainage should be cleaned to
maintain the drainage is functional. (Whole site area) |
Mud and silt removal work was carried out to
maintain the temporary drainage. |
Stagnant water cumulated inside the drip tray was observed.
Stagnant water inside the drip tray should be removed. (Near Gate 2) |
The drip tray and the generator were removed from
site and no stagnant water was observed. |
|
Ponding water cumulated after rainstorm should be
removed to prevent mosquito breeding. |
Not required for reminder. |
Contract 7
9.2.9
In the Reporting Period, joint site
inspection for Contract 7 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 4, 11, 18 and 25 October 2016. No non-compliance was noted.
9.2.10
The findings / deficiencies of Contract
7 that observed during the weekly site inspection are listed in Table
9-5.
Table 9-5 Site
Observations for Contract 7
Date |
Findings / Deficiencies |
Follow-Up Status |
4 October 2016 |
No adverse environmental issue was
observed. |
NA |
11 October 2016 |
No adverse environmental issue was
observed. |
NA |
18 October 2016 |
No adverse environmental issue was
observed. |
NA |
25 October 2016 |
Open stockpile was found in Bridge A, the Contractor should cover the stockpile to avoid
surface runoff and dust impact. |
The open stockpile was removed. |
It was reminded that stagnant water
should be cleaned up to prevent mosquito breeding. |
Not required for reminder. |
9.2.11
General housekeeping such as daily site
tidiness and cleanliness should be
maintained for all Contracts. Furthermore, the Contractors were
reminded to implement Waste Management Plan of the Project.
Other Contracts
9.2.12
Since the construction work of Contract 5 has
substantially completed and Contract 4 has not commenced, no site inspection was
performed.
10.1.1
In
the Reporting Period, no summons and prosecution under the EM&A Programme
was lodged for Contracts 2, 3, 6, 7 and Contract SS C505. However, two (2) documented environmental
complaints were received. In brief,
one of the complaints was about transportation of dusty construction waste
material which related to Contract 6 and another complaint was about wastewater
discharge from construction site which related to Contracts 2 and 6. Investigation reports have been completed
by the ET and the detail of the complaints and the investigation results are
presented below.
Investigation Result for the Documented Complaints received by EPD on 20
October 2016 (Contracts 6)
10.1.2
A warning letter (ref.: EP560/G1/1(VII)) was issued
from EPD to CCKJV on 25 October 2016 regarding a dump truck vehicle (vehicle
registration mark: RX2229) carrying dusty construction waste materials
arisen under the subject account travelling to the North East New Territories
(NENT) Landfill on 20 October 2016 without proper cover.
10.1.3
Joint
site inspection was carried out by the RE, IEC, CCKJV and ET on 27 October 2016
for the complaint investigation. The aim of the inspection was to spot check
whether the skip of the
dump truck under the Contract were properly covered before leaving the site
until it reached the check point at NENT. The inspection area included the subject
site exit, Wo Keng Shan Road as well as NENT
Landfill. The observations during the site inspection are summarized in below.
(a)
At the
subject site exit (Ng Chow Road), all vehicles were
thoroughly washed in the wheel washing facilities implemented at the site exit.
(b)
There were two stationary frontline staff deployed at the site
exit to check whether the skip of the dump truck was properly covered and carry
out cleaning for all vehicles.
After final checking, trip ticket was given to the dump truck driver
after before it leaving the site.
(c)
All
dump trucks left the site were properly covered without leakage of dusty
materials and wastewater. The
concerned dump truck
vehicle (vehicle registration mark: RX2229) was spotted in the inspection and
it was noted that the skip this dump truck was well covered.
(d)
The
dump trucks travelling on Wo Keng Shan Road were
properly covered.
(e)
Inspection
inside NENT Landfill was unable to carry out as it was restricted to public
access. At the entrance of NENT
Landfill, there was queue of dump truck
vehicles with properly covered and some of them were belong to the Contract.
However, it was observed that one of the dump truck flipped over the skip cover
when queueing outside NENT and this dump truck was not belong
to the Contract after checking.
