Dragages QSE Lock-up

Name of Department : CEDD Contract No./ Work Order No. : CV/2012/08

Appendix I - Monthly Summary Waste Flow Table for 2017

(All quantities shall be rounded off to 3 decimal places)

Month Actual Quantities of Inert C&D Materials Generated / Imported (in '000 m3) Actual Quantities of Other C&D Materials / Wastes Generated
Total Quantities Generated [a+b+c+d) Broken Concrete (including rock for recycling into aggregates) (a) Reused in the Contract (b) Reused in Other Projects (c) Disposed as Public Fill (d) Imported C&D Material Metal (in '000kg) Paper/ Cardboard Packaging (in '000kg) Plastic (bottles/containers, plastic sheets/ foams from package material) (in '000kg) Chemical Waste (in '000kg) Others (e.g. General Refuse etc.) (in '000m3)
January 68.1954 0.0000 1.9613 27.9028 39.3063 1.7050 162.4150 0.3600 1.9179 1.7600 0.3210
February 85.7063 0.0000 1.4795 29.8662 54.2343 1.6040 67.5900 0.3000 2.1663 4.3480 0.3365
March 28.3513 0.0000 0.5425 28.2593 2.8910 1.5500 137.7800 0.3000 2.0421 4.0720 0.4167
April 0.0000
May 0.0000
June 0.0000
Half-year total 182.2530 0.0000 3.9834 82.5798 95.6898 4.8590 367.7850 0.9600 2.0179 10.1800 0.6575
July 0.0000
August 0.0000
September 0.0000
October 0.0000
November 0.0000
December 0.0000
Yearly Total 182.2530 0.0000 3.9834 82.5798 95.6898 4.8590 367.7850 0.9600 2.0179 10.1800 0.6575

(All quantities shall be rounded off to 3 decimal places)

Year Actual Quantities of Inert C&D Materials Generated / Imported (in '000 m3) Actual Quantities of Other C&D Materials / Wastes Generated
Total Quantities Generated [a+b+c+d) Broken Concrete (including rock for recycling into aggregates) (a) Reused in the Contract (b) Reused in Other Projects (c) Disposed as Public Fill (d) Imported C&D Material Metal (in '000kg) Paper/ Cardboard Packaging (in '000kg) Plastic (bottles/containers, plastic sheets/ foams from package material) (in '000kg) Chemical Waste (in '000kg) Others (e.g. General Refuse etc.) (in '000m3)
2013 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
2014 425.4406 0.0000 2.7362 376.3945 46.3099 5.6245 3.2100 0.4390 0.0070 10.8800 2.2609
2015 570.9459 0.0000 20.8159 543.2162 6.9138 4.5492 14.1300 3.9220 11.9700 16.1920 1.1696
2016 905.0989 0.0000 7.4372 427.7834 469.8783 24.8350 259.2290 3.8500 18.7262 34.2936 1.9720
2017 182.2530 0.0000 3.9834 82.5798 95.6898 4.8590 367.7850 0.9600 2.0179 10.1800 0.6575
2018
Total 2083.7384 0.0000 34.9726 1429.9739 618.7918 39.8677 644.3540 9.1710 32.7211 71.5456 6.0600
Remark:
1) Density of C&D material to be 2.2 metric ton/m3 3) Density of Spent Oil to be 0.88 metric ton/m3
2) Density of General Refuse to be 1.6 metric ton/m3

Name of Department: CEDD Contract No.: CV/2012/09

Monthly Summary Waste Flow Table for 2017 (year)

Month Actual Quantities of Inert C&D Materials Generated Monthly Actual Quantities of C&D Wastes Generated Monthly
Total Quantity Generated Hard Rock and Large Broken Concrete Reused in the Contract Reused in other Projects Disposed as Public Fill Imported Fill Metals Paper/ cardboard packaging Plastics Chemical Waste Others, e.g. general refuse
(in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in m3) (in '000m3)
Jan 1.150 0.204 0.150 0.000 0.796 1.150 0.000 0.000 0.001 0.000 0.170
Feb 1.160 0.308 0.192 0.000 0.660 0.926 0.000 0.000 0.001 0.000 0.140
Mar 2.287 0.565 0.060 0.000 1.662 1.055 0.000 0.000 0.000 0.000 0.115
Apr
May
Jun
Sub-total 4.597 1.077 0.402 0.000 3.118 3.131 0.000 0.000 0.002 0.000 0.425
Jul
Aug
Sep
Oct
Nov
Dec
Total 4.597 1.077 0.402 0.000 3.118 3.131 0.000 0.000 0.002 0.000 0.425

Note: 1. Assume the density of soil fill is 2 ton/m3 .

