Job No.: TCS00694/13

 

 

 

 

 

 

 

 

 

Agreement No. CE 45/2008 (CE)

Liantang/Heung Yuen Wai

Boundary Control Point and Associated Works

 

 

 

 

 

 

 

 

 

Monthly Environmental Monitoring and Audit Report (No.35) ¡V June 2016

 

 

 

 

 

 

 

 

Prepared For

 

 

 

 

Civil Engineering and Development Department (CEDD)

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

14 July 2016

TCS00694/13/600/R0460v2

Winnie Chiu

 (Assistant Environmental Consultant)

Tam Tak Wing

(Environmental Team Leader)

 

Version

Date

Remarks

1

11 July 2016

First Submission

2

14 July 2016

Amended against IEC¡¦s comments on 12 July 2016

 

 

 


 

 

 

 

 

 

executive summary

ES01            This is the 35th monthly EM&A report presenting the monitoring results and inspection findings for the reporting period from 1 to 30 June 2016 (hereinafter ¡¥the Reporting Period¡¦).

 

Environmental Monitoring and Audit Activities

ES02            To facilitate the project management and implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (TCSS), Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD contract (Contract SS C505).

 

ES03            In the Reporting Period, the construction works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project currently included Contract 2, Contract 3, Contract 5, Contract 6, Contract 7 and Contract SS C505.  Environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the following table.

 

Environmental Aspect

Environmental Monitoring Parameters / Inspection

Reporting Period

Number of Monitoring Locations to undertake

Total Occasions  

Air Quality

1-hour TSP

9

150

24-hour TSP

9

50

Construction Noise

Leq(30min) Daytime

10

45

Water Quality

Water in-situ measurement and/or sampling

WM1 & WM1-C,

13 Scheduled & 1 extra

WM2A & WM2A-C

13 Scheduled & 7 extra

WM2B & WM2B-C

13 Scheduled & 1 extra

WM3 &WM3-C

13 Scheduled & 0 extra

WM4, WM4-CA &WM4-CB

13 Scheduled & 1 extra

Joint Site Inspection / Audit

IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing

Contract 2

5

Contract 3

4

Contract 5

4

Contract 6

5

Contract 7

4

Contract SS C505

5

Note: Extra monitoring day was due to measurement results exceedance

One scheduled day and one extra day were unsuccessful conducted water quality monitoring at WM2A

 

 

Breach of Action and Limit (A/L) Levels

ES04            In the Reporting Period, no air quality exceedance and one construction noise exceedance was registered for the Project. For water quality monitoring, a total of thirty-two (31) Limit Level (LL) exceedances and one (1) Action Level (AL) exceedance, namely fifteen (15) LL exceedances and one (1) AL exceedances of turbidity and sixteen (16) LL exceedances of Suspended Solids.  The summary of exceedance in the Reporting Period is shown below.

 

 

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation Result

Corrective Actions

Air Quality

1-hour TSP

0

0

0

--

--

24-hour TSP

0

0

0

--

--

Construction Noise

Leq(30min) Daytime

1

0

0

The noise complaint is not related to CEDD¡¦s Contracts and the complaint is under investigation.

--

Water Quality

DO

0

0

0

--

--

Turbidity

1

15

16

Eight exceedances are not due to the project construction activities. Eight exceedances are due to the project construction activities.

The relevant Contractor  shall implemented water quality mitigation measures in accordance with ISEMM of the EM&A Manual requirements

SS

0

16

16

Eight exceedances are not due to the project construction activities. Eight exceedances are due to the project construction activities.

 

Environmental Complaint

ES05            In this Reporting Period, three (3) documented environmental complaints were received by 1823. The complaint received on 20 June 2016 regarding noise nuisance from Lain Tang Construction work is under investigation.

 

Notification of Summons and Successful Prosecutions

ES06            No environmental summons or successful prosecutions were recorded in the Reporting Period.  

 

Reporting Change

ES07            No reporting changes were made in the Reporting Period.

 

Site Inspection

ES08            In this Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 2 has been carried out by the RE, IEC, ET and the Contractor on 3, 10, 17, 24, 29 June 2016.  No non-compliance was noted.

 

ES09            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 3 has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 22, 27 June 2016.  No non-compliance was noted.

 

ES10            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 5 has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 22, 28 June 2016.  No non-compliance was noted.

 

ES11            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 6 has been carried out by the RE, IEC, ET and the Contractor on 2, 10, 16, 23, 30 June 2016.  No non-compliance was noted.

 

ES12            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract SS C505 has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 15, 22, 29 June 2016.  No non-compliance was noted.

 

ES13            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 7 has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 22, 28 June 2016.  No non-compliance was noted.

Future Key Issues

ES14            As wet season has come, preventive measures for muddy water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River or public area would be the key issue.  The Contractors should paid special attention on water quality mitigation measures and fully implement according ISEMM of the EM&A Manual, in particular for working areas near Ma Wat Channel and Ping Yuen River.  Moreover, all effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland and Coastal Waters criteria or discharge permits stipulation.

 

ES15            Construction noise would be a key environmental issue during construction work of the Project.  Noise mitigation measures such as using quiet plants should be implemented in accordance with the EM&A requirement.

 

ES16            Since most of construction sites under the Project are located adjacent to villages, the Contractors should fully implement air quality mitigation measures to reduce construction dust emission.


 

 

 

Table of Contents

1     Introduction   1

1.1            Project Background   1

1.2            Report Structure  1

2     Project Organization and Construction progress  3

2.1            Construction Contract Packaging   3

2.2            Project Organization   5

2.3            Concurrent Projects  7

2.4            Construction Progress  7

2.5            Summary of Environmental Submissions  9

3     Summary of Impact Monitoring Requirements  14

3.1            General  14

3.2            Monitoring Parameters  14

3.3            Monitoring Locations  14

3.4            Monitoring Frequency and Period   16

3.5            Monitoring Equipment  17

3.6            Monitoring Methodology   19

3.7            Equipment Calibration   21

3.8            Derivation of Action/Limit (A/L) Levels  21

3.9            Data Management and Data QA/QC Control  22

4     Air Quality Monitoring   23

4.1            General  23

4.2            Air Quality Monitoring Results in Reporting Month   23

5     Construction Noise Monitoring   26

5.1            General  26

5.2            Noise Monitoring Results in Reporting Month   26

6     Water Quality Monitoring   26

6.1            General  27

6.2            Results of Water Quality Monitoring   27

7     Waste Management   32

7.1            General Waste Management  32

7.2            Records of Waste Quantities  32

8     Site Inspection   33

8.1            requirements  33

8.2            Findings / Deficiencies During the Reporting Month   33

9     Environmental Complaint and Non-Compliance   41

9.1            Environmental Complaint, Summons and Prosecution   38

10   Implementation Status of Mitigation Measures  47

10.1          General Requirements  47

10.2          Tentative Construction Activities in the Coming Month   47

10.3          Key Issues for the Coming Month   49

11   Conclusions and Recommendations  50

11.1          Conclusions  50

11.2          Recommendations  50

 


List of TABLES

Table 2-1        Status of Environmental Licenses and Permits of the Contracts

Table 3-1        Summary of EM&A Requirements

Table 3-2        Impact Monitoring Stations - Air Quality

Table 3-3        Impact Monitoring Stations - Construction Noise

Table 3-4        Impact Monitoring Stations - Water Quality

Table 3-5        Air Quality Monitoring Equipment

Table 3-6        Construction Noise Monitoring Equipment

Table 3-7        Water Quality Monitoring Equipment

Table 3-8        Action and Limit Levels for Air Quality Monitoring

Table 3-9        Action and Limit Levels for Construction Noise

Table 3-10      Action and Limit Levels for Water Quality

Table 4-1        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM1a

Table 4-2        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM2

Table 4-3        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM3

Table 4-4        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM4B

Table 4-5        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM5a

Table 4-6        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM6

Table 4-7        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM7a

Table 4-8        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM8

Table 4-9        Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b

Table 5-1        Summary of Construction Noise Monitoring Results (Contract 3 and 5)

Table 5-2        Summary of Construction Noise Monitoring Results (Contract 2 and 6)

Table 6-1        Summary of Water Quality Monitoring Results for Contract 2 and 3

Table 6-2        Summary of Water Quality Monitoring Results for Contract 5 and SS C505

Table 6-3        Summary of Water Quality Monitoring Results for Contract 6

Table 6-4        Summary of Water Quality Monitoring Results for Contract 2 and 6

Table 6-5        Breaches of Water Quality Monitoring Criteria in Reporting Period

Table 6-6        Summary of Water Quality Exceedance in the Reporting Period

Table 7-1        Summary of Quantities of Inert C&D Materials

Table 7-2        Summary of Quantities of C&D Wastes

Table 8-1        Site Observations for Contract 2

Table 8-2        Site Observations for Contract 3

Table 8-3        Site Observations for Contract 5

Table 8-4        Site Observations for Contract 6

Table 8-5        Site Observations for Contract SS C505

Table 8-6        Site Observations for Contract 7

Table 9-1        Statistical Summary of Environmental Complaints

Table 9-2        Statistical Summary of Environmental Summons

Table 9-3        Statistical Summary of Environmental Prosecution

Table 10-1      Environmental Mitigation Measures

 

List of Appendices

Appendix A    Layout Plan of the Project

Appendix B    Organization Chart

Appendix C    3-month rolling construction program

Appendix D    Designated Monitoring Locations as Recommended in the Approved EM&A Manual

Appendix E    Monitoring Locations for Impact Monitoring

Appendix F     Calibration Certificate of Monitoring Equipment and HOKLAS-accreditation Certificate of the Testing Laboratory

Appendix G    Event and Action Plan

Appendix H    Impact Monitoring Schedule

Appendix I     Database of Monitoring Result

Appendix J     Graphical Plots for Monitoring Result

Appendix K    Meteorological Data

Appendix L    Waste Flow Table

Appendix M   Implementation Schedule for Environmental Mitigation Measures

Appendix N    Investigation Report for Exceedance

 

 

 

 


1                    Introduction

1.1                       Project Background

1.1.1                 Civil Engineering and Development Department is the Project Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE) Liantang / Heung Yuen Wai Boundary Control Point and Associated Works, which is a Designated Project to be implemented under Environmental Permit number EP-404/2011/C granted on 12 March 2015. 

 

1.1.2                 The Project consists of two main components: Construction of a Boundary Control Point (hereinafter referred as ¡§BCP¡¨); and Construction of a connecting road alignment.  Layout plan of the Project is shown in Appendix A.

 

1.1.3                 The proposed BCP is located at the boundary with Shenzhen near the existing Chuk Yuen Village, comprising a main passenger building with passenger and cargo processing facilities and the associated customs, transport and ancillary facilities.  The connecting road alignment consists of six main sections:

1)             Lin Ma Hang to Frontier Closed Area (FCA) Boundary ¡V this section comprises at-grade and viaducts and includes the improvement works at Lin Ma Hang Road;

2)             Ping Yeung to Wo Keng Shan ¡V this section stretches from the Frontier Closed Area Boundary to the tunnel portal at Cheung Shan and comprises at-grade and viaducts including an interchange at Ping Yeung;

3)             North Tunnel ¡V this section comprises the tunnel segment at Cheung Shan and includes a ventilation building at the portals on either end of the tunnel;

4)             Sha Tau Kok Road ¡V this section stretches from the tunnel portal at Wo Keng Shan to the tunnel portal south of Loi Tung and comprises at-grade and viaducts including an interchange at Sha Tau Kok and an administration building;

5)             South Tunnel ¡V this section comprises a tunnel segment that stretches from Loi Tung to Fanling and includes a ventilation building at the portals on either end of the tunnel as well as a ventilation building in the middle of the tunnel near Lau Shui Heung;

6)             Fanling ¡V this section comprises the at-grade, viaducts and interchange connection to the existing Fanling Highway.

 

1.1.4                 Action-United Environmental Services & Consulting has been commissioned as an Independent ET to implement the relevant EM&A program in accordance with the approved EM&A Manual, as well as the associated duties.  As part of the EM&A program, the baseline monitoring has carried out between 13 June 2013 and 12 July 2013 for all parameters including air quality, noise and water quality before construction work commencement.  The Baseline Monitoring Report summarized the key findings and the rationale behind determining a set of Action and Limit Levels (A/L Levels) from the baseline data.  Also, the Project baseline monitoring report which verified by the IEC has been submitted to EPD on 16 July 2013 for endorsement.  The major construction works of the Project was commenced on 16 August 2013 in accordance with the EP Section 5.3 stipulation.

 

1.1.5                 This is 35th monthly EM&A report presenting the monitoring results and inspection findings for reporting period from 1 to 30 June 2016.

 

1.2                       Report Structure

1.2.1                 The Monthly Environmental Monitoring and Audit (EM&A) Report is structured into the following sections:-

Section 1     Introduction

Section 2     Project Organization and Construction Progress

Section 3     Summary of Impact Monitoring Requirements

Section 4     Air Quality Monitoring

Section 5     Construction Noise Monitoring

Section 6     Water Quality Monitoring

Section 7     Waste Management

Section 8     Site Inspections

Section 9     Environmental Complaints and Non-Compliance

Section 10   Implementation Status of Mitigation Measures

Section 11   Conclusions and Recommendations

 

 

 


2                             Project Organization and Construction progress

2.1                       Construction Contract Packaging

2.1.1                 To facilitate the project management and implementation, the Project would be divided by the following contracts:

¡P              Contract 2 (CV/2012/08)

¡P              Contract 3 (CV/2012/09)

¡P              Contract 4 (NE/2014/02)

¡P              Contract 5 (CV/2013/03)

¡P              Contract 6 (CV/2013/08)

¡P              Contract 7 (NE/2014/03)

¡P              ArchSD Contract No. SS C505

 

2.1.2                 The details of each contracts is summarized below and the delineation of each contracts is shown in Appendix A.

 

Contract 2 (CV/2012/08)

2.1.3                 Contract 2 has awarded in December 2013 and construction work was commenced on 19 May 2014.  Major Scope of Work of the Contract 2 is listed below:

¡P                construction of an approximately 5.2km long dual two-lane connecting road (with about 0.4km of at-grade road and 4.8km of tunnel) connecting the Fanling Interchange with the proposed Sha Tau Kok Interchange;

¡P                construction of a ventilation adit tunnel and the mid-ventilation building;

¡P                construction of the north and south portal buildings of the Lung Shan Tunnel and their associated slope works;

¡P                provision and installation of ventilation system, E&M works and building services works for Lung Shan tunnel and Cheung Shan tunnel and their portal buildings;

¡P                construction of Tunnel Administration Building adjacent to Wo Keng Shan Road and the associated E&M and building services works; and

¡P                construction of associated footpath, slopes, retaining structures, drainage, sewerage, waterworks, landscaping works and other ancillary works.

 

Contract 3 (CV/2012/09)

2.1.4                 Contract 3 was awarded in July 2013 and construction work was commenced on 5 November 2013.  Major Scope of Work of the Contract 3 is listed below:

¡P                construction of four link roads connecting the existing Fanling Highway and the south portal of the Lung Shan Tunnel;

¡P                realignment of the existing Tai Wo Service Road West and Tai Wo Service Road East;

¡P                widening of the existing Fanling Highway (HyD¡¦s entrustment works);

¡P                demolishing existing Kiu Tau vehicular bridge and Kiu Tau footbridge and reconstruction of the existing Kiu Tau Footbridge (HyD¡¦s entrustment works); and

¡P                construction of associated footpath, slopes, retaining structures, drainage, sewerage, waterworks, landscaping works and other ancillary works.