10.1.4
CCKJV has conducted an interview with the caught
dump truck drivers after receipt of the warning letter. According to the incident report
prepared by CCKJV, the dump truck driver had covered the dump skip before
leaving the site. However, the driver
unintentionally pressed the open button and triggered one side of the
mechanical cover when he travelling to NENT Landfill.
10.1.5
In our investigation, no dump trucks vehicles under
the Contract violated the legal requirement. As a preventive measures for ensuring
covering of skip and cleaning of vehicle leaving works area, the driver would
check whether dump skip was properly covered according to rear mirror of the
truck and two stationary frontline staff would conduct final checking at the
checking point of the site exit. The trip ticket will only be given to the
driver if vehicle is thoroughly cleaned and skip is properly covered before
leaving the site. It is considered
that the complaint was a single incident which resulted of careless mistake of
the dump truck driver.
10.1.6
As additional measures, CCKJV agreed to erect
signage at the site exit to aware all vehicles drivers to check the vehicles
were washed and well covered before leaving the construction. Moreover, CCKJV was advised to conduct
surprise check for the dump truck on regular basis (such as twice per month) to
ensure the dump trucks driver strictly follow all the procedure when carrying
dusty materials from the construction site to the disposal locations.
10.1.7
In response to the complaint, CCKJV has arranged a
specified training on topic of ¡§proper cover of dump trucks, wheel washing and
responsibility¡¨ to all sub-constructor representative of dump truck on 2
November 2016. The aim of the
training is to ensure all responsible parties are fully understand the
requirements and their duties, in particular, to ensure all dump trucks are
covered and checked when they leave the site. An incident report for uncovered dump
trucks was prepared by CCKJV and issued to EPD 2 November 2016 which included
the investigation result for the incident, interview record for RX2229 dump
truck driver and the specified training record.
Investigation Result for the Documented Complaints received by 1823 on 28
October 2016 (Contracts 2 and 6)
10.1.8
A complaint was received from 1823 on 28 October 2016
regard to muddy water discharged out of the construction sites near the traffic
light post at the junction of Sha Tau Kok Road and Wo Keng
Shan Road. The cumulated muddy
water splashed on the pedestrian when vehicles passing by the road which
causing inconvenience to the pedestrian and public.
10.1.9
Joint site inspection was carried out by RE, IEC,
CCKJV and ET on 3 November 2016 at the suspected four (4) site exits along the Sha
Tau Kok Road and Wo Keng Shan Road for the complaint
investigation. The aim of the
inspection was to check condition of the site exit and the implementation the
wheel washing facilities and to assess the possibility of muddy water discharge
out of the construction site to the public road. The observations during the site
inspection are summarized in below.
North Portal under Contract 2
10.1.10
The site exit of North Portal under Contract 2 is
located on Sha Tau Kok Road. As
observed during weekly site inspection, wheel washing
facilities were provided within the construction site. The vehicles after wheel washing were pass through a hard paved haul
road and reached the main site exit before leaving construction site. A cut-off drain was accompanied
at the exit to divert the runoff from the construction area. As advised by the
Contractor, manual water spraying was provided at the entrance of North Portal,
it is not a wheel washing facilites but to clean and tidy the site entrance as
needed. The condition of the site exit was clean and satisfactory and no trails of mud and muddy water were observed on
the adjacent Sha Tau Kok Road.
Proposed Sha Tau Kok Interchange under
Contract 6
10.1.11
The site exit of proposed Sha
Tau Kok Interchange under Contract 6 was located at the junction of Sha Tau Kok
Road and Wo Keng Shan Road. Wheel washing facilities was properly implemented
at the site exit and the area between the wheel washing bay and site exit was
hard paved. No trails of mud and
muddy water were observed on the adjacent Sha Tau Kok Road and Wo Keng Shan Road.
Wo Keng Shan Park under Contract 6
10.1.12
The site exit of Wo Keng
Shan Park under Contract 6 was located on Wo Keng
Shan Road. Wheel washing facilities was properly implemented
at the site exit and the area between the wheel washing bay and site exit was
hard paved. No trails of mud and
muddy water were observed on the adjacent Wo Keng
Shan Road.