  1. Assume the density of rock and broken concrete is 2.5 ton/m3 .
  2. Assume each truck of C&D wastes is 5m3 .
  3. The inert C&D materials except slurry and bentonite are disposed at Tuen Mun 38.
  4. The slurry and bentonite are disposed at Tseung Kwun O 137.
  5. The non-inert C&D wastes are disposed at NENT.
  6. Assume the density of metal is 7,850 kg/m3 .
  7. Assume the density of plastic is 941 kg/m3.

Monthly Summary Waste Flow Table for 2017 (year)

Name of Person completing the record: K.M. Lui (EO) Project : Liangtang / Heung Yuen Wai Boundary Control Point Site Formation and Infrastructure Works – Contract 6 Contract No.: CV/2013/08

Month Actual Quantities of Inert C&D Materials Generated Monthly Actual Quantities of C&D Wastes Generated Monthly
Total Quantity Generated Hard Rock and Large Broken Concrete Reused in the Contract Reused in other Projects Disposed as Public Fill Imported Fill Metals Paper/ cardboard packaging Plastics (see Note 3) Chemical Waste Others, e.g. general refuse
(in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in ‘000m3) (in '000 kg) (in '000kg) (in '000kg) (in '000kg) (in ‘000 m3)
Jan 40.128 0 19.297 6.067 14.764 0 0 0.171 0 0 0.065
Feb 48.065 0 16.328 7.123 24.614 0 0 0.294 0 0 0.107
Mar 28.540 0 0 0 28.540 0 0 0 0 0 0.217
Apr
May
Jun
Sub-total 116.733 0 35.625 13.19 67.918 0 0 0.465 0 0 0.389
Jul
Aug
Sep
Oct
Nov
Dec
Total 859.895 0 119.316 211.482 529.097 53.939 0 3.238 0.007 33.755 5.241

Notes: (1) The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site.

(2)
Plastics refer to plastic bottles/containers, plastic sheets/ foam from packaging materials.
(3)
Broken concrete for recycling into aggregates.
Appendix I

MONTHLY SUMMARY WASTE FLOW TABLE

Name of Department: CEDD Liantang/ Heung Yuen Wai Boundary Control Point

Contract Title: Contract No.: NE/2014/03

Site Formation and Infrastructure Works – Contract 7

Monthly Summary Waste Flow Table for 2017 (year)

Month Actual Quantities of Inert C&D Materials Generated Monthly Actual Quantities of Inert C&D Wastes Generated Monthly
Total Quantity Generated Hard Rock and Large Broken Concrete Contract Reused in the Reused in other Projects Public Fill Disposed as Imported Fill Metals Paper/cardboard packaging Plastic (see Note 3) Chemical Waste Others, e.g. general refuse
(in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000m3) (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000m3)
Jan 0 0 0 0 0 0 0.1 0.05 0.001 0 0.01
Feb 0 0 0 0 0 0 0.5 0.04 0.001 0 0.015
Mar 0.822 0 0 0 0.822 0 2.2 0.04 0.001 0 0.025
Apr
May
June
Sub-total 0.822 0 0 0 0.822 0 2.8 0.13 0.003 0 0.05
July
Aug
Sept
Oct
Nov
Dec
Total 0.822 0 0 0 0.822 0 2.8 0.13 0.003 0 0.05

Notes: (1) The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site.

(2) Plastics refer to plastic bottles/containers, plastic sheets/foam from packaging material.