 

Contract 4 (NE/2014/02)

2.1.5                 Contract 4 has awarded in mid-April 2016. However, the major construction work still is not yet commenced.  The scope of work of the Contract 4 includes:

¡P             design, supply, delivery, installation, testing and commissioning of a traffic control and surveillance system for the connecting road linking up the Liantang / Heung Yuen Wai Boundary Control Point and the existing Fanling Highway.

 

Contract 5 (CV/2013/03)

2.1.6                 Contract 5 has awarded in April 2013 and construction work was commenced in August 2013.  Major Scope of Work of the Contract 5 is listed below:

¡P                site formation of about 23 hectares of land for the development of the BCP;

¡P                construction of an approximately 1.6 km long perimeter road at the BCP including a 175m long depressed road;

¡P                associated diversion/modification works at existing local roads and junctions including Lin Ma Hang Road;

¡P                construction of pedestrian subway linking the BCP to Lin Ma Hang Road;

¡P                provision of resite area with supporting infrastructure for reprovisioning of the affected village houses; and

¡P                construction of associated footpath, slopes, retaining structures, drainage, sewerage, waterworks, landscaping works and other ancillary works.

 

Contract 6 (CV/2013/08)

2.1.7                 Contract 6 has awarded in June 2015 and construction work was commenced on 23 October 2015.  Major Scope of Work of the Contract 6 would be included below:

Ÿ    construction of an approximately 4.6km long dual two-lane connecting road (with about 0.6km of at-grade road, 3.3km of viaduct and 0.7km of tunnel) connecting the BCP with the proposed Sha Tau Kok Road Interchange and the associated ventilation buildings;

Ÿ    associated diversion/modification works at access roads to the resite of Chuk Yuen Village;

Ÿ    provision of sewage collection, treatment and disposal facilities for the BCP and the resite of Chuk Yuen Village;

Ÿ    construction of a pedestrian subway linking the BCP to Lin Ma Hang Road;

Ÿ    provisioning of the affected facilities including Wo Keng Shan Road garden; and

Ÿ    construction of associated footpath, slopes, retaining structures, drainage, sewerage, waterworks, landscaping works and other ancillary works.

 

Contract 7 (NE/2014/03)

2.1.8                 Contract 7 has awarded in December 2015 and the construction works of Contract 7 was commenced on 15 February 2016.  Major Scope of Work of the Contract 7 would be included below:

Ÿ    construction of the Hong Kong Special Administrative Region (HKSAR) portion of four vehicular bridge

Ÿ    construction of one pedestrian bridge crossing Shenzhen (SZ) River (cross boundary bridges)

 

ArchSD Contract No. SS C505

2.1.9                 SS C505 has awarded in July 2015 and construction work was commenced on 1 September 2015.  Major Scope of Work of the SS C505 would be included below:

Ÿ    passenger-related facilities including processing kiosks and examination facilities for private cars and coaches, passenger clearance building and halls, the interior fitting works for the pedestrian bridge crossing Shenzhen River, etc.;

Ÿ    cargo processing facilities including kiosks for clearance of goods vehicles, customs inspection platforms, X-ray building, etc.;

Ÿ    accommodation for the facilities inside of the Government departments providing services in connection with the BCP;

Ÿ    transport-related facilities inside the BCP including road networks, public transport interchange, transport drop-off and pick-up areas, vehicle holding areas and associated road furniture etc;

Ÿ    a public carpark; and

Ÿ    other ancillary facilities such as sewerage and drainage, building services provisions and electronic systems, associated environmental mitigation measure and landscape works.

 

2.2                       Project Organization

2.2.1                 The project organization is shown in Appendix B.  The responsibilities of respective parties are:

 

Civil Engineering and Development Department (CEDD)

2.2.2                 CEDD is the Project Proponent and the Permit Holder of the EP of the development of the Project and will assume overall responsibility for the project. An Independent Environmental Checker (IEC) shall be employed by CEDD to audit the results of the EM&A works carried out by the ET.

 

Architectural Services Department (ArchSD)

2.2.3                 ArchSD acts as the works agent for Development Bureau (DEVB), for Contract SS C505 Liantang/ Heung Yuen Wai Boundary Control Point (BCP) ¡V BCP Buildings and Associated Facilities.

 

Environmental Protection Department (EPD)

2.2.4                 EPD is the statutory enforcement body for environmental protection matters in Hong Kong.

 

Ronald Lu & Partners (Hong Kong) Ltd (The Architect)

2.2.5                 Ronald Lu & Partners (Hong Kong) Ltd is appointed by ArchSD as an Architect for Contract SS C505 Liantang/ Heung Yuen Wai Boundary Control Point (BCP) ¡V BCP Buildings and Associated Facilities.  It responsible for overseeing the construction works of Contract SS C505 and for ensuring that the works are undertaken by the Contractor in accordance with the specification and contract requirements. The duties and responsibilities of the Architect with respect to EM&A are:

Ÿ    Monitor the Contractors¡¦ compliance with contract specifications, including the implementation and operation of the environmental mitigation measures and their effectiveness

Ÿ    Monitor Contractors¡¦ and ET¡¦s compliance with the requirements in the Environmental Permit (EP) and EM&A Manual

Ÿ    Facilitate ET¡¦s implementation of the EM&A programme

Ÿ    Participate in joint site inspection by the ET and IEC

Ÿ    Oversee the implementation of the agreed Event / Action Plan in the event of any exceedance

Ÿ    Adhere to the procedures for carrying out complaint investigation

Ÿ    Liaison with DSD, Engineer/Engineer¡¦s Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s Regulation of Shenzhen River Stage 4 (RSR 4)¡¨ Project discussing regarding the cumulative impact issues.

 

Engineer or Engineers Representative (ER)

2.2.6                 The ER is responsible for overseeing the construction works and for ensuring that the works are undertaken by the Contractor in accordance with the specification and contract requirements. The duties and responsibilities of the ER with respect to EM&A are:

¡P           Monitor the Contractors¡¦ compliance with contract specifications, including the implementation and operation of the environmental mitigation measures and their effectiveness

¡P           Monitor Contractors¡¦s, ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental Permit (EP) and EM&A Manual

¡P           Facilitate ET¡¦s implementation of the EM&A programme

¡P           Participate in joint site inspection by the ET and IEC

¡P           Oversee the implementation of the agreed Event / Action Plan in the event of any exceedance

¡P           Adhere to the procedures for carrying out complaint investigation

¡P           Liaison with DSD, Engineer/Engineer¡¦s Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s Regulaiton of Shenzhen River Stage 4 (RSR 4)¡¨ Project discussing regarding the cumulative impact issues.

 

The Contractor(s)

2.2.7                 There will be one contractor for each individual works contract. Once the contractors are appointed, EPD, ET and IEC will be notified the details of the contractor.

2.2.8                 The Contractor for Contracts under CEDD should report to the ER. For ArchSD Contract, the Contractor should report to the Architect or Architect¡¦s Representative (AR). The duties and responsibilities of the Contractor are:

¡P           Comply with the relevant contract conditions and specifications on environmental protection

¡P           Employ an Environmental Team (ET) to undertake monitoring, laboratory analysis and reporting of EM &A Facilitate ET¡¦s monitoring and site inspection activities

¡P           Participate in the site inspections by the ET and IEC, and undertake any corrective actions

¡P           Provide information / advice to the ET regarding works programme and activities which may contribute to the generation of adverse environmental impacts

¡P           Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event / Action Plans

¡P           Implement measures to reduce impact where Action and Limit levels are exceeded

¡P           Adhere to the procedures for carrying out complaint investigation

 

Environmental Team (ET)

2.2.9                 Once the ET is appointed, the EPD, CEDD, ER, Architect and IEC will be notified the details of the ET.

 

2.2.10             The ET shall not be in any way an associated body of the Contractor(s), and shall be employed by the Project Proponent/Contractor to conduct the EM&A programme.  The ET should be managed by the ET Leader. The ET Leader shall be a person who has at least 7 years¡¦ experience in EM&A and has relevant professional qualifications. Suitably qualified staff should be included in the ET, and resources for the implementation of the EM&A programme should be allocated in time under the Contract(s), to enable fulfillment of the Project¡¦s EM&A requirements as specified in the EM&A Manual during construction of the Project.  The ET shall report to the Project Proponent and the duties shall include:

¡P           Monitor and audit various environmental parameters as required in this EM&A Manual

¡P           Analyse the environmental monitoring and audit data, review the success of EM&A programme and the adequacy of mitigation measures implemented, confirm the validity of the EIA predictions and identify any adverse environmental impacts arising

¡P           Carry out regular site inspection to investigate and audit the Contractors¡¦ site practice, equipment/plant and work methodologies with respect to pollution control and environmental mitigation, and effect proactive action to pre-empt problems

¡P           Monitor compliance with conditions in the EP, environmental protection, pollution prevention and control regulations and contract specifications

¡P           Audit environmental conditions on site

¡P           Report on the environmental monitoring and audit results to EPD, the ER, the Architect, the lEC and Contractor or their delegated representatives

¡P           Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans

¡P           Liaise with the IEC on all environmental performance matters and timely submit all relevant EM&A proforma for approval by IEC

¡P           Advise the Contractor(s) on environmental improvement, awareness, enhancement measures etc., on site

¡P           Adhere to the procedures for carrying out complaint investigation

¡P           Liaison with the client departments, Engineer/Engineer¡¦s Representative, ET, lEC and the Contractor(s) of the concurrent projects as listed under Section 2.3 below regarding the cumulative impact issues.

 

Independent Environmental Checker (IEC)

2.2.11             One IEC will be employed for this Project. Once the IEC is appointed, EPD, ER, the Architect and ET will be notified the details of the IEC.

 

2.2.12             The Independent Environmental Checker (IEC) should not be in any way an associated body of the Contractor or the ET for the Project. The IEC should be employed by the Permit Holder (i.e., CEDD) prior to the commencement of the construction of the Project. The IEC should have at least 10 years¡¦ experience in EM&A and have relevant professional qualifications. The appointment of IEC should be subject to the approval of EPD. The IEC should:

¡P           Provide proactive advice to the ER and the Project Proponent on EM&A matters related to the project, independent from the management of construction works, but empowered to audit the environmental performance of construction

¡P           Review and audit all aspects of the EM&A programme implemented by the ET

¡P           Review and verify the monitoring data and all submissions in connection with the EP and EM&A Manual submitted by the ET

¡P           Arrange and conduct regular, at least monthly site inspections of the works during construction phase, and ad hoc inspections if significant environmental problems are identified

¡P           Check compliance with the agreed Event / Action Plan in the event of any exceedance

¡P           Check compliance with the procedures for carrying out complaint investigation

¡P           Check the effectiveness of corrective measures

¡P           Feedback audit results to ET by signing off relevant EM&A proforma

¡P           Check that the mitigation measures are effectively implemented

¡P           Verify the log-book(s) mentioned in Condition 2.2 of the EP, notify the Director by fax, within one working day of receipt of notification from the ET Leader of each and every occurrence, change of circumstances or non-compliance with the EIA Report and/or the EP, which might affect the monitoring or control of adverse environmental impacts from the Project

¡P           Report the works conducted, the findings, recommendation and improvement of the site inspections, after reviewing ET¡¦s and Contractor¡¦s works, and advices to the ER and Project Proponent on a monthly basis

¡P           Liaison with the client departments, Engineer/Engineer¡¦s Representative, the Architect, ET, lEC and the Contractor of the concurrent projects as listed under Section 2.3 below regarding the cumulative impact issues.

 

2.3                       Concurrent Projects

2.3.1                 The concurrent construction works that may be carried out include, but not limited to, the following:

                                (a)            Regulation of Shenzhen River Stage IV;

                                (b)            Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange ¡V Contract No. HY/2012/06;

                                (c)            Construction of BCP facilities in Shenzhen.

 

2.4                       Construction Progress

2.4.1                 In the Reporting Period, the major construction activity conducted under the Project is located in Contracts 2, 3, 5, 6, 7 and SS C505 and they are summarized in below.  Moreover, 3-month rolling construction program for all the current contracts is enclosed in Appendix C. 

 

Contract 2 (CV/2012/08)

2.4.2                 The contract commenced in May 2014. In this Reporting Period, construction activities conducted are listed below:

Mid-Vent Portal

Ÿ    Tube excavation (NB + SB)

Ÿ    Adit invert slab, waterproofing and lining, post-excavation grouting

Ÿ    Ventilation building superstructure

North Portal

Ÿ    Slope stabilization and retaining wall

Ÿ    Southbound TBM excavation

Ÿ    Northbound bottom bench excavation and tunnel enlargement

Ÿ    Ventilation building foundation

South Portal

Ÿ    Southbound and Northbound Drill and Blast (D&B) excavation

Ÿ    South ventilation building superstructure

Admin Building

Ÿ    Building works foundation

Contract 3 (CV/2012/09)

2.4.3                 The Contract commenced in November 2013.  In this Reporting Period, construction activities conducted are listed below:

Ÿ   Cable detection and trial trenches

Ÿ   Filling works at Tong Hang East

Ÿ   Storm drain laying

Ÿ   Noise barrier construction

Ÿ   Pier / pier table construction

Ÿ   Pile cap works

Ÿ   Portal beam construction

Ÿ   Pre-drilling Works and Piling Works for Viaduct

Ÿ   Pre-drilling Works and Piling Works for Noise Barrier

Ÿ   Retaining Wall construction

Ÿ   Road works

Ÿ   Sewer works

Ÿ   Slope works

Ÿ   Socket H-pile Installation

Ÿ   Waterworks

Ÿ   Tree Felling Works

Ÿ   Utilities Duct Laying

Ÿ   Viaduct segment erection

 

Contract 4 (Contract number to be assigned)

2.4.4                 The Contract was awarded in mid-April 2016 and the major construction work has not yet commenced.

 

Contract 5 (CV/2013/03)

2.4.5                 The Contract awarded in April 2013 and commenced on August 2013.  In this Reporting Period, construction activities conducted are listed below:

Ÿ   Construction of rising main (VO61) at existing Lin Ma Hang (LMH) Road

Ÿ   Bituminous laying at existing LMH road

Ÿ   Brick laying at footpath at LMH road

Ÿ   Planting at proposed and existing LMH road

Ÿ   Installation of Underground Utility (UU) at proposed and existing LMH road

Ÿ   Irrigation system at existing LMH Road

 

Contract 6 (CV/2013/08)

2.4.6                 Contract 6 has awarded in June 2015 and construction work was commenced on 23 October 2015. In this Reporting Period, construction activities conducted are listed below:

Ÿ    Site Clearance

Ÿ    Slope Works

Ÿ    Site Accesses Construction

Ÿ    Ground Investigation Works

Ÿ    Soil Nail

Ÿ    Bored Piling

Ÿ    Pile Cap Construction

Ÿ    Tunnel Excavation

Ÿ    Sewage Treatment Plant Construction

 

Contract 7 (NE/2014/03)

2.4.7                 Contract 7 has awarded in December 2015 and construction work was commenced on 15 February 2016.  In this Reporting Period, construction activities conducted are listed below:

Ÿ   Ground Investigation Works at Bridge C and E

Ÿ   Piling Works at Bridge C, D

Ÿ   Pile Caps Construction at Bridge B

 

 

Contract SS C505

2.4.8                 Contract SS C505 has awarded in July 2015 and construction work was commenced on 1 September 2015.  In this Reporting Period, construction activities conducted are listed below:

Ÿ   General Site Setup

Ÿ   CLP temporally sub-station works

Ÿ   Erection of Welfare Shelter

Ÿ   Building number 4, 5, 6, 9 and 36 construction

Ÿ   Pile cap construction for Building number 4, 6 & 7

Ÿ   Tower crane operation and Tower crane TC10 construction

Ÿ   H-pile works and loading test

Ÿ   Disassembly of crawler crane

Ÿ   Grouting and full core to completed bored piles

Ÿ   Bridge construction works including construction of bridge column, retaining wall, pile cap

Ÿ   Underground drainage works

Ÿ   Prototype ¡§A¡¨ Construction works

Ÿ   Mock up for south entrance double curve cladding

Ÿ   Formwork and falsework for PTB¡¦s slap construction

Ÿ   Pile Cap construction for PTB, including excavation and backfilling works

Ÿ   Footing construction

 

2.5                       Summary of Environmental Submissions

2.5.1                 In according to the EP, the required documents have submitted to EPD which listed in below:

Ÿ   Project Layout Plans of Contracts 2, 3, 5, 6, 7 and SS C505

Ÿ   Landscape Plan

Ÿ   Topsoil Management Plan

Ÿ   Environmental Monitoring and Audit Programme

Ÿ   Baseline Monitoring Report (TCS00690/13/600/R0030v3) for the Project

Ÿ   Waste Management Plan of the Contracts 2, 3, 5, 6, 7 and SS C505

Ÿ   Contamination Assessment Plan (CAP) and Contamination Assessment Report (CAR) for Po Kat Tsai, Loi Tung and the workshops in Fanling

Ÿ   Vegetation Survey Report

Ÿ   Woodland Compensation Plan

Ÿ   Habitat Creation Management Plan

Ÿ   Wetland Compensation Plan

 

2.5.2                 Summary of the relevant permits, licenses, and/or notifications on environmental protection for the Project of each contracts are presented in Table 2-1.