10.1.13
South Portal and Site Office under Contract 6
10.1.14
The site exit of South Portal and Site Office under
Contract 6 was located on Wo Keng Shan Road. Wheel washing facilities was properly implemented
at the site exit and the area between the wheel washing bay and site exit was
hard paved. No trails of mud and
muddy water were observed on the adjacent Wo Keng
Shan Road.
10.1.15
In our investigation, the site exits near the
complaint location under the project were satisfactory and muddy water
discharge out of the construction site to the public roads was unlikely to
occur. It is considered that the
suspected muddy water discharge from the works area out to Sha Tau Kok Road and
Wo Keng Shan Road was unlikely due to the project.
10.1.16
As advised by both contractors, road washing/ cleaning
by water bowsers was provided along Wo Keng Shan Road
to Sha Tau Kok Road in every normal working day (Mon-Sat), except for rainy
day. Moreover, road sweeping would
be provided for the concerned roads twice a week. To address the complainant¡¦s concern,
the ET will keep closely inspection on the cleanliness situation on both roads
during weekly site inspection.
Table 10-1 Statistical
Summary of Environmental Complaints
Reporting Period |
Contract No |
Environmental
Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
19 May 2014 ¡V 30 Sep 2016 |
Contract 2 |
0 |
20 |
(9)Water Quality (8) Dust (3) Noise |
06 Nov 2013 ¡V 30 Sep 2016 |
Contract 3 |
0 |
4 |
(1) Dust (2) Water quality (1) Noise |
16 Aug 2013 ¡V 30 Sep 2016 |
Contract 5 |
0 |
4 |
(3) Dust (1) Noise |
16 Aug 2013 ¡V 30 Sep 2016 |
Contract 6 |
0 |
24 |
(18) Water Quality (5) Dust (1) Noise |
15 Feb 2016 ¡V 30 Sep 2016 |
Contract 7 |
0 |
0 |
N/A |
16 Aug 2013 ¡V 30 Sep 2016 |
SS C505 |
0 |
1 |
(1) Noise |
1 ¡V 31 Oct 2016 |
Contract 2 |
1 |
21 |
(10)Water Quality (8) Dust (3) Noise |
Contract 3 |
0 |
4 |
(1) Dust (2) Water quality (1) Noise |
|
Contract 6 |
2 |
26 |
(19) Water Quality (6) Dust (1) Noise |
|
Contract 7 |
0 |
0 |
N/A |
|
SS C505 |
0 |
0 |
N/A |
Table 10-2 Statistical
Summary of Environmental Summons
Reporting Period |
Contract No |
Environmental
Summons Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
19 May 2014 ¡V 30 Sep 2016 |
Contract 2 |
0 |
0 |
NA |
06 Nov 2013 ¡V 30 Sep 2016 |
Contract 3 |
0 |
0 |
NA |
16 Aug 2013 ¡V 30 Sep 2016 |
Contract 5 |
0 |
0 |
NA |
16 Aug 2013 ¡V 30 Sep 2016 |
Contract 6 |
0 |
0 |
NA |
15 Feb 2016 ¡V 30 Sep 2016 |
Contract 7 |
0 |
0 |
NA |
16 Aug 2013 ¡V 30 Sep 2016 |
SS C505 |
0 |
0 |
NA |
1 ¡V 31 Oct 2016 |
Contract 2 |
0 |
0 |
NA |
Contract 3 |
0 |
0 |
NA |
|
Contract 6 |
0 |
0 |
NA |
|
Contract 7 |
0 |
0 |
NA |
|
SS C505 |
0 |
0 |
NA |
Table 10-3 Statistical
Summary of Environmental Prosecution
Reporting Period |
Contract No |
Environmental
Prosecution Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
19 May 2014 ¡V 30 Sep 2016 |
Contract 2 |
0 |
0 |
NA |
06 Nov 2013 ¡V 30 Sep 2016 |
Contract 3 |
0 |
0 |
NA |
16 Aug 2013 ¡V 30 Sep 2016 |
Contract 5 |
0 |
0 |
NA |
16 Aug 2013 ¡V 30 Sep 2016 |
Contract 6 |
0 |
0 |
NA |
15 Feb 2016 ¡V 30 Sep 2016 |
Contract 7 |
0 |
0 |
NA |
16 Aug 2013 ¡V 30 Sep 2016 |
SS C505 |
0 |
0 |
NA |
1 ¡V 31 Oct 2016 |
Contract 2 |
0 |
0 |
NA |
Contract 3 |
0 |
0 |
NA |
|
Contract 6 |
0 |
0 |
NA |
|
Contract 7 |
0 |
0 |
NA |
|
SS C505 |
0 |
0 |
NA |
The Other Contracts
10.1.17
Since the construction works at the Contract
5 was substantially completed and Contract 4 has not yet commenced, no
environmental complaint, summons
and prosecution under the EM&A Programme are registered in the Reporting
Period.
