|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report (No.46)
¡V May 2017 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
13 June 2017 |
TCS00694/13/600/R1020v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
7 June 2017 |
First
Submission |
2 |
13 June 2017 |
Amended according to the IEC¡¦s comments on 8 June
2017 |
|
|
|
executive summary
ES01
This is the 46th monthly EM&A
report presenting the monitoring results and inspection findings for the reporting
period from 1 to 31 May 2017 (hereinafter ¡¥the Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08),
Contract 3 (CV/2012/09), Contract 4 (NE/2014/02),
Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and
an ArshSD contract (Contract SS C505).
ES03
In the Reporting Period, the major construction
works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project included Contract 2, Contract 3, Contract 4, Contract 6, Contract 7 and Contract SS C505. Environmental monitoring activities
under the EM&A programme in the Reporting Period are summarized in the
following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
135 |
24-hour TSP |
9 |
45 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
45 |
Water Quality |
Water in-situ
measurement and/or sampling |
WM1 & WM1-C |
14 Scheduled & 6 extra |
WM2A(a) & WM2A-Cx |
14 Scheduled & 4 extra |
||
WM2B & WM2B-C |
(*) 14 Scheduled |
||
WM3x &WM3-C |
14 Scheduled & 2 extra |
||
WM4, WM4-CA &WM4-CB |
14 Scheduled & 1 extra |
||
Ecology |
Woodland compensation i) General Health condition of planted species ii) Survival of planted species |
9 Quadrats |
0 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and
Auditing |
Contract 2 |
4 |
Contract 3 |
5 |
||
Contract 4 (#) |
3 |
||
Contract 6 |
4 |
||
Contract 7 |
5 |
||
Contract SS C505 (#) |
5 |
Note: Extra monitoring day was due to measurement
results exceedance
(#) IEC only
joined one (1) event of site inspection for Contracts 4 and SS C505.
(*) Water sampling was unable to carry out at WM2B and
WM2B-C due to shallow water (water depth under 150mm)
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no air quality and construction noise exceedances were recorded. For water quality monitoring, thirty-one (31) Action level/ Limit Level exceedances were recorded under the Project.
The summary of exceedance in the Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
|||
NOE Issued |
Investigation Result |
Project related exceedance |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
0 |
14 |
14 |
-
exceedances
recoded on 4 to 19 May 2017 were
concluded as non-project related -
exceedances recorded on 23 to 29 May 2017 were under investigation. |
0 |
The Contractors were reminded to implement water quality mitigation
measures in accordance with ISEMM of the EM&A Manual requirements |
|
SS |
1 |
16 |
17 |
0 |
Environmental
Complaint
ES05
In
this Reporting Period, no environmental
complaints were received under the EM&A program.
Notification of Summons and Successful Prosecutions
ES06
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
ES07
No reporting changes
were made in the Reporting Period.
ES08
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 5, 12, 19 and 26
May 2017. No non-compliance was noted during the
site inspection.
ES09
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 2, 8, 17, 22 and
29 May 2017. No non-compliance was noted during the site
inspection.
ES10
For Contract 4, there
were only minor construction activities, such as preparation work for E&M
installation, carried out on the 1st week of May 2017,
therefore, the site inspection was commenced on the 2nd week of May
2017. In the
Reporting, joint site
inspection for Contract 4 to evaluate
the site environmental performance has been carried out by the RE, ET and the
Contractor on 11, 18 and 26 May
2017 in which IEC joined the site inspection on 26
May 2017. No non-compliance was noted.
ES11
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 4, 11, 18, 25 May 2017. No non-compliance was noted during the site
inspection.
ES12
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
7 has been carried out by the RE, IEC, ET and the Contractor on 2, 9, 16, 23 and
31 May 2017. No non-compliance
was noted during the site inspection.
ES13
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, ET and the Contractor on 5, 10, 17, 27 and
31 May 2017 in which IEC joined the site inspection on 31
May 2017. No non-compliance was noted during the site
inspection.
Future Key Issues
ES14
During wet season, preventive measures for
muddy water or other water pollutants from site surface flow to local stream such
as Kong Yiu Channel, Ma Wat Channel, Ping
Yuen River, Kwan Tei River or public area should be
properly maintained. The Contractors should paid special
attention on water quality
mitigation measures and fully implement according ISEMM of the EM&A Manual,
in particular for working areas near Ma Wat Channel and Ping Yuen River.
ES15
In addition, all effluent
discharge shall be ensure to fulfill Technical Memorandum of Effluent
Discharged into Drainage and Sewerage Systems, inland and Coastal Waters criteria
or discharge permits stipulation.
ES16
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
ES17
Since most of construction sites under the Project are
located adjacent to villages, the Contractors should fully
implement air quality mitigation measures to reduce construction dust emission.