Table 2-1    Status of Environmental Licenses and Permits of the Contracts

Item

Description

License/Permit Status

Ref. no.

Effective Date

Expiry Date

Contract 2

1

Air pollution Control (Construction Dust) Regulation

Ref No.: 368864

31 Dec 2013

Till Contract ends

2

Chemical Waste Producer Registration

North Portal

Waste Producers Number: No.5213-652-D2523-01

25 Mar 2014

Till Contract ends

Mid-Vent Portal

Waste Producers Number: No.5213-634-D2524-01

25 Mar 2014

Till Contract ends

South Portal

Waste Producers Number: No.5213-634-D2526-01

9 Apr 2014

Till Contract ends

3

Water Pollution Control Ordinance - Discharge License

No.WT00018374-2014

8 Oct 2014

30 Sep 2019

No.: W5/1I389

28 Mar 2014

31 Mar 2019

No. WT00023063-2015

18 Dec 2015

31 Mar 2019

No.: W5/1I392

28 Mar 2014

31 Mar 2019

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

Account No. 7019105

8 Jan 2014

Till Contract ends

5

Construction Noise Permit

GW-RN0795-15

7 Dec 2015

6 Jun 2016

GW-RN0893-15

01-Jan-2016

27-Jun-2016

GW-RN0071-16

02-Feb-16

31-Jul-2016

GW-RN0077-16

07-Feb-2016

06-Aug-2016

GW-RN0199-16

24-Mar-2016

17-Sep-2016

GW-RN0323-16

30-Apr-2016

29-Jun-2016

GW-RN0321-16

30-Apr-2016

29-Jun-2016

GW-RN0359-16

20-May-2016

19-Aug-2016

GW-RN0378-16

30-May-2016

29-Aug-2016

GW-RN0451-16

24-Jun-2016

19-Sep-2016

GW-RN0457-16

22-Jun-2016

14-Dec-2016

GW-RN0435-16

27-Jun-2016

26-Dec-2016

GW-RN0332-16

09-May-2016

08-Aug-2016

6

Specified Process License

(Mortar Plant Operation)

 

L-3-251(1)

 

 

12-Apr-2016

 

11-Apr-2021

Contract 3

1

Air pollution Control (Construction Dust) Regulation

Ref. No: 362101

17 Jul 2013

Till Contract ends

2

Chemical Waste Producer Registration

Waste Producers Number: No.:5113-634-C3817-01

 

7 Oct 2013

Till Contract ends

3

Water Pollution Control Ordinance - Discharge License

No.:WT00016832 ¡V 2013

28 Aug 13

31 Aug 2018

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

Account No. 7017914

2 Aug 13

Till Contract ends

5

 

 

Construction Noise Permit

GW-RN0892-15

9 Jan 2016

8 July 2016

GW-RN0064-16

16 Feb 2016

13 Aug 2016

GW-RN0096-16

6 Mar 2016

12 Jun 2016

GW-RN0097-16

1 Mar 2016

17 Jun 2016

GW-RN0098-16

1 Mar 2016

4 Sep 2016

GW-RN0113-16

25 Feb 2016

24 Aug 2016

GW-RN0139-16

2 Mar 2016

24 Aug 2016

GW-RN0140-16

2 Mar 2016

24 Aug 2016

GW-RN0158-16

8 Mar 2016

31 Aug 2016

GW-RN0168-16

15 Mar 2016

14 Jun 2016

GW-RN0170-16

11 Mar 2016

10 Sep 2016

GW-RN0218-16

6 April 2016

30 Sep 2016

GW-RN0233-16

11 April 2016

10 Oct 2016

GW-RN0297-16            

4 May 2016

30 June 2016

GW-RN0303-16

30 April 2016

29 July 2016

GW-RN0307-16

10 May 2016

9 Sep 2016

GW-RN0308-16

10 May 2016

9 Sep 2016

GW-RN0309-16

30 April 2016

29 Oct 2016

GW-RN0414-16

18 June 2016

17 Dec 2016

GW-RN0419-16

21 June 2016

30 Sep 2016

GW-RN0421-16

21 June 2016

30 Sep 2016

GW-RN0446-16

24 June 2016

31 Aug 2016

GW-RN0434-16

22 June 2016

21 Dec 2016

GW-RN0305-16

5 May 2016

4 Aug 2016

Contract 5

1

Air pollution Control (Construction Dust) Regulation

Ref. No: 359338

 

13 May 2013

Till the end of Contract

2

Chemical Waste Producer Registration

Waste Producers Number No.: 5213-642-S3735-01

8 Jun 2013

Till the end of Contract

3

Water Pollution Control Ordinance - Discharge License

No.: W5/1G44/1

8 Jun 13

30 Jun 2018

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

Account No. 7017351

29 Apr 13

Till the end of Contract

Contract 6

1

Air pollution Control (Construction Dust) Regulation

Ref. No: 390614

29 Jun 2015

Till the end of Contract

2

Chemical Waste Producer Registration

Waste Producers Number No.: 5213-652-C3969-01

31 Aug 2015

Till the end of Contract

3

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

Account No. 7022707

9 Jul 2015

Till the end of Contract

4

Water Pollution Control Ordinance - Discharge License

No.:WT00024574-2016

31 May 2016

31 May 2021

No.:WT00024576-2016

31 May 2016

31 May 2021

No.:WT00024742-2016

14 June 2016

30 June 2021

No.:WT00024746-2016

14 June 2016

30 June 2021

Contract SS C505

1

Air pollution Control (Construction Dust) Regulation

Ref. No: 390974

13 Jul 2015

Till the end of Contract

2

Chemical Waste Producer Registration

Waste Producer No.: 5213-642-L1048-07

16 Sep 2015

Till the end of Contract

3

Water Pollution Control Ordinance - Discharge License

No.: WT00022774-2015

17 Nov 2015

30 Nov 2020

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

Account No. 7022831

23 Jul 2015

Till the end of Contract

5

Construction Noise Permit

GW-RN0396-16

5 June 2016

4 Nov 2016

PP-RN0015-16

16 May 2016

15 July 2016

GW-RN0337-16

23 May 2016

22 July 2016

Contract 7

1

Air pollution Control (Construction Dust) Regulation

Ref. No: 397015

21 Dec 2015

Till the end of Contract

2

Chemical Waste Producer Registration

Waste Producer No.: 5214-641-K3202-01

24 Mar 2016

Till the end of Contract

3

Water Pollution Control Ordinance - Discharge License

No.: WT00024422-2016

 

10 May 2016

31 May 2021

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

Account No. 7024129

21 Jan 2016

Till the end of Contract

5

Construction Noise Permit

GW-RN0329-16

23 May 2016

22 July 2016

                                  Contract 4

1

 

Air pollution Control (Construction Dust) Regulation

Application is under preparation

2

Chemical Waste Producer Registration

Application is under preparation

3

Water Pollution Control Ordinance - Discharge License

Application is under preparation

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

Application is under preparation


3                             Summary of Impact Monitoring Requirements

3.1                       General

3.1.1                 The Environmental Monitoring and Audit requirements are set out in the Approved EM&A manual. Environmental issues such as air quality, construction noise and water quality were identified as the key issues during the construction phase of the Project.

 

3.1.2                 A summary of construction phase EM&A requirements are presented in the sub-sections below.

 

3.2                       Monitoring Parameters

3.2.1                 The EM&A program of construction phase monitoring shall cover the following environmental issues:

                     Air quality;

                     Construction noise; and

                     Water quality

 

3.2.2                 A summary of the monitoring parameters is presented in Table 3-1.

Table 3-1         Summary of EM&A Requirements

Environmental Issue

Parameters

Air Quality

Ÿ  1-hour TSP by Real-Time Portable Dust Meter; and

Ÿ  24-hour TSP by High Volume Air Sampler.

Noise

Ÿ  Leq(30min) in normal working days (Monday to Saturday) 07:00-19:00 except public holiday; and

Ÿ  3 sets of consecutive Leq(5min) on restricted hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday

Ÿ  Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

Water Quality

In-situ Measurements

Ÿ  Dissolved Oxygen Concentration (mg/L);

Ÿ  Dissolved Oxygen Saturation (% );

Ÿ  Turbidity (NTU);

Ÿ  pH unit;

Ÿ  Water depth (m); and

Ÿ  Temperature (¢J).

Laboratory Analysis

Ÿ  Suspended Solids (mg/L)

 

3.3                       Monitoring Locations

3.3.1                 The designated monitoring locations as recommended in the EM&A Manual are shown in Appendix D.  As the access to some of the designated monitoring locations was questionable due to safety reason or denied by the landlords, alternative locations therefore have had proposed. The proposed alternative monitoring locations has updated in the revised EM&A Programme which verified by IEC and certified by ET Leader prior submitted to EPD on 10 July 2013.  Table 3-2, Table 3-3 and Table 3-4 are respectively listed the air quality, construction noise and water quality monitoring locations for the Project and a map showing these monitoring stations is presented in Appendix E.

Table 3-2        Impact Monitoring Stations - Air Quality

Station ID

Description

Works Area

Related to the Work Contract

AM1b^

Open area at Tsung Yuen Ha Village

BCP

SS C505

Contract 5

Contract 7

AM2

Village House near Lin Ma Hang Road

LMH to Frontier Closed Area

Contract 5

Contract 6

AM3

Ta Kwu Ling Fire Service Station of Ta Kwu Ling Village.

LMH to Frontier Closed Area

Contract 5

Contract 6

AM4b^

House no. 10B1 Nga Yiu Ha Village

LMH to Frontier Closed Area

Contract 6

AM5a^

Ping Yeung Village House

Ping Yeung to Wo Keng Shan

Contract 6

AM6

Wo Keng Shan Village House

Ping Yeung to Wo Keng Shan

Contract 6

AM7b@

Loi Tung Village House

Sha Tau Kok Road

Contract 2

Contract 6

AM8

Po Kat Tsai Village No. 4

Po Kat Tsai

Contract 2

AM9b#

Nam Wa Po Village House No. 80

Fanling

Contract 3

# Proposal for the change of air quality monitoring location from AM9a to AM9b was submitted to EPD on 4 Nov 2013 after verified by the IEC and it was approved by EPD (EPD¡¦s ref.: (15) in EP 2/N7/A/52 Pt.10 dated 8 Nov 2013).

* Proposal for the change of air quality monitoring location from AM1to AM1a was submitted to EPD on 24 March 2014 after verified by the IEC. It was approved by EPD (EPD¡¦s ref.: (6) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).

@ Proposal for the change of air quality monitoring location from AM7a to AM7b was submitted to EPD on 4 June 2014 after verified by the IEC. It was approved by EPD (EPD¡¦s ref.: (7) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).

^ Proposal for change of air quality monitoring locations was enclosed in the updated EM&A Programme which approval by EPD on 29 Mar 2016.

 

Table 3-3        Impact Monitoring Stations - Construction Noise

Station ID

Description

Works Area

Related to the Work Contract

NM1

Tsung Yuen Ha Village House No. 63

BCP

SS C505

Contract 5

Contract 7

NM2a#

Village House near Lin Ma Hang Road

Lin Ma Hang to Frontier Closed Area

Contract 5,

Contract 6

NM3

Ping Yeung Village House (facade facing northeast)

Ping Yeung to Wo Keng Shan

Contract 6

NM4

Wo Keng Shan Village House

Ping Yeung to Wo Keng Shan

Contract 6

NM5

Village House, Loi Tung

Sha Tau Kok Road

Contract 2,

Contract 6

NM6

Tai Tong Wu Village House 2

Sha Tau Kok Road

Contract 2,

Contract 6

NM7

Po Kat Tsai Village

Po Kat Tsai

Contract 2

NM8

Village House, Tong Hang

Fanling

Contract 2

Contract 3

NM9

Village House, Kiu Tau Village

Fanling

Contract 3

NM10

Nam Wa Po Village House No. 80

Fanling

Contract 3

# Proposal for the change of construction noise monitoring location from NM2 to NM2a was verified by the IEC on 6 May 2016 and was effective on 9 May 2016.

 

 

Table 3-4        Impact Monitoring Stations - Water Quality

Station ID

Description

Coordinates of Designated / Alternative Location

Nature of the location

Related to the Work Contract

WM1

Downstream of Kong Yiu Channel

833 679

845 421

Alternative location located at upstream 51m of the designated location

SS C505

Contract 5

Contract 6

WM1- Control

Upstream of Kong Yiu Channel

834 185

845 917

NA

SS C505

Contract 5

Contract 6

WM2A

Downstream of River Ganges

834 204

844 471

Alternative location located at downstream 81m of the designated location

Contract 6

WM2A- Controlx

Upstream of River Ganges

835 377

844 188

Alternative location located at upstream 160m of the designated location

Contract 6

WM2B

Downstream of River Ganges

835 433

843 397

NA

Contract 6

WM2B- Control

Upstream of River Ganges

835 835

843 351

Alternative location located at downstream 31m of the designated location

Contract 6

WM3x

Downstream of River Indus

836 206

842 270

Alternative location located at downstream 180m of the designated location

Contract 2

Contract 6

WM3- Control

Upstream of River Indus

836 763

842 400

Alternative location located at downstream 26m of the designated location

Contract 2

Contract 6

WM4

Downstream of Ma Wat Channel

833 850

838 338

Alternative location located at upstream 11m of the designated location

Contract 2

Contract 3

WM4¡V Control A

Kau Lung Hang Stream

834 028

837 695

Alternative location located at downstream 28m of the designated location

Contract 2

Contract 3

WM4¡V Control B

Upstream of Ma Wat Channel

833760

837395

Alternative location located at upstream 15m of the designated location

Contract 2

Contract 3

Note: EPD has approved the revised EM&A Programme on 29th March 2016. If the measured water depth of the monitoring station is lower than 150 mm, alternative location (WM3x and WM2A-Controlx) based on the criteria were selected to perform water monitoring in accordance with the updated EM&A Programme (Rev. 05) (Section 4.1.4)

 

 

3.4                       Monitoring Frequency and Period

The requirements of impact monitoring are stipulated in Sections 2.1.6, 3.1.5 and 4.1.6 of the approved EM&A Manual and presented as follows.