11.1.1
The environmental mitigation measures that
recommended in the Implementation Schedule for Environmental Mitigation
Measures (ISEMM) in the approved EM&A Manual covered the issues of dust,
noise, water and waste and they are summarized presented in Appendix
M.
11.1.2
All contracts under the Project shall be
implementing the required environmental mitigation measures according to the approved
EM&A Manual as subject to the site condition. Environmental mitigation measures
generally implemented by Contracts 2, 3, 5, 6, 7 and Contract SS C505 in this
Reporting Period are summarized in Table 11-1.
Table 11-1 Environmental
Mitigation Measures
Issues |
Environmental
Mitigation Measures |
Water Quality |
¡P Wastewater to be treated by the
wastewater treatment facilities i.e. sedimentation tank or similar facility before
discharge. |
Air Quality |
¡P Maintain damp / wet surface
on access road ¡P Low vehicular speed within
the works areas. ¡P All vehicles must use wheel
washing facility before off site ¡P Sprayed water during
breaking works ¡P A
cleaning truck was regularly performed on the public road to prevent fugitive dust emission |
Noise |
¡P Restrain operation time of
plants from 07:00 to 19:00 on any working day except for Public Holiday and
Sunday. ¡P Keep good maintenance of
plants ¡P Place noisy plants away from
residence or school ¡P Provide noise barriers or
hoarding to enclose the noisy plants or works ¡P Shut down the plants when
not in used. |
Waste and Chemical Management |
¡P On-site sorting prior to
disposal ¡P Follow requirements and
procedures of the ¡§Trip-ticket System¡¨ ¡P Predict required quantity of
concrete accurately ¡P Collect the unused fresh
concrete at designated locations in the sites for subsequent disposal |
General |
¡P The site was generally kept
tidy and clean. |
11.2.1
As advised by the ER, the construction works
under Contract 5 was substantially completed on 31 August 2016. Construction activities for other
Contracts in the coming month are listed below:
Contract 2
Mid-Vent Portal |
Stud tunnel and cavern
excavation
Adit invert slab, water proofing
and lining
Ventilation building
superstructure and backfilling |
North Portal |
Slope stabilization &
retaining wall
Southbound TBM excavation
Northbound bench excavation
Tunnel enlargement and
construction of cross passage
Tunnel internal structure
and cross passage
Ventilation building
foundation |
South Portal |
Southbound and Northbound D&B
excavation
South ventilation building
superstructure
Tunnel invert, waterproofing
and lining |
Admin
Building |
Building superstructure and
external wall |
Contract 3
Cable detection and trial trenches
Demolition of existing vehicular bridge
Footbridge construction
Storm drains laying
Noise barrier construction
Pier / Pier Table construction
Pile cap works
Portal beam construction
Retaining Wall construction
Road works
Sewer works
Utilities duct laying
Viaduct segment erection
Water Main Laying
Contract 6
Slope Works
Bored Piling
Pile Cap Construction
Bridge Pier Construction
Segment section
Sewage Treatment Plant Construction
Tunnel Works
Contract 7
Piling Works at Bridge A and E
Pile caps construction at Bridge A, B,D and
E
Column construction at Bridge B, C and D
2nd floor construction of Bridge
C
Contract SS C505
General Site Set-up
Building no. 4, 5, 6, 7, 9, 10, 11 and 36
construction
Excavation waterproofing works for Building
no. 4, 6 & 11
Substructure for Building no.4,6&7
Tower crane operation
Bridge construction works including
construction of bridge column, retaining wall, pile cap and pier
Underground drainage works
Prototype ¡§A¡¨ & ¡§B¡¨ construction works
Mock up for south entrance double curve
cladding
Formwork and falsework for PTB¡¦s slab
construction
Construction PTB M/F & 1/F flat slab
Steel beam works for maintenance platform
for PTB
Pile cap construction for PTB, including
excavation and backfilling works
Bridge deck construction for Bridges 1 - 5
Footing construction
11.3.1
Key
issues to be considered in the coming month for Contracts 2, 3, 6, 7 and SS
C505 include:
Implementation of control measures for rainstorm;