Architectural Services Department Form No. D/OI.03/09.002

SSC505

Contract No./ Works Order No.: -

Monthly Summary Waste Flow Table for 201 7[year] [to be submitted not later than the 15thday of each month following reporting month] (All quantities shall be rounded off to 3 decimal places.)

Month Actual Quantities of Inert Construction Waste Generated Monthly
(a)=(b)+(c)+(d)+(e) Total Quantity Generated (b) Broken Concrete (see Note 4) (c) Reused in the Contract (d) Reused in other Projects (e) Disposed of as Public Fill
(in ‘000m3) (in ‘000m3) (in ‘000m3) (in ‘000m3) (in ‘000m3)
Jan 3.160 0 2.003 0 1.157
Feb 1.374 0 0.249 0 1.1245
Mar 0.548 0 0.054 0 0.494
Apr - - - - -
May - - - - -
Jun - - - - -
Sub-total 5.0815 0 2.306 0 2.7755
Jul - - - - -
Aug - - - - -
Sep - - - - -
Oct - - - - -
Nov - - - - -
Dec - - - - -
Total 5.0815 0 2.306 0 2.7755

Architectural Services Department First Issue Date -20 : 07 : 2009 Standard Form No. D/OI.03/09.002 Current Issue Date -21 : 09 : 2011

Page 1

Architectural Services Department Form No. D/OI.03/09.002
Month Actual Quantities of Non-inert Construction Waste Generated Monthly
Timber Metals Paper/ cardboard packaging Plastics (see Note 3) Chemical Waste Other Recyclable Materials _________________ (see Page 3) General Refuse disposed of at Landfill
(in ‘000kg) (in ‘000kg) (in ‘000kg) (in ‘000kg) (in ‘000kg) (in ‘000kg) (in ‘000m3)
generated recycled generated recycled generated recycled generated recycled generated recycled generated recycled generated
Jan 0 0 458.15 458.15 0.560 0.560 0.058 0.058 0.000 0.000 0.024 0.024 0.481
Feb 0 0 177.18 177.18 0.370 0.370 0.036 0.036 0.000 0.000 0.008 0.008 0.280
Mar 0 0 97.37 97.37 3.380 3.380 1.573 1.573 0.000 0.000 0.0355 0.0355 0.4225
Apr - - - - - - - - - - - - -
May - - - - - - - - - - - - -
Jun - - - - - - - - - - - - -
Sub-total 0 0 732.70 732.70 4.310 4.310 1.667 1.667 0.000 0.000 0.068 0.068 1.183
Jul - - - - - - - - - - - - -
Aug - - - - - - - - - - - - -
Sep - - - - - - - - - - - - -
Oct - - - - - - - - - - - - -
Nov - - - - - - - - - - - - -
Dec - - - - - - - - - - - - -
Total 0 0 732.70 732.70 4.310 4.310 1.667 1.667 0.000 0.000 0.068 0.068 1.183

Architectural Services Department First Issue Date -20 : 07 : 2009 Standard Form No. D/OI.03/09.002 Current Issue Date -21 : 09 : 2011

Page 2

Architectural Services Department Form No. D/OI.03/09.002
Description of mode and details of recycling if any for the month e.g. XX kg of used timber was sent to YY site for transformation into fertilizers
16.5kg of cans and 3.38tons of paper were sent to Kong Han for recycling. 1.573tons of plastics (bottles and water-filled barrier) were sent to Action Health and Forest Hill for recycling. 97.37 tons of scrap metals from LCAL.
Notes: (1) The performance targets are given in the Particular Specification on Environmental Management Plan.
(2) The waste flow table shall also include construction waste that are specified in the Contract to be imported for use at the site.
(3) Plastics refer to plastic bottles/containers, plastic sheets/foam from packaging material.
(4) Broken concrete for recycling into aggregates.
(5) If necessary, use the conversion factor: 1 full load of dumping truck being equivalent to 6.5 m3 by volume.

Architectural Services Department First Issue Date -20 : 07 : 2009 Standard Form No. D/OI.03/09.002 Current Issue Date -21 : 09 : 2011

Page 3