 

Air Quality Monitoring

3.4.1                 Frequency of impact air quality monitoring is as follows:

Ÿ   1-hour TSP

3 times every six days during course of works

Ÿ   24-hour TSP

Once every 6 days during course of works.

 

Noise Monitoring

3.4.2                 One set of Leq(30min) as 6 consecutive Leq(5min) between 0700-1900 hours on normal weekdays and once every week during course of works.  If construction work necessary to carry out at other time periods, i.e. restricted time period (19:00 to 07:00 the next morning and whole day on public holidays) (hereinafter referred as ¡§the restricted hours¡¨), 3 consecutive Leq(5min) measurement will depended CNP requirements to undertake.  Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

 

Water Quality Monitoring

3.4.3                 The water quality monitoring frequency shall be 3 days per week during course of works.  The interval between two sets of monitoring shall not be less than 36 hours.

 

3.5                       Monitoring Equipment

Air Quality Monitoring

3.5.1                 The 24-hour and 1-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.  If the ET proposes to use a direct reading dust meter to measure 1-hour TSP levels, it shall submit sufficient information to the IEC to approve.

 

3.5.2                 The filter paper of 24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.

 

3.5.3                 All equipment to be used for air quality monitoring is listed in Table 3-5.

Table 3-5         Air Quality Monitoring Equipment

Equipment

Model

24-Hr TSP

High Volume Air Sampler

TISCH High Volume Air Sampler, HVS Model TE-5170*

Calibration Kit

TISCH Model TE-5025A*

1-Hour TSP

Portable Dust Meter

Sibata LD-3B Laser Dust monitor Particle Mass Profiler & Counter*

* Instrument was used in the Reporting Period and the calibration certificate could be referred in Appendix F.

 

Wind Data Monitoring Equipment

3.5.4                 According to the approved EM&A Manual, wind data monitoring equipment shall also be provided and set up for logging wind speed and wind direction near the dust monitoring locations.  The equipment installation location shall be proposed by the ET and agreed with the IEC.  For installation and operation of wind data monitoring equipment, the following points shall be observed:

1)          The wind sensors should be installed 10 m above ground so that they are clear of obstructions or turbulence caused by buildings.

2)          The wind data should be captured by a data logger. The data shall be downloaded for analysis at least once a month.

3)          The wind data monitoring equipment should be re-calibrated at least once every six months.

4)          Wind direction should be divided into 16 sectors of 22.5 degrees each.

 

3.5.5                 ET has liaised with the landlords of the successful granted HVS installation premises.  However, the owners rejected to provide premises for wind data monitoring equipment installation.

 

3.5.6                 Under this situation, the ET proposed alternative methods to obtain representative wind data.  Meteorological information as extracted from ¡§the Hong Kong Observatory Ta Kwu Ling Station¡¨ is alternative method to obtain representative wind data.  For Ta Kwu Ling Station, it is located nearby the Project site.  Moreover, this station is located at 15m above mean sea level while its anemometer is located at 13m above the existing ground which in compliance with the general setting up requirement.  Furthermore, this station also can be to provide the humidity, rainfall, and air pressure and temperature etc. meteorological information.  In Hong Kong of a lot development projects, weather information extracted from Hong Kong Observatory is common alternative method if weather station installation not allowed.

 

Noise Monitoring

3.5.7                 Sound level meter in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring.  The sound level meter shall be checked using an acoustic calibrator.  The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

 

3.5.8                 Noise monitoring equipment to be used for monitoring is listed in Table 3-6.

Table 3-6         Construction Noise Monitoring Equipment

Equipment

Model

Integrating Sound Level Meter

B&K Type 2238* or Rion NL-31 or Rion NL-52*

Calibrator

B&K Type 4231* or Cesva CB-5 or Rion NC-74

Portable Wind Speed Indicator

Testo Anemometer

* Instrument was used in the Reporting Period and the calibration certificate could be referred in Appendix F.

 

3.5.9                 Sound level meters listed above comply with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications, as recommended in TM issued under the NCO.  The acoustic calibrator and sound level meter to be used in the impact monitoring will be calibrated yearly.

 

Water Quality Monitoring

3.5.10             DO and water temperature should be measured in-situ by a DO/temperature meter. The instrument should be portable and weatherproof using a DC power source. It should have a membrane electrode with automatic temperature compensation complete with a cable. The equipment should be capable of measuring:

                 a DO level in the range of 0-20 mg/l and 0-200% saturation; and

                 a temperature of between 0 and 45 degree Celsius.

 

3.5.11             A portable pH meter capable of measuring a range between 0.0 and 14.0 should be provided to measure pH under the specified conditions accordingly to the APHA Standard Methods.

 

3.5.12             The instrument should be portable and weatherproof using a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0-1000 NTU.

 

3.5.13             A portable, battery-operated echo sounder or tape measure will be used for the determination of water depth at each designated monitoring station as appropriate.

 

3.5.14             A water sampler e.g. Kahlsico Water Sampler, which is a transparent PVC cylinder with capacity not less than 2 litres, will be used for water sampling if water depth over than 0.5m.   For sampling from very shallow water depths e.g. <0.5 m, water sample collection will be directly from water surface below 100mm use sampling plastic bottle to avoid inclusion of bottom sediment or humus.  Moreover, Teflon/stainless steel bailer or self-made sampling buckets maybe used for water sampling.  The equipment used for sampling will be depended the sampling location and depth situations.

 

3.5.15             Water samples for laboratory measurement of SS will be collected in high density polythene bottles, packed in ice (cooled to 4 ºC without being frozen), and delivered to the laboratory in the same day as the samples were collected.

 

3.5.16             Analysis of suspended solids should be carried out in a HOKLAS or other accredited laboratory. Water samples of about 1L should be collected at the monitoring stations for carrying out the laboratory suspended solids determination.  The SS determination work should start within 24 hours after collection of the water samples. The SS analyses should follow the APHA Standard Methods 2540D with Limit of Reporting of 2 mg/L.

 

3.5.17             Water quality monitoring equipment used in the impact monitoring is listed in Table 3-7.  Suspended solids (SS) analysis is carried out by a local HOKLAS-accredited laboratory, namely ALS Technichem (HK) Pty Ltd.

Table 3-7         Water Quality Monitoring Equipment

Equipment

Model

Water Depth Detector

Eagle Sonar or tape measures

Water Sampler

A 2-litre transparent PVC cylinder with latex cups at both ends or teflon/stainless steel bailer or self-made sampling bucket

Thermometer & DO meter

YSI Professional Plus /YSI PRO20 Handheld Dissolved Oxygen Instrument* / YSI 550A Multifunctional Meter/ YSI Professional DSS*

pH meter

YSI Professional Plus / AZ8685 pH pen-style meter*/ YSI 6820/ 650MDS/ YSI Professional DSS*

Turbidimeter

Hach 2100Q*/ YSI 6820/ 650MDS/ YSI Professional DSS*

Sample Container

High density polythene bottles (provided by laboratory)

Storage Container

¡¥Willow¡¦ 33-liter plastic cool box with Ice pad

* Instrument was used in the Reporting Period and the calibration certificate could be referred in Appendix F.

 

3.6                       Monitoring Methodology

1-hour TSP Monitoring

3.6.1                 The 1-hour TSP monitor was a brand named ¡§Sibata LD-3B Laser Dust monitor Particle Mass Profiler & Counter¡¨ which is a portable, battery-operated laser photometer.  The 1-hour TSP meter provides a real time 1-hour TSP measurement based on 90o light scattering.  The 1-hour TSP monitor consists of the following:

(a.)         A pump to draw sample aerosol through the optic chamber where TSP is measured;

(b.)        A sheath air system to isolate the aerosol in the chamber to keep the optics clean for maximum reliability; and

(c.)         A built-in data logger compatible with Windows based program to facilitate data collection, analysis and reporting.

 

3.6.2                 The 1-hour TSP meter is used within the valid period as follow manufacturer¡¦s Operation and Service Manual.

 

24-hour TSP Monitoring

3.6.3                 The equipment used for 24-hour TSP measurement is Tisch Environmental, Inc. Model TE-5170 TSP high volume air sampling system, which complied with EPA Code of Federal Regulation, Appendix B to Part 50. The High Volume Air Sampler (HVS) consists of the following:

(a.)         An anodized aluminum shelter;

(b.)        A 8¡¨x10¡¨ stainless steel filter holder;

(c.)         A blower motor assembly;    

(d.)        A continuous flow/pressure recorder;

(e.)         A motor speed-voltage control/elapsed time indicator;

(f.)         A 7-day mechanical timer, and

(g.)         A power supply of 220v/50 Hz

 

3.6.4                 The HVS is operated and calibrated on a regular basis in accordance with the manufacturer¡¦s instruction using Tisch Calibration Kit Model TE-5025A.  Calibration would carry out in two month interval.

 

3.6.5                 24-hour TSP is collected by the ET on filters of HVS and quantified by a local HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd (ALS), upon receipt of the samples.  The ET keep all the sampled 24-hour TSP filters in normal air conditioned room conditions, i.e. 70% RH (Relative Humidity) and 25oC, for six months prior to disposal.

 

Noise Monitoring

3.6.6                 Noise measurements were taken in terms of the A-weighted equivalent sound pressure level (Leq) measured in decibels dB(A). Supplementary statistical results (L10 and L90) were also obtained for reference.

 

3.6.7                 During the monitoring, all noise measurements would be performed with the meter set to FAST response and on the A-weighted equivalent continuous sound pressure level (Leq).  Leq(30min) in six consecutive Leq(5min) measurements will use as the monitoring parameter for the time period between 0700-1900 hours on weekdays; and also Leq(15min) in three consecutive Leq(5min) measurements would be used as monitoring parameter for other time periods (e.g. during restricted hours), if necessary.

 

3.6.8                 Prior of noise measurement, the accuracy of the sound level meter is checked using an acoustic calibrator generating a known sound pressure level at a known frequency.  The checking is performed before and after the noise measurement.

 

Water Quality

3.6.9                 Water quality monitoring is conducted at the designated or alternative locations. The sampling procedures with the in-situ monitoring are presented as below:

 

Sampling Procedure

3.6.10             A Digital Global Positioning System (GPS) is used to identify the designated monitoring stations prior to water sampling.  A portable, battery-operated echo sounder or tape measurement is used for the determination of water depth at each station.  At each station, water sample would be collected from 0.1m below water surface or the water surface to prevent the river bed sediment for stirring.

 

3.6.11             The sample container will be rinsed with a portion of the water sample.  The water sample then will be transferred to the high-density polythene bottles as provided by the laboratory, labeled with a unique sample number and sealed with a screw cap.

 

3.6.12             Before sampling, general information such as the date and time of sampling, weather condition as well as the personnel responsible for the monitoring would be recorded on the field data sheet.

 

3.6.13             A ¡¥Willow¡¦ 33-liter plastic cool box packed with ice will be used to preserve the water samples prior to arrival at the laboratory for chemical determination.  The water temperature of the cool box is maintained at a temperature as close to 40C as possible without being frozen.  Samples collected are delivered to the laboratory upon collection.

 

In-situ Measurement

3.6.14             YSI PRO20 Handheld Dissolved Oxygen Instrument or YSI Professional DSS is used for water in-situ measures, which automates the measurements and data logging of temperature, dissolved oxygen and dissolved oxygen saturation. 

 

3.6.15             A portable AZ Model 8685 pH pen-style meter or YSI Professional DSS is used for in-situ pH measurement.  The pH meter is capable of measuring pH in the range of 0 ¡V 14 and readable to 0.1.

 

3.6.16             A portable Hach 2100Q Turbidimeter or YSI Professional DSS is used for in-situ turbidity measurement. The turbidity meter is capable of measuring turbidity in the range of 0 ¡V 1000 NTU. 

 

3.6.17             All in-situ measurement equipment are calibrated by HOKLAS accredited laboratory of three month interval.

 

Laboratory Analysis

3.6.18             All water samples analyzed Suspended Solids (SS) will be carried out by a local HOKLAS-accredited testing laboratory (ALS Technichem (HK) Pty Ltd HOKLAS registration no. 66).  SS determination using APHA Standard Methods 2540D as specified in the EM&A Manual will start within 48 hours of water sample receipt.

 

3.7                       Equipment Calibration

3.7.1                 Calibration of the HVS is performed upon installation and thereafter at bimonthly intervals in accordance with the manufacturer¡¦s instruction using the certified standard calibrator (TISCH Model TE-5025A).  Moreover, the Calibration Kit would be calibrated annually. The calibration data are properly documented and the records are maintained by ET for future reference.

 

3.7.2                 The 1-hour TSP meter was calibrated by the supplier prior to purchase.  Zero response of the equipment would be checked before and after each monitoring event.  Annually calibration with the High Volume Sampler (HVS) in same condition would be undertaken by the Laboratory.

 

3.7.3                 The sound level meter and calibrator are calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme at yearly basis.

 

3.7.4                 All water quality monitoring equipment would be calibrated by HOKLAS accredited laboratory of three month intervals.

 

3.7.5                 The calibration certificates of all monitoring equipment used for the impact monitoring program in the Reporting Period and the HOKLAS accredited certificate of laboratory are attached in Appendix F.   

 

3.8                       Derivation of Action/Limit (A/L) Levels

3.8.1                 The baseline results form the basis for determining the environmental acceptance criteria for the impact monitoring.  According to the approved Environmental Monitoring and Audit Manual, the air quality, construction noise and water quality criteria were set up, namely Action and Limit levels are listed in Tables 3-8, 3-9 and 3-10.

Table 3-8        Action and Limit Levels for Air Quality Monitoring

Monitoring Station

Action Level (mg /m3)

Limit Level (mg/m3)

1-hour TSP

24-hour TSP

1-hour TSP

24-hour TSP

AM1b

265

143

500

260

AM2

268

149

AM3

269

145

AM4b

267

148

AM5a

268

143

AM6

269

148

AM7b

275

156

AM8

269

144

AM9b

271

151

 

Table 3-9         Action and Limit Levels for Construction Noise

Monitoring Location

Action Level

Limit Level in dB(A)

Time Period: 0700-1900 hours on normal weekdays

NM1, NM2a, NM3, NM4, NM5, NM6, NM7, NM8, NM9, NM10

When one or more documented complaints are received

75 dB(A)Note 1 & Note 2

Note 1:  Acceptable Noise Levels for school should be reduced to 70 dB(A) and65 dB(A) during examination period

Note 2:  If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the NCA have to be followed.

 

Table 3-10       Action and Limit Levels for Water Quality

Parameter

Performance criteria

Monitoring Location

WM1

WM2A

WM2B

WM3

WM4

DO (mg/L)

Action Level

(*)4.23

(**)4.00

(*)4.74

(**)4.00

(*)4.14

Limit Level

(#)4.19

(**)4.00

(#)4.60

(**)4.00

(#)4.08

Turbidity (NTU)

Action Level

51.3

24.9

11.4

13.4

35.2

AND  120% of upstream control station of the same day

Limit Level

67.6

33.8

12.3

14.0

38.4

AND  130% of upstream control station of the same day

SS (mg/L)

Action Level

54.5

14.6

11.8

12.6

39.4

AND  120% of upstream control station of the same day

Limit Level

64.9

17.3

12.4

12.9

45.5

AND  130% of upstream control station of the same day

Remarks:

(*)      The Proposed Action Level of Dissolved Oxygen is adopted to be used 5%-ile of baseline data

(**)  The Proposed Action & Limit Level of Dissolved Oxygen is used 4mg/L

(#)     The Proposed Limit Level of Dissolved Oxygen is adopted to be used 1%-ile of baseline data

 

3.8.2                 Should non-compliance of the environmental quality criteria occurs, remedial actions will be triggered according to the Event and Action Plan which presented in Appendix G.

 

3.9                       Data Management and Data QA/QC Control

3.9.1                 All monitoring data will be handled by the ET¡¦s in-house data recording and management system.  The monitoring data recorded in the equipment will be downloaded directly from the equipment at the end of each monitoring day.  The downloaded monitoring data will input into a computerized database maintained by the ET.  The laboratory results will be input directly into the computerized database and checked by personnel other than those who input the data.

 

3.9.2                 For monitoring parameters that require laboratory analysis, the local laboratory shall follow the QA/QC requirements as set out under the HOKLAS scheme for the relevant laboratory tests.


4                             Air Quality Monitoring

4.1                       General

4.1.1                 In the Reporting Period, construction works under the project have been commenced in Contracts 2, 3, 5, 6, 7 and Contract SS C505. Hence, air quality monitoring was performed at all designated locations.

 

4.1.2                 The air quality monitoring schedule is presented in Appendix H and the monitoring results are summarized in the following sub-sections.

 

4.2                       Air Quality Monitoring Results in Reporting Month

4.2.1                 In the Reporting Period, a total of 150 events of 1-hour TSP and 50 events 24-hours TSP monitoring were carried out and the monitoring results are summarized in Tables 4-1 to 4-9.   The detailed 24-hour TSP monitoring data are presented in Appendix I and the relevant graphical plots are shown in Appendix J.

Table 4-1         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM1b

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

4-Jun-16

83

6-Jun-16

13:00

41

43

44

10-Jun-16

37

11-Jun-16

10:18

45

47

44

16-Jun-16

51

17-Jun-16

10:21

37

36

59

22-Jun-16

60

23-Jun-16

13:01

100

102

99

27-Jun-16

23

28-Jun-16

13:00

69

69

67

Average

(Range)

51

(23 ¡V 83)

Average

(Range)

60

(36 ¡V 102)

 

Table 4-2         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM2

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

4-Jun-16

74

6-Jun-16

13:02

43

45

42

10-Jun-16

54

11-Jun-16

10:05

39

40

38

16-Jun-16

73

17-Jun-16

10:08

30

37

53

22-Jun-16

57

23-Jun-16

13:04

102

104

103

27-Jun-16

115

28-Jun-16

13:02

74

74

70

Average

(Range)

75

(54 ¡V 115)

Average

(Range)

60

(30 ¡V 104)

 

Table 4-3         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM3

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

4-Jun-16

144

6-Jun-16

13:10

45

47

46

10-Jun-16

63

11-Jun-16

10:00

36

38

35

16-Jun-16

99

17-Jun-16

10:05

65

39

40

22-Jun-16

118

23-Jun-16

13:07

98

100

101

27-Jun-16

41

28-Jun-16

13:04

76

73

66

Average

(Range)

93

 (41 ¡V 144)

Average

(Range)

60

 (35 ¡V 101)

 

Table 4-4         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM4b

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

1-Jun-16

57

2-Jun-16

11:18

56

42

41

7-Jun-16

33

8-Jun-16

10:12

67

70

70

13-Jun-16

41

14-Jun-16

10:08

63

64

62

18-Jun-16

50

20-Jun-16

10:25

96

95

92

24-Jun-16

42

25-Jun-16

10:00

78

77

85

29-Jun-16

34

30-Jun-16

9:12

82

75

76

Average

(Range)

43

(33 - 57)

Average

(Range)

72

(41 ¡V 96)

 

Table 4-5         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM5a

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

1-Jun-16

23

2-Jun-16

11:17

33

23

23

7-Jun-16

26

8-Jun-16

10:13

74

69

57

13-Jun-16

37

14-Jun-16

10:00

85

86

84

18-Jun-16

26

20-Jun-16

10:24

91

90

92

24-Jun-16

29

25-Jun-16

9:55

83

85

76

29-Jun-16

24

30-Jun-16

9:21

73

74

71

Average

(Range)

27

(23 - 37)

Average

(Range)

71

(23 ¡V 92)

 

Table 4-6         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM6

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

1-Jun-16

44

2-Jun-16

10:29

50

36

27

7-Jun-16

68

8-Jun-16

10:01

67

69

66

13-Jun-16

81

14-Jun-16

9:45

80

82

79

18-Jun-16

94

20-Jun-16

9:56

94

94

97

24-Jun-16

65

25-Jun-16

9:45

80

79

87

29-Jun-16

127

30-Jun-16

9:26

67

65

66

Average

(Range)

80

(44 - 127)

Average

(Range)

71

(27 ¡V 97)

 

Table 4-7         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM7b

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

1-Jun-16

54

2-Jun-16

9:22

88

83

88

7-Jun-16

32

8-Jun-16

10:16

36

32

31

13-Jun-16

49

14-Jun-16

9:21

117

113

91

18-Jun-16

44

20-Jun-16

9:28

54

53

50

24-Jun-16

43

25-Jun-16

9:49

23

25

24

29-Jun-16

124

30-Jun-16

9:13

82

87

102

Average

(Range)

58

(32 - 124)

Average

(Range)

66

(23 ¡V 117)

 

Table 4-8         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM8

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

1-Jun-16

32

2-Jun-16

13:04

68

58

68

7-Jun-16

29

8-Jun-16

9:28

15

14

14

13-Jun-16

40

14-Jun-16

13:07

124

119

96

18-Jun-16

30

20-Jun-16

13:07

58

53

35

24-Jun-16

34

25-Jun-16

9:33

23

25

24

29-Jun-16

22

30-Jun-16

13:01

65

68

79

Average

(Range)

31

(22 - 40)

Average

(Range)

56

(14 -124)

 

Table 4-9         Summary of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st reading

2nd reading

3rd reading

6-Jun-16

68

6-Jun-16

13:04

26

27

26

11-Jun-16

52

11-Jun-16

13:04

50

51

49

16-Jun-16

10

17-Jun-16

13:07

50

36

37

22-Jun-16

24

23-Jun-16

9:35

17

17

23

27-Jun-16

36

28-Jun-16

13:10

35

31

32

Average

(Range)

38

(10 ¡V 68)

Average

(Range)

34

(17 ¡V 111)

 

4.2.2                 As shown in Tables 4-1 to 4-9, all the 1-hour TSP and 24-hour TSP monitoring results were below the Action/Limit Levels.  No Notification of Exceedance (NOE) was issued in this Reporting Period.

 

4.2.3                 The meteorological data during the impact monitoring days are summarized in Appendix K.

 


 

5                             Construction Noise Monitoring

5.1                       General

5.1.1                 In the Reporting Period, construction works under the project have been commenced in Contracts 2, 3, 5, 6, 7 and Contract SS C505 and noise monitoring was performed at all designated locations.

 

5.1.2                 Relocation of Noise Monitoring Location NM2 to NM2a was proposed and verified by IEC on 6 May 2016 and was effective on 9 May 2016.

 

5.1.3                 The noise monitoring schedule is presented in Appendix H and the monitoring results are summarized in the following sub-sections.

 

5.2                       Noise Monitoring Results in Reporting Month

5.2.1                 In the Reporting Period, a total of 45 event noise measurements were carried out at the designated locations.  The sound level meter was set in 1m from the exterior of the building façade including noise monitoring locations NM1, NM3, NM4, NM5, NM6, NM7, NM8 and NM9.  Therefore, no façade correction (+3 dB(A)) is added according to acoustical principles and EPD guidelines.  However, free-field status were performed at NM2a and NM10 and façade correction (+3 dB(A)) has added according to the requirement in this month.  The noise monitoring results at the designated locations are summarized in Tables 5-1 and 5-2.  The detailed noise monitoring data are presented in Appendix I and the relevant graphical plots are shown in Appendix J.

Table 5-1         Summary of Construction Noise Monitoring Results

Construction Noise Level (Leq30min), dB(A)

Date

NM1

NM2a

NM8

NM9

NM10(*)

6-Jun-16

63

67

60

61

65

17-Jun-16

65

73

59

64

61

23-Jun-16

65

68

58

65

68

28-Jun-16

54

63

59

62

60

Limit Level

75 dB(A)

Remarks

(*)    façade correction (+3 dB(A) is added according to acoustical principles and EPD guidelines

Table 5-2         Summary of Construction Noise Monitoring Results

Construction Noise Level (Leq30min), dB(A)

 

Date

NM3

NM4

NM5

NM6

NM7

 

2-Jun-16

62

64

54

52

68

 

8-Jun-16

66

69

55

57

67

 

14-Jun-16

58

59

58

54

61

 

20-Jun-16

56

65

55

59

67

 

30-Jun-16

59

63

64

59

70

 

Limit Level

75 dB(A)

 

 

54

 

5.2.2                 As shown in Tables 5-1 and 5-2, the noise level measured at all designated monitoring locations were below 75dB(A). Furthermore, there was one noise complaint (Action Level exceedance) received from 1823 on 20 June 2016 and further clarification with the complainant by RE on 24 June 2016. Therefore, one Action Level exceedance was triggered.

 

 

 

 

 

 

 

 

 

6                             Water Quality Monitoring

6.1                       General

6.1.1                 In the Reporting Period, construction works under the project has been commenced in Contracts 2, 3, 5, 6, 7 and Contract SS C505 and water quality monitoring was performed at all designated locations.  The water quality monitoring schedule is presented in Appendix H.  The monitoring results are summarized in the following sub-sections.

 

6.2                       Results of Water Quality Monitoring

6.2.1                 In the Reporting Period, a total of thirteen (13) sampling days was scheduled to carry out for all designated locations with their control stations.  Except for WM3, total thirty-one (31) Limit Level (LL) and one (1) Action Level (AL) of water quality exceedances were respectively recorded at the monitoring stations WM1, WM2A, WM2B and WM4. According to ¡§Event and Action Plan¡¨ stipulation, additional water quality monitoring days respectively were conducted one day for WM1 and its control station, seven days for WM2A and its control station, one days for WM2B and its control station, one day for WM4 and its control stations.

 

6.2.2                 The key monitoring parameters including Dissolved Oxygen, Turbidity and Suspended Solids are summarized in Tables 6-1 to 6-5.  Breaches of water quality monitoring criteria are shown in Table 6-6.  Detailed monitoring database including in-situ measurements and laboratory analysis data are shown in Appendix I and the relevant graphical plot are shown in Appendix J.

Table 6-1         Water Quality Monitoring Results Associated of Contracts 2 and 3

Date

Dissolved Oxygen

(mg/L)

Turbidity

(NTU)

Suspended Solids

(mg/L)

WM4

WM4-CA

WM4-CB

WM4

WM4-CA

WM4-CB

WM4

WM4-CA

WM4-CB

2-Jun-16

7.2

7.3

6.8

9.4

7.5

16.6

8.0

7.0

13.5

4-Jun-16

7.3

7.5

6.8

8.9

6.9

11.6

8.5

3.0

9.0

6-Jun-16

7.9

8.2

7.5

423.0

336.0

231.5

542.5

368.5

206.5

#7-Jun-16

--

--

--

28.8

15.1

16.6

18.0

16.0

20.0

8-Jun-16

7.0

7.4

6.8

253.0

214.0

148.5

318.5

381.5

162.0

10-Jun-16

6.5

7.4

5.5

26.7

4.7

15.8

34.5

7.0

24.0

13-Jun-16

7.3

7.6

6.5

34.1

14.9

30.7

22.0

8.0

30.5

15-Jun-16

6.9

7.4

6.4

34.0

29.4

29.7

38.5

31.5

31.0

17-Jun-16

7.2

7.5

6.6

24.8

15.3

20.9

17.5

9.5

17.5

20-Jun-16

6.4

7.1

5.4

26.6

17.9

21.8

13.5

11.5

15.0

22-Jun-16

5.8

5.8

6.5

11.2

8.0

16.1

10.0

6.0

17.0

24-Jun-16

5.5

5.5

5.5

13.7

8.5

16.7

14.0

8.5

22.5

28-Jun-16

6.8

7.0

5.5

33.0

14.6

17.5

26.5

9.0

13.0

30-Jun-16

6.8

6.7

6.5

13.7

58.5

19.0

10.5

39.5

11.0

Remarks:

bold with underline indicated Limit Level exceedance

bold without underline indicated Action Level exceedance

# Additional water quality monitoring at the exceeded location(s) due to two consecutive monitoring days indicated Limit Level exceedance.

 

Table 6-2         Water Quality Monitoring Results Associated of Contracts 5, 6 and SS C505

Date

Dissolved Oxygen

(mg/L)

Turbidity

(NTU)

Suspended Solids

(mg/L)

WM1

WM1- Control

WM1

WM1- Control

WM1

WM1- Control

2-Jun-16

7.1

7.4

14.8

10.3

15.5

3.0

4-Jun-16

7.3

7.4

15.9

9.0

13.5

2.0

6-Jun-16

7.4

7.2

543.5

229.0

409.0

259.5

#7-Jun-16

--

--

18.8

8.1

34.0

11.0

8-Jun-16

5.7

6.5

26.5

11.9

41.5

27.0

10-Jun-16

7.2

7.4

15.1

17.3

25.5

6.0

13-Jun-16

7.0

6.5

10.7

8.1

39.5

10.0

15-Jun-16

7.1

7.1

21.9

11.4

20.0

5.5

17-Jun-16

7.5

7.5

29.8

96.0

23.0

100.5

20-Jun-16

7.4

7.6

27.6

21.7

25.5

6.0

22-Jun-16

6.5

6.7

39.6

16.6

53.5

10.5

24-Jun-16

6.1

5.9

28.2

22.5

35.5

12.5

28-Jun-16

6.5

5.4

44.3

43.5

28.5

21.0

30-Jun-16

6.6

6.7

39.7

21.9

51.0

16.5

Remarks:

bold with underline indicated Limit Level exceedance

# Additional water quality monitoring at the exceeded location(s) due to two consecutive monitoring days indicated Limit Level exceedance.

 

Table 6-3         Water Quality Monitoring Results Associated only Contract 6

Date

Dissolved Oxygen

(mg/L)

Turbidity

(NTU)

Suspended Solids

(mg/L)

WM2A

WM2A- C

WM2B

WM2B- C

WM2A

WM2A- C

WM2B

WM2B- C

WM2A

WM2A- C

WM2B

WM2B- C

#1-Jun-16

--

--

--

--

22.4

4.8

--

--

13.0

6.0

--

--

2-Jun-16

7.3

7.6

8.1

7.0

16.4

8.1

10.7

3.2

14.0

5.0

10.5

2.0

4-Jun-16

7.2

7.4

7.3

6.9

258.0

9.8

11.2

4.4

457.0

11.5

10.5

<2

6-Jun-16

7.6

8.1

7.9

7.9

421.0

96.0

213.5

96.5

534.5

86.5

256.0

207.5

#7-Jun-16

--

--

--

--

137.0

7.0

10.8

4.7

168.0

6.0

11.0

2.0

8-Jun-16

7.2

7.8

8.1

6.8

131.0

6.1

10.2

6.9

395.5

<2

9.5

<2

10-Jun-16

6.9

7.6

7.7

6.8

22.0

8.6

6.6

2.8

13.5

3.5

10.5

<2

13-Jun-16

7.4

7.8

7.7

6.6

218.5

8.7

10.9

9.7

111.5

6.0

9.0

<2

#14-Jun-16

--

--

--

--

212.0

6.2

--

--

203.0

5.0

--

--

15-Jun-16

7.1

7.6

7.3

6.7

71.2

7.0

10.9

4.0

73.5

3.0

10.5

<2

#16-Jun-16

--

--

--

--

159.5

33.3

--

--

152.0

29.0

--

--

17-Jun-16

7.2

7.7

7.9

6.5

358.0

44.4

11.1

8.2

300.5

6.5

10.5

13.5

#18-Jun-16

--

--

--

--

54.7

12.1

--

--

63.0

3.0

--

--

20-Jun-16

7.3

7.5

8.5

7.6

196.0

12.4

4.8

3.9

141.5

4.5

3.0

2.5

#21-Jun-16

--

--

--

--

231.0

10.3

--

--

300.0

7.0

--

--

22-Jun-16

6.5

5.2

5.9

4.4

24.2

13.8

10.8

3.3

13.5

3.0

10.5

2.0

#23-Jun-16

--

--

--

--

21.9

9.9

--

--

12.0

4.0

--

--

24-Jun-16

6.4

4.9

6.5

4.0

24.5

12.6

10.2

4.6

12.5

3.5

11.5

<2

28-Jun-16

6.6

7.1

7.4

5.2

44.2

40.5

11.2

3.3

14.5

14.0

6.5

<2

30-Jun-16

5.9

6.2

7.0

4.8

130.0

10.6

10.0

3.4

117.5

4.5

5.0

<2

 

Remarks:

bold with underline indicated Limit Level exceedance

# Additional water quality monitoring at the exceeded location(s) due to two consecutive monitoring days indicated Limit Level exceedance.

 

Table 6-4         Water Quality Monitoring Results Associated Contracts 2 and 6

Date

Dissolved Oxygen

(mg/L)

Turbidity

(NTU)

Suspended Solids

(mg/L)

WM3

WM3- Control

WM3

WM3- Control

WM3

WM3- Control

2-Jun-16

7.5

6.9

7.6

3.4

9.5

7.5

4-Jun-16

7.0

6.8

12.8

12.8

4.5

26.0

6-Jun-16

7.6

7.5

714.5

Over-range

900.0

1350.0

8-Jun-16

6.9

7.1

28.3

Over-range

30.0

1560.0

10-Jun-16

6.6

6.8

5.5

6.1

10.0

57.0

13-Jun-16

7.0

6.9

10.8

26.7

12.5

55.5

15-Jun-16

6.4

6.9

10.4

16.1

10.5

26.0

17-Jun-16

6.8

6.8

8.7

4.3

8.5

16.0

20-Jun-16

7.1

6.9

10.9

8.7

8.0

8.0

22-Jun-16

5.7

5.9

5.7

4.3

4.0

4.0

24-Jun-16

5.7

5.8

6.5

6.8

7.0

8.0

28-Jun-16

6.0

6.5

18.3

17.1

9.5

5.5

30-Jun-16

6.2

6.5

11.3

10.0

8.5

8.5

 

Table 6-5      Breaches of Water Quality Monitoring Criteria in Reporting Period

Location

Dissolved Oxygen

Turbidity

Suspended Solids

Total Exceedance

Action

Limit

Action

Limit

Action

Limit

Action

Limit

WM1

0

0

0

1

0

1

0

2

WM2A

0

0

0

13

0

13

0

26

WM2B

0

0

0

1

0

1

0

2

WM3

0

0

0

0

0

0

0

0

WM4

0

0

1

0

0

1

1

1

No of Exceedance

0

0

1

15

0

16

1

31

 

6.2.3                 In this Reporting Period, a total of thirty-one (31) Limit Level (LL) exceedances and one (1) Action Level (AL) exceedance, namely fifteen (15) LL exceedances and one (1) AL exceedance of turbidity and sixteen (16) LL exceedances of Suspended Solids were recorded for the Project and they are summarized in Table 6-5.

 

6.2.4                 NOE was issued to relevant parties upon confirmation of the monitoring result.  The cause of exceedance is summarized in Table 6-6 accordance to investigation findings and the detailed investigation reports for the exceedances are attached in Appendix N.

 

Table 6-6      Summary of Water Quality Exceedance in the Reporting Period

Date of Exceedance

Location

Exceeded Parameter

Cause of Water Quality Exceedance

6th June 2016

WM1

(C5, C6 and SS C505)

NTU & SS

According to the Daily Extract of Meteorological Observations from the Hong Kong Observatory, heavy rainfall was recorded on 6 June 2016. Water flow rate increased vigorously under the heavy rain and the sediment at the river bed was stirred up, resulting in turbid water. According to the field photos, accumulation of rubbish were observed at the bar screen of the box culvert near WM1 after heavy rainstorm on 6 June 2016. Water flow near WM1 was therefore retarded and turbid water was cumulated at WM1. Also, water level at the box culvert increased to a high level due to the combined effect of heavy rain and accumulation of rubbish, overflow of the Kong Yiu River occurred.

Hence, it is considered that the exceedance on 6 June 2016 was due to the heavy rain and accumulation of rubbish at the bar screen of the box culvert near WM1, and unlikely due to the construction activities of the Contract.

4th,6th, 7th, 8th, 13th, 14th, 15th 16th, 17th, 18th, 20th, 21th, 30th June 2016

WM2A

(C6)

NTU &SS

Exceedances on 4th, 6th, 7th, 8th June 2016

During joint site inspection with RE, IEC, ET and Contractor on 2 June 2016, it was observed that unknown source of turbid water was seeping out from the river bed at upstream of WM2A continuously, turning the water in the river turbid.

From the photo taken by the Contractor on 4 June 2016, it was observed that turbid water was seeping out from the river bed at upstream of WM2A continuously. Thus, it is considered that the exceedance on 4 June was likely due to the unknown source of turbid water.

According to the Daily Extract of Meteorological Observations from the Hong Kong Observatory, intense rainfall (100-150 mm) was recorded at Ta Kwu Ling monitoring station on 6 June 2016. Under the intense rain, water flow rate increased vigorously and the sediment at the river bed was stirred up at WM2A, resulting in turbid water. As the river bed at WM2A-C was mostly small rocks, the stirred up of sediment at WM2A-C was limited. The turbid water recorded at WM2A-C may due to runoff from upper stream or surrounding slopes.

According to the Daily Extract of Meteorological Observations from the Hong Kong Observatory, heavy rainfall (10-20 mm) was recorded at Ta Kwu Ling monitoring station on 7 and 8 June 2016. Water flow rate increased and the stirred up sediment could not settle down in a short period of time after intense raining on 6 June 2016. The river bed at WM2A was cumulated with thick silt and sediment, while the river bed at WM2A-C was mostly small rocks. Hence, sediment stirred up more vigorous in WM2A while the stirred up of sediment at WM2A-C was limited. It is considered that the exceedances on 6, 7 and 8 June at WM2A were related to the heavy rainfall.

 

Exceedance on 30th June 2016

During weekly joint site inspection with RE, IEC, ET and Contractor(CCKJV) on 30 June 2016, no discharge and surface runoff was observed from the site.  As water mitigation measures, wastewater treatment facilities including one AquaSed and three series of sedimentation tank have been installed for piling work and most of the time the wastewater was recirculated. However, it was observed that unknown source of turbid water was seeping out from the river bed. Hence, it is considered that the exceedance on 30 June 2016 was due to the above event.

 

Exceedance on 13th, 14th, 15th 16th, 17th, 18th, 20th, 21th June

During joint site inspection with RE, IEC, ET and Contractor (CCKJV) on 16 June 2016, no surface runoff was observed from the site into the river.

As advised by the Contractor, the source of turbid water recorded at WM2A was identified. Due to continual heavy loading, uneven ground and cracks on the haul road were formed.  As dust suppression measures, a series of sprinklers was installed along the haul road for continuous spraying and the excessive water was cumulated on uneven ground/ cracks.  When vehicles passed the puddles, muddy water trapped on the uneven ground/ cracks was spilled from the road into a channel connecting to Ping Yuen River.

To resolve the deficiency, the Contractor has filled the uneven ground and reduce the frequency of water spraying on that area. Also, the haul road was levelled up to avoid muddy runoff.  The situation was found improved during site inspection on 7 July 2016.

There was no exceedance recorded in the subsequent monitoring days on 22, 23 June 2016. Hence, it is considered that the rectification measures carried out by the Contractor were effective in preventing further exceedances.

 

6th June 2016

WM2B

(C6)

NTU &SS

According to the Daily Extract of Meteorological Observations from the Hong Kong Observatory, heavy rainfall was recorded on 6 June 2016. The flow rate of the river increased vigorously, sediment and cumulated silt at the river bed was stirred up during rain, resulting in turbid water in river channel.

Apart from the disturbance of cumulated silt at the river bed during rain, it was observed that trails of muddy runoff from the public road surface into the existing channel under the rain. Thus, it is considered that the exceedance on 6 June 2016 is due to the heavy rainfall.

6th June 2016

WM4

(C2 and C3)

NTU &SS

According to the Daily Extract of Meteorological Observations from the Hong Kong Observatory, heavy rainfall was recorded on 6 June 2016. Water flow rate increased vigorously under the heavy rain and the sediment at the river bed was stirred up, resulting in turbid water.

It is considered that the exceedances were due to the heavy rainfall and unlikely related to the construction activities under the Contracts.

 

 

 

 

7                             Waste Management

7.1                       General Waste Management

7.1.1                 Waste management was carried out in accordance with the Waste Management Plan (WMP) for each contract.

 

7.2                       Records of Waste Quantities

7.2.1                 All types of waste arising from the construction work are classified into the following:

l Construction & Demolition (C&D) Material;

l Chemical Waste;

l General Refuse; and

l Excavated Soil.

 

7.2.2                 The quantities of waste for disposal in this Reporting Period are summarized in Tables 7-1 and 7-2 and the Monthly Summary Waste Flow Table is shown in Appendix L.  Whenever possible, materials were reused on-site as far as practicable.

Table 7-1         Summary of Quantities of Inert C&D Materials for the Project

Type of Waste

Contract 2

Contract 3

Contract 5

Contract 6

Contract 7

Contract SS C505

Total Quantity

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

C&D Materials (Inert)

(in '000m3)

62.4192

--

0.523

--

0

--

61.126

--

0.613

--

0.104

--

124.7852

Reused in this Contract (Inert)

(in '000 m3)

0.5848

--

0

--

0

--

 6.921

--

0

--

8.541

--

16.0468

Reused in other Contracts/ Projects (Inert)

(in '000 m3)

45.2952

C6/ NENT# & other projects approved by the ER

0

--

0

--

23.286

C5 & other projects approved by the ER

0

--

0

--

68.5812

Disposal as Public Fill (Inert)

(in '000 m3)

16.5392

Tuen Mun 38

0.420

Tuen Mun 38

0

--

30.919

Tuen Mun 38

0.613

Tuen Mun 38

0.104

TKO 137

48.5952

Remark #: The C&D materials were delivered to NENT for reuse by laying cover of the landfilling area.

 

Table 7-2        Summary of Quantities of C&D Wastes for the Project

Type of Waste

Contract 2

Contract 3

Contract 5

Contract 6

Contract 7

Contract SS C505

Total

Quantity

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

Qty.

Disposal location

Recycled Metal (¡¥000kg) #

67.73

-

0

-

0

--

0

--

0

--

725.0582

Licensed collector

792.7882

Recycled Paper / Cardboard Packing (¡¥000kg) #

0

-

0

-

0.062

--

0.166

Licensed collector

0.005

--

0.33

--

0.563

Recycled Plastic (¡¥000kg) #

0

--

0.001

-

0

--

0

--

0.001

--

0.004

--

0.006

Chemical Wastes (¡¥000kg) #

0

Licensed collector

0

-

0

--

0

--

0

--

0

--

0

General Refuses (¡¥000m3)

0.0916

NENT

0.135

NENT

0.01

NENT

0.043

NENT

0

--

0.117

NENT

0.3966

Remark #: Unit of recycled metal, recycled paper/ cardboard packing, recycled plastic and chemical waste for Contract 3 was in (¡¥000m3).


8                             Site Inspection

8.1                       requirements

8.1.1                 According to the approved EM&A Manual, the environmental site inspection shall be formulation by ET Leader.  Weekly environmental site inspections should carry out to confirm the environmental performance.

 

8.2                       Findings / Deficiencies During the Reporting Month

Contract 2

8.2.1                 In the Reporting Period, joint site inspection for Contract 2 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 3, 10, 17, 24, 29 June 2016.  No non-compliance was noted.

 

8.2.2                 The findings / deficiencies of Contract 2 that observed during the weekly site inspection are listed in Table 8-1.

Table 8-1           Site Observations for Contract 2

Date

Findings / Deficiencies

Follow-Up Status

3 June 2016

Ÿ  The contractor was reminded to provide proper maintenance for the de-silting system and make sure the system is in normal operation condition. (South and North Portal)

Ÿ  Not required for reminder.

 

 

 

 

10 June 2016

Ÿ  Turbidity and muddy water cumulated inside the de-silting plant area should be clean to prevent overflow into the stream. (North Portal)

Ÿ  Not required for reminder.

 

17 June 2016

Ÿ  Milky water was observed at the discharge outfall in Mid-vent, the Contractor should review the water diversion system and ensure the water which fulfil the discharge license before discharge. (Location: Mid-vent)

Ÿ  It was observed that the pH value was over the standard level. The Contractor should ensure pH adustment is provided for the wastewater treatment and ensure the pH value is within 6-9 before discharge. (Location: Mid-vent)

Ÿ  Mosquito breeding control measures was checked during the site inspection.

Ÿ  No turbidity water discharge was observed.

 

 

 

Ÿ  pH value resumed to normal after cleaning the pH probe and testing with the pH paper the pH level is comply with the discharge license requirement.

Ÿ  Not required for reminder.

 

24 June 2016

Ÿ  Stagnant water cumulated inside the lifting eye of the concrete block was observed. The contractor was reminded to fill up the lifting eye to prevent stagnant water accmulation.

Ÿ  Lifting eyes has been filled up with sand.

29 June 2016

Ÿ  No adverse environmental issue was observed.

Ÿ  NA

 

Contract 3

8.2.3                 In the Reporting Period, joint site inspection for Contract 3 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 22, 27 June 2016.  No non-compliance was noted.

 

8.2.4                 The findings / deficiencies of Contract 3 that observed during the weekly site inspection are listed in Table 8-2.

Table 8-2           Site Observations for Contract 3

Date

Findings / Deficiencies

Follow-Up Status

6 June 2016

Ÿ  No adverse environmental issue was observed.

Ÿ  NA

13 June 2016

Ÿ  Muddy trail was observed near SA1A. The Contractor should remove the muddy trail and ensure all the vehicles are washed properly before leaving the site.

Ÿ  No muddy trail was observed near SA1A.

22 June 2016

Ÿ  Noise emission label was missing on a handheld breaker, the Contractor should display the noise emission label on the handheld breaker.

Ÿ  Noise emission label was provided for the handheld breaker.

27 June 2016

Ÿ  Chemical container without drip tray was observed near NB68. The Contractor should provide drip tray for the chemical container to avoid land contamination.

Ÿ  Not required for reminder.

 

 

Contract 5

8.2.5                 In the Reporting Period, joint site inspection for Contract 5 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 22, 28 June 2016.  No non-compliance was noted.

 

8.2.6                 The findings / deficiencies of Contract 5 that observed during the weekly site inspection are listed in Table 8-3.

Table 8-3           Site Observations for Contract 5

Date

Findings / Deficiencies

Follow-Up Status

7 June 2016

Ÿ  No adverse environmental issue was observed.

Ÿ  NA

14 June 2016

Ÿ  No adverse environmental issue was observed.

Ÿ  NA

22 June 2016

Ÿ  No adverse environmental issue was observed.

Ÿ  NA

28 June 2016

Ÿ  No adverse environmental issue was observed.

Ÿ  NA

 

 

Contract 6

8.2.7                 In the Reporting Period, joint site inspection for Contract 6 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 2, 10, 16, 23, 30 June 2016.  No non-compliance was noted.

 

 

8.2.8                 The findings / deficiencies of Contract 6 that observed during the weekly site inspection are listed in Table 8-4.

Table 8-4           Site Observations for Contract 6

Date

Findings / Deficiencies

Follow-Up Status

2 June 2016

Ÿ  Stagnant water accumulated was observed at Bridge D. The Contractor should remove the stagnant water to prevent mosquito breeding.

Ÿ  Exposed slope adjacent to Ping Yuen River was observed at Bridge D. The Contractor should cover the exposed slope to prevent muddy runoff.

 

Ÿ  The uneven ground has been filled up with soil.

 

Ÿ  Exposed slop surface has been covered with tarpaulin sheet.

 

 

10 June 2016

Ÿ  Earth bund should be provided to prevent surface runoff overflow into public area. (Bridge D)

Ÿ  Wooden boards have been erected to prevent run-off from entering public area.

16 June 2016

Ÿ  The cover of control panel of an air compressor was left open, the Contractor should ensure the cover of the air compressor is closed properly. (Location: Bridge D)

Ÿ  A tree without proper protective fencing was found in Bridge D, the Contractor should provide tree protection fencing for the tree.

Ÿ  The cover of air compressor has been closed.

 

 

Ÿ  Tree protection fencing has been provided.

 

23 June 2016

Ÿ  No adverse environmental issue was observed.

 

Ÿ  NA

30 June 2016

Ÿ  Sandy vehicle trails at site exit of LMH road was observed, the Contractor should ensure all the vehicles are washed before leaving the site and also to maintain the cleanliness condition at the site exit.

Ÿ  Exposed earth surface along the site boundary at LMH road was found, the Contractor should provide relevant mitigation measures to prevent surface run-off.

Ÿ  It was reminded that water accumulated in drip tray should be cleaned up especially after rain.

Ÿ  The site exit has been cleaned and the wheel washing procedure is maintained.

 

 

 

Ÿ  Exposed surface has been covered with tarpaulin sheet and sandbag bund is provided.

 

Ÿ  Not required for reminder.

 

 

 

Contract SS C505

8.2.9                 In the Reporting Period, joint site inspection for Contract SS C505 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 15, 22, 29 June 2016. No non-compliance was noted.  

 

8.2.10             The findings / deficiencies of Contract SS C505 that observed during the weekly site inspection are listed in Table 8-5.

Table 8-5           Site Observations for Contract SS C505

Date

Findings / Deficiencies

Follow-Up Status

1 June 2016

Ÿ  Stagnant water was observed near Training Centre, Building 4 and PTB. The Contractor should remove the stagnant water to prevent mosquito breeding.

Ÿ   Mud clearing work at drainage channel near Training Centre was carried out to avoid accumulation of stagnant water.

Ÿ   Stagnant water was removed near Building 4.

Ÿ   Water pump was provided to remove the stagnant water near PTB.

8 June 2016

Ÿ  Stagnant water was observed at PTB, PTB Northside near drainage channel, near building 5 and near the portable toilet at Portion 1. The Contractor should remove the stagnant water to prevent mosquito breeding.

Ÿ   The stagnant water at PTB was removed.

Ÿ   Stagnant water near PTB Northside near drainage channel was pumped away.

Ÿ   Water pump was provided to remove the stagnant water near Building 5.

Ÿ   Stagnant water near the portable toilet at Portion 1 was removed.

15 June 2016

Ÿ  The Contractor was reminded to remove stagnant water on site after rainy days to prevent mosquito breeding.   

Ÿ   Not required for reminder.

 

22 June 2016

Ÿ  Stagnant water was observed at container in Portion 2 storage area, lifting eye of concrete paving slabs near Portion 2 storage area, and near CLP station. The Contractor should remove the stagnant water to prevent mosquito breeding.

Ÿ   Stagnant water at container in Portion 2 storage area was removed.

Ÿ   The lifting eyes of the concrete paving slabs were filled by sand to avoid accumulation of stagnant water.

Ÿ   Stagnant water near CLP station was removed.

29 June 2016

Ÿ  Chemical container without drip tray was observed near site office. The Contactor should provide drip tray for the containers to avoid land contamination.

Ÿ  Chemical leakage from mobile toilet near PTB was observed. The Contractor should carry out maintenance work for the mobile toilet to ensure no chemical leakage and treat the leaked chemical as chemical waste.

Ÿ   Chemical containers without drip tray were removed from site.

 

 

Ÿ   The leaked chemical was removed and treated as chemical waste.

 

 

Contract 7

8.2.11             In the Reporting Period, joint site inspection for Contract 7 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 22, 28 June 2016.  No non-compliance was noted.

 

8.2.12             The findings / deficiencies of Contract 7 that observed during the weekly site inspection are listed in Table 8-6.

 

Table 8-6           Site Observations for Contract 7

Date

Findings / Deficiencies

Follow-Up Status

7 June 2016

Ÿ  No adverse environmental issue was  observed.

Ÿ  NA

14 June 2016

Ÿ  Smoke emission from an air compressor was observed, the Contractor should provide plant maintenance to avoid smoke emission.

         Plant maintenance was provided for the air compressor, and no smoke emission was observed.

22 June 2016

Ÿ  No adverse environmental issue was  observed.

NA

28 June 2016

Ÿ  Free standing oil drum was observed on site, the Contractor should provide drip tray for all the chemical containers.

Ÿ  Water leakage through the pipe connection was found, the Contractor should maintain the condition of the pipe connection to avoid leakage.

              The oil drum has been removed from site.

              The condition of the pipe connection has been modified, no water leakage was observed.

 

8.2.13             Overall, general housekeeping such as daily site tidiness and cleanliness should be maintained for all Contracts.  Furthermore, the Contractors were reminded to implement Waste Management Plan of the Project.

 

Other Contracts

8.2.14             Since the construction work of Contract 4 has not commenced, no site inspection was performed.


 

9                             Environmental Complaint and Non-Compliance

9.1                       Environmental Complaint, Summons and Prosecution

9.1.1                 In the Reporting Period, no summons and prosecution under the EM&A Programme was lodged for Contracts 2, 3, 5, 6, 7 and Contract SS C505.  However, a total of Three (3) documented environmental complaints were received in the reporting month regarding to dust, noise and water issues. One (1) documented complaint is under investigation and the result will be presented in the coming monthly report. Two (2) documented environmental complaint received in April 2016 and Three (3) documented environmental complaints received in May 2016 were completed investigation. The investigation reports were reviewed by IEC. The detail of the complaints and the investigation results are presented below.

 

Investigation Result for the Documented Complaint received by 1823 on 28 April 2016

 

9.1.2                 A complaint was received on 28 April 2016 regarding suspected muddy water discharged from the construction site, affecting the growth of crops and condition of soil in farmland at junction of Wo Keng Shan Road and Ng Chow Road. The complainant also claimed that the gravestone was disappeared due to the construction activities in the above location.

9.1.3                 As the exact location of the disappeared gravestone cannot be provided by the complainant, investigation regarding to it cannot be conducted.

9.1.4                 According to Contractor¡¦s record (CCKJV), starting from the project¡¦s commencement, there is only one report of accidental leakage of muddy water from the site into the nearby farmland on 4 January 2016. Since after that, contractor and ET do not receive any record or complaint regarding to the discharge of muddy water to the nearby farms.

9.1.5                 During weekly joint site inspections with RE, IEC, ET and Contractor, no leakage of muddy water to the nearby farms was observed.

9.1.6                 As advised by the Contractor (CCKJV), the construction activities in the above location is mainly bored piling work. This construction activity unlikely generates any chemicals that contaminate the soil and adversely affect the growth of crops.

9.1.7                 To collect runoff due to the rain, the Contractor has provided mitigation measures such as site hoardings, concrete blocks, sandbags and temporary drainage. Also, it is advised that runoff due to the rain unlikely contains any chemicals that contaminate the soil and adversely affect the growth of crops.

9.1.8                 On 26 May 2016, a joint site inspection was carried out with RE, IEC, ET and Contractor, the findings during the site inspection are summarized below:

(a)       No leakage of soil or muddy water was observed from the site to the concerned farm.

(b)      Site hoardings, concrete blocks and sandbags barriers have been constructed along the boundary of the farm.

(c)       Temporary drainage was constructed and regularly maintained. Runoff is collected and diverted to treat in wastewater treatment facilities including the sedimentation tank and AquaSed. (As advised by the Contractor, in order to further enhance the performance of collecting runoff, water pump was provided to pump runoff in the temporary drainage to the wastewater treatment facilities)

9.1.9                 Based on the site observations and the work activity of the site, the complaint regarding to discharge of muddy water from the construction site, affecting the growth of crops and the condition of soil is not evidenced. Nevertheless, the Contractor (CCKJV) is reminded to follow the mitigation measures as recommended in the EM&A Manual. The ET will continue inspect the environmental performance of the construction site and ensure all activities comply with the relevant environmental contractual requirement.

 

 

Investigation Result for the Documented Complaint received by 1823 on 21 April 2016

 

9.1.10              A complaint was received from 1823 on 21 April 2016 and passed to CEDD and EPD. There are two concerns. Firstly, it is suspected that dump trucks were not washed in wheel washing facilities before leaving the site and the site had not carried out water spraying. Hence, these suspected concerns lead to dust nuisance to the nearby farmlands. Secondly, it is suspected that the Contractor discharged wastewater directly into the storm drain and Ng Tung River, affecting the residents and farmers of Tai Tong Wu.

9.1.11             A joint inspection was carried out by the Contractor, CEDD and RE on 21 April 2016. The inspected area included the wastewater treatment facilities (AquaSed SH-15) of C6 (CCKJV). CEDD has not given any adverse comments.

 

9.1.12             Dust

As advised by Contractor C6(CCKJV), they have carried out dust suppression measures to minimize construction dust impact. For instance,

(a)       Use of regular watering to reduce dust emissions from the construction sites, particularly   during dry weather.

(b)      Establishment and use of wheel washing facilities at the exit points of the site.

 

During weekly joint site inspection with RE, IEC, ET and Contractor on 7 April 2016, it was observed that wheel washing facilities was provided at vehicle exit point. Also, the exit was hard paved. The cleanliness condition of the site exit connecting to Sha Tau Kok Road was satisfactory.

9.1.13             As reported by C6, they have carried out regular watering to reduce dust impact. Besides, tarpaulin covering was provided on exposed slopes to minimize dust impact.

9.1.14             According to our air quality monitoring records from January to April 2016, no limit level exceedance was recorded on 1-hour and 24-hour Total Suspended Particulates (TSP) levels at air monitoring station AM7b, which is the nearest one to the complaint area.

9.1.15             Based on the observations from the site inspections and monitoring data, it is considered that the complaint regarding to dust is not evidenced.

 

9.1.16             Wastewater

As advised by Contractor of C6(CCKJV), in April 2016, all wastewater from that site area was stored in temporary pit and diverted to treat in wastewater treatment facilities including sedimentation tank and AquaSed. After that, all treated effluent was diverted to the drainage hole and then the drainage outlet for discharge.

9.1.17             During site inspection with Contractor(C6) on 23 May 2016, it was observed that the Contractor (C6) has provided AquaSed for wastewater treatment. From the photo taken, the effluent was visually clear. (Photo 8) Runoff from wheel washing is diverted to the temporary pit and then to the AquaSed. The treated effluent is used for wheel washing or diverted to the drainage outlet for discharge. Also, all storm drains were blocked. No discharge of wastewater or runoff into the storm drains and directly into Ng Tung River could be observed.

9.1.18             According to the monitoring data in April 2016, out of thirteen samplings in WM-3, four exceedances of turbidity at WM-3 was recorded and investigated. Investigation reports concluded that none of the exceedances were due to the direct discharge of wastewater into the storm drains or Ng Tung River.

9.1.19             Based on the observations from site inspection and the result of monitoring data, the complaint regarding to the direct discharge of wastewater in storm drains and Ng Tung River is not evidenced.

9.1.20             The Contractor (C6) is reminded to follow the mitigation measures as recommended in the EM&A Manual. Mitigation measures such as increasing the frequency of watering if necessary, carrying out regular desilting of sedimentation tanks shall be maintained. ET will continue inspect the environmental performance of the construction site and ensure all activities comply with the relevant environmental contractual requirement.

 

Investigation Result for the Documented Complaints received by 1823 on 28 May 2016

 

9.1.21             A complaint was received from 1823, regarding to the mud found on Sha Tau Kok Road -Wo Keng Shan was suspected from the construction site.

 

Contract 2 (Dragages)

9.1.22             On 2 June 2016, ET, IEC and RE carried out joint site inspection. It was observed that no muddy trails or loosen mud was found on Sha Tau Kok Road- Wo Keng Shan.

9.1.23             During weekly joint site inspection with RE, IEC, ET and Contractor (Dragages) on 3 June 2016, the observations are summarized below:

(a)   wheel washing facilities were provided at the site exit of North Portal within the site area. Vehicles were thoroughly washed before leaving construction site.

(b)   cleanliness condition of the exit of North Portal within the site area was satisfactory. Also, the site exit is clear of mud.

(c)   Water browser for haul road cleaning within the construction site was provided.

(d)   The footing of the administration building site was completed and hard paved.

(e)   Wheel washing facilities was provided for administration building site.

9.1.24             As advised by the Contractor, public road cleaning was provided on Sha Tau Kok Road by Contractor 2 (Dragages).

9.1.25             Since there were many other heavy vehicles using the Sha Tau Kok Road - Wo Keng Shan, it is considered that the mud on Sha Tau Kok Road - Wo Keng Shan is unlikely due to the Contract 2.  Nevertheless, ET will continue to inspect the cleanliness of site exit and adjacent roads.

 

Contract 6 (CCKJV)

9.1.26             During weekly joint site inspection with RE, IEC, ET and Contractor (CCKJV) on 2 June 2016, the observations are summarized below.

9.1.27             no muddy trails or loosen mud was found on Sha Tau Kok - Wo Keng Shan Road

9.1.28             wheel washing facilities were provided at the site exit.

9.1.29             cleanliness condition of the exit of North Portal and adjoined Sha Tau Kok Road were satisfactory. Also, the site exit is hard paved in concrete.

9.1.30             As advised by the Contractor, public road cleaning was provided on Sha Tau Kok Road by the Contractor.

9.1.31             During joint site inspection with RE, IEC, ET and Contractor on 26 May 2016, it was observed that wheel washing facilities was provided at site exit located at Sha Tau Kok Interchange. Also, the site exit is clear of mud.

9.1.32             Since there were many other heavy vehicles using the Sha Tau Kok -Wo Keng Shan Road, it is considered that the mud on Sha Tau Kok -Wo Keng Shan Road is unlikely due to the Contract 6.  Nevertheless, ET will continue to inspect the cleanliness of site exit and adjacent roads.

 

Investigation Result for the Documented Complaints received by CEDD on 26 May 2016

 

9.1.33             A complaint was received from CEDD on 26 May 2016, regarding noise nuisance from the construction site of Contract 2 (North Portal). Loi Tung Villagers complained that noise was made at midnight from the construction site. Also, early in the morning at 5, dump trucks were suspected to operate in the construction site, making noise thus affecting the daily lives of villagers

9.1.34             In view of (1) the complaint location which is North Portal of Construction Site of Contract 2 (2) Loi Tung Villagers complained that noise was made at midnight from the construction site. The construction noise permit applicable for the use of Powered Mechanical Equipment from 23:00 ¡V 7:00 for this complaint is GW-RN0359-16.

9.1.35             Regarding the complaint of noise from dump trucks, the Contractor advised that the noise source may come from the dump trucks queuing outside the site on Sha Tau Kok Road early in the morning at around 5 to 6, waiting to enter the construction site at around 7 am on working days (not included on Sunday or public holidays). To address public concern, the Contractor has requested the dump trucks¡¦ drivers to arrive after 6:30am on working days (not included on Sunday or public holidays).

 

Administrative procedure of managing the use of Powered Mechanical Equipment (PME)

9.1.36             As advised by the Contractor (DHK), the DHK¡¦s environmental team (Appointed Environmental Officer - Simon Wong, Appointed Environmental Supervisor - Tony Tsoi) review the content of a construction work reporting form before the start of the work on every working day. The respective working area, powered mechanical equipment (PME) grouping, CNP number and restricted hour sections are clearly written. The night shift foreman have to sign to ensure the operations of PME according to the listed groupings.

 

Observations on 27 May 2016

9.1.37             Based on the photos provided by RE on 30 May 2016 and the report from the night shift team from AECOM, the observations on 27 May 2016 are summarized below:

(a)       The operators of powered mechanical equipment (tracked excavator and loader) were stopped immediately from starting the machine outside tunnel by Resident Supervisory Staff. No machine was operating outside the tunnel. Hence, there was no non-compliance of construction noise permit conditions

(b)      Two tunnel doors were kept partly opened through the night while the work activities inside the tunnel were uncertain based on the photos. As advised by DHK, TBM was broken down on 27 May 2016. Under the circumstances, TBM¡¦s operation was ceased. Hence, there was no non-compliance of construction noise permit conditions.

 

Site investigation by ET

9.1.38             During site inspection by ET at around 1 :00 am on 31 May 2016, the findings are summarized below:

(a)    No powered mechanical equipment was observed to be operated at any works areas including working areas C, E, F, H and I of the CNP outside the tunnel.

(b)   Two tunnel doors were completely closed.

(c)    No dump trucks queuing on Sha Tau Kok Road could be observed.

(d)   No particular noise with low or high frequency could be noted.

Based on the site findings, no non-compliance of CNP conditions could be found.

 

9.1.39             As advised by the Contractor, specific refresh trainings on this particular CNP are provided by competent person (Appointed Environmental Officer - Simon Wong or Appointed Environmental Supervisor - Tony Tsoi) to the frontline staff. Besides, simple pictorial illustrations are displayed in the site for easy understanding of the grouping of PME to be used under restricted hours. Also, random spot checks at different time of night will be carried out to ensure compliance with CNP. The Contractor is advised to strengthen the administrative procedures in managing the use of PME such as preparing copies of the reporting form to frontline staff to remind them the operations of proper PME on restricted hour. The Contractor (DHK) is reminded to fully follow the conditions under the construction noise permit

 

Investigation Result for the Documented Complaints received by 1823 on 31 May 2016

 

9.1.40             A complaint was received from 1823, regarding water spraying over dump trucks was suspected to be carried out outside site area. The above action resulted in muddy water on Sha Tau Kok Road - Wo Hang and Sha Tau Kok Road - Ma Mei Ha, affecting other road users.

9.1.41             As advised by Contractor (Dragages), vehicles were thoroughly washed in the wheel washing facilities within the site area.

9.1.42             On 2 June 2016, ET, IEC and RE carried out joint site inspection. It was observed that no muddy trails or loosen mud was found on Sha Tau Kok Road - Ma Mei Ha. The cleanliness condition of the site exit connecting Sha Tau Kok Road was satisfactory. The site exit is hard paved. Also, no water spraying activities at the site exit connecting Sha Tau Kok Road was observed.

9.1.43             During weekly joint site inspection with RE, IEC, ET and Contractor (Dragages) on 3 June 2016, the observations are summarized below.

(a)   wheel washing facilities were provided at the site exit of North Portal which is inside the site area. Vehicles were thoroughly washed before leaving construction site.

(b)   cleanliness condition of the site exit of North Portal within the site area was satisfactory. Also, the site exit is hard paved.

9.1.44             According to the site inspections on 2 and 3 June 2016, no water spraying activities outside the work area by Contract 2 (Dragages) could be observed. While the complaint regarding water spraying to dump trucks outside the work area is not evidenced based on the site observations, the Contractor is reminded to fully implement the mitigation measures as specified in the implementation schedule of the EM&A manual.

 

Investigation Result for the Documented Complaints received by 1823 on 10 June 2016

 

9.1.45             A complaint was received from 1823, regarding to the mud found on Lin Ma Hang Road was suspected from the construction site.

9.1.46             Considering the site areas located along Lin Ma Hang Road, four contracts which under the Project may involve in this complaint, are included Contract 5 (SRJV), Contract 6 (CCKJV), Contract 7 (KRSJV) and SS C505 (Leighton). These four Contracts were all under our investigation and presented in this investigation report.

9.1.47             Site investigation had been carried out by ET, RE and the Contractor of C6 (CCKJV) on 14 June 2016, the observations are summarized below.

In General:

9.1.48             Having reviewed the complaint locations and the photo records provided by complainant, the condition of Lin Ma Hang Road was considered as satisfactory and no muddy trails or loosen mud was observed during the investigation on 14th June 2016.

 

9.1.49             Contract 5 (SRJV)

(a)    No muddy trails or loosen mud was found at the site exit of C5 and on Lin Ma Hang Road. Cleanliness condition of the Lin Ma Hang Road was satisfactory.

(b)   The most active construction works under C5 are located near Tai Kwu Ling Fire Station and Tai Kwu Ling Sub-division Police Station in Lin Ma Hang Road. No surface run-off or muddy trails were observed during the investigation and weekly joint site inspection on 14th June 2016.

(c)    Footpath paving, U-channel and tree & shrub planting had been completed, no surface runoff through the site area entering the public road was observed.

(d)   Less use of the site exit due the inactive construction activities at site exit in Lin Ma Hang Road. However, wheel washing facilities were provided at the site exit and the exit was hard paved in metal plate and stone.

(e)    It was concluded that the major and active construction works were located far from the complaint¡¦s location and the condition of site exit in Lin Ma Hang Road was considered as satisfactory.

 

9.1.50    Contract 6 (CCKJV)

(c)       Generally, no muddy trails or loosen mud was found on Lin Ma Hang Road and the site exits of C6.

(d)      Regard to C6, there were three site exits located in Lin Ma Hang Road, and only one site exit was located within the complaint¡¦s area.

(e)      Having investigated the complaint¡¦s area along the Lin Ma Hang Road, the cleanliness condition of the road was generally satisfactory. The site exit (SA22) was provided with wheel washing facility and the exit road was hard paved in concrete.

(f)      Apart from complaint¡¦s location, the cleanliness condition at the site exit of piling portion was considered as under average and needed further improvement. It was found that the water accumulated in the Lin Ma Hang Road was due to the uneven ground surface at the site exit of piling portion. The cause of the muddy water accumulated in the uneven ground surface was due to road watering, street washing and rain. However, the condition of other section of Lin Ma Hang Road was satisfactory.

(g)      Furthermore, the site exit of Bridge Y was provided with high pressure water jet and labour for wheel washing. The cleanliness condition at the site exit of Bridge Y was clean and no muddy trails was found.

(h) During the investigation, it was observed that water truck for road pressure washing carried by C6 for the purpose of dust suspension and road cleaning in regular basis.

(i)   Preventive measures for the surface run-off were provided for the construction activities along Lin Ma Hang Road. It was found that sheet pile, sandbag bund and pit were constructed to retain and avoid surface or storm water run-off.

(j)   It was concluded that the cleanliness condition of Lin Ma Hang Road, wheel washing facility at site exits and the preventive measures of run-off were generally satisfactory.

9.1.51      Contract 7 (KRSJV)

(a)    During the investigation, the cleanliness condition of the Lin Ma Hang Road at the site exit was satisfactory. No muddy trails or loosen mud was found on Lin Ma Hang Road and the site exit.

(b)   High pressure water jet and labour were provided at the site exit for vehicle washing.

(c)    It was concluded that construction works are located far from the complaint¡¦s location and the condition of site exit of C7 and the adjacent public road were considered as satisfactory.

 

9.1.52      SS C505 (Leighton)

(a)    During the investigation, the cleanliness condition of the Lin Ma Hang Road at the Portion of BCP area was satisfactory. No muddy trails or loosen mud was found on Lin Ma Hang Road and the site exit of SS C505.

(b)   Automatic wheel washing facilities were provided at the site exit and labour was also provided at the site exit to maintain cleanliness.

(c)    It was concluded that construction works are located far from the complaint¡¦s location and the condition of site exit of SS C505 and the adjacent public road were considered as satisfactory.

 

9.1.53                  As advised by the Contractors, public road cleaning was provided on Lin Ma Hang Road by the Contractor of Contract 5 and Contract 6.

9.1.54                  As informed by C6, muddy water leakage via the bored pile area entering the Lin Ma Hang Road was accidentally occurred at 11 am on 10th June 2016. Immediate corrective actions had promptly taken to stop the leakage and the muddy water on the public road was also cleaned up by 12:15 noon.

9.1.55                  As reported by C5, a private trailer driving through a muddy ground to Lin Ma Hang Road was recorded in the afternoon on 10th June 2016. Afterward muddy trails were found on road where is within the complaint¡¦s location in Lin Ma Hang Road.

9.1.56                  According to the Hong Kong Observatory record, about 20mm ~ 30mm rainfall was recorded in North District at 12 noon to 2 p.m. on 10 June 2016. As one of the considerations, the rainwater could cumulate in the uneven ground surface on Lin Ma Hang Road and cause puddle.

9.1.57                  In conclusion, firstly immediate corrective actions for the incident of leakage to stop the leakage and to clean up muddy water on the road were taken by C6 within an hour. Furthermore, the location of leakage was not within the complaint¡¦s area. Secondly, rainwater accumulated in the uneven ground surface in Lin Ma Hang Road could possibly happened during and after the rainfall. Thirdly, private trailer causing muddy trails within the complaint¡¦s area was recorded and the puddle could lead to the occurrence of muddy water. Finally, based on our observations from the investigation on 14th June 2016, it is considered that the mud on Lin Ma Hang Road is unlikely due to the Contract 5 (SRJV), Contract 6 (CCKJV), Contract 7 (KRSJV) and SS C505 (Leighton).  Nevertheless, ET will continue to inspect the cleanliness of site exits and adjacent roads.

9.1.58                  In view of the incident of leakage by C6, the Contractor of C6 is recommended to improve the preventive measures of surface run-off and improve the condition of uneven ground surface in Lin Ma Hang Road, such as 1.) Improve cut-off drain at site exits for the water diversion and prevention of surface run-off. 2.) Enhance the preventive measures such as sandbag bund, earth bund and U-channel at construction activities area. 3.) Improve the condition of uneven ground surface to minimize puddle in Lin Ma Hand Road.

 

Investigation Result for the Documented Complaints received by 1823 on 20 June 2016

 

9.1.59             A complaint received from 1823 on 20 June 2016 regarding noise nuisance from Lain Tang Construction work. After identifying the date, time as well as the exact location with the complainant, the complainant advised that the concerned construction work was not carried out by CEDD¡¦s Contractors. The complainant complained that piling works carried out by (SSC 505) Leighton subcontractor Kwan Shing at BCP site recently generated high noise level. Also, during the piling works, the complainant queried why no noise abatement measures such as fabric cover being available. The complaint was transferred to ArchSD on 8 July 2016. This complaint is still under investigation and the result will be presented in the next monthly report.

 

Investigation Result for the Documented Complaints received by ICC on 20 June 2016

 

9.1.60             A complaint was received from ICC, regarding uneven ground and muddy water found on Lin Ma Hang Road.

9.1.61             During weekly joint site inspection by RE, IEC, ET and Contractor (CCKJV) on 30 June 2016, uneven ground was found near the site exit of piling portion of Contract 6 on Lin Ma Hang Road.  It was observed that muddy water was cumulated in the puddles created from the uneven ground after road cleaning by water truck and rainfall.

9.1.62             Since Lin Ma Hang Road is a public road and frequent used by heavy vehicles, it is believed that the uneven ground was due to over usage and not created by construction of Contract 6.

9.1.63             Regarding to the muddy water issue, there were three site exits located on Lin Ma Hang Road and the condition of the site exits were inspected during regular site inspection.  Our observations are summarized in below.

9.1.64             (a) The site exit (SA22) was provided with wheel washing facility and the exit road was hard paved in concrete.  No muddy water getting into Lin Ma Hang Road was observed.

9.1.65             (b) The site exit of piling portion was provided with high pressure water jet and labour for wheel washing. Also, cut off drain was provided at site exit for collecting water from vehicles¡¦ washing. No muddy water getting into Lin Ma Hang Road was observed.

9.1.66             (c) The site exit of Bridge Y was provided with high pressure water jet and labour for wheel washing. No muddy water getting into Lin Ma Hang Road was observed.

9.1.67             According to the findings during site inspection, the muddy water found on Lin Ma Hang Road was unlikely caused by the works of CCKJV.  To address public concern, C6 has repaired the uneven ground by paving asphalt on 8 July 2016 to minimize the impact to the public. The ET will closely inspect the cleanliness of the Lin Ma Hang Road in forthcoming site inspections.

 

Table 9-1           Statistical Summary of Environmental Complaints

Reporting Period

Contract No

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

19 May 2014 ¡V

31 May 2016

Contract 2

0

17

Ÿ  (7) Water Quality

Ÿ  (7) Dust

Ÿ  (3) Noise

06 Nov 2013 ¡V

31 May 2016

Contract 3

0

4

Ÿ  (1) Dust

Ÿ  (2) Water quality

Ÿ  (1) Noise

16 Aug 2013 ¡V

31 May 2016

Contract 5

0

2

Ÿ  (2) Dust

16 Aug 2013 ¡V

31 May 2016

Contract 6

0

14

Ÿ  (11) Water Quality

Ÿ  (3) Dust

15 Feb 2016 ¡V

31 May 2016

Contract 7

0

0

N/A

16 Aug 2013 ¡V

31 May 2016

SS C505

0

0

N/A

1 ¡V 30 June 2016

Contract 2

0

17

Ÿ  (7)Water Quality

Ÿ  (7) Dust

Ÿ  (3) Noise

Contract 3

0

4

Ÿ  