Regular clearance of stagnant water during wet season;
Implementation of dust suppression measures at all
times;
Potential wastewater quality impact due to surface
runoff;
Potential fugitive dust quality impact due from the
dry/loose/exposure soil surface/dusty material;
Disposal of empty engine oil containers within site
area;
Ensure dust suppression measures are implemented
properly;
Sediment catch-pits and silt removal
facilities should be regularly maintained;
Management of chemical wastes;
Discharge of site effluent to the nearby
wetland, stockpiling or disposal of materials, and any dredging or construction
area at this area are prohibited;
Follow-up of improvement on general waste
management issues; and
Implementation of construction noise
preventative control measures
11.3.2
Since the construction work of Contract 4 has
not commenced, no
environmental issue is presented.
12.1.1
This is the 39th monthly EM&A report presenting the monitoring
results and inspection findings for the Reporting Period from 1 to 31 October 2016.
12.1.2
For
air quality monitoring, no 1-hour and 24-hour TSP monitoring results triggered
the Action or Limit Levels were recorded. No NOEs or
the associated corrective actions were therefore issued.
12.1.3
No noise complaint (which is an Action Level
exceedance) was received and no construction noise measurement results that
exceeded the Limit Level were recorded in the Reporting Period. No NOEs or the associated corrective actions were therefore
issued.
12.1.4
For water quality monitoring, thirty-seven (37)
LL exceedances, namely seventeen (17) LL exceedance of turbidity and twenty (20)
LL exceedances of Suspended Solids were recorded for the Project. Investigations reports revealed that all
exceedances on 4 to 18 October 2016 were not project related, except for
exceedances at WM2A(a) on 4 Oct were due to damage
pipe under C6. Exceedances on 18 to
31 October 2016 at WM2A(a) are under investigated by
ET. The completed IRs had submitted
to relevant parties.
12.1.5
No
environmental summons or successful prosecutions were recorded in the Reporting
Period.
12.1.6
In this Reporting Period, two (2) documented
environmental complaints were received.
One of the complaints was about transportation of dusty construction
waste material and investigation result revealed that the complaint was related
to works under Contract 6. Another
complaint was about wastewater discharge from construction site near the works
areas of Contracts 2 and 6 and investigation result revealed that the complaint
was not related to works under Contracts.
12.1.7
During
the Reporting Period, weekly joint site inspection by the RE, IEC, ET with the
relevant Main-contractor were carried out for Contracts 2, 3, 6, 7 and SS C505
in accordance with the EM&A Manual stipulation. No non-compliance observed during the
site inspection.
12.2.1
During
dry season, special attention should be paid on the potential construction dust
impact since most of the construction sites are adjacent to villages. The
Contractor should fully implement the construction dust mitigation measures
properly.
12.2.2
Preventive
measures for muddy water or other water pollutants from site surface flow to local
stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River or public area
should be properly maintained. The
Contractors should paid special attention on water quality mitigation measures and
fully implement according ISEMM of the EM&A Manual, in particular for
working areas near Ma Wat Channel and Ping Yuen River. Moreover, all effluent discharge shall
be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage
and Sewerage Systems, inland and Coastal Waters criteria or discharge permits
stipulation.
12.2.3
Construction
noise would be a key environmental issue during construction work of the
Project. Noise mitigation measures
such as using quiet plants should be implemented in accordance with the
EM&A requirement.
12.2.4
Furthermore, daily cleaning and weekly tidiness shall be properly performed
and maintained. In addition, mosquito
control should be kept to prevent mosquito breeding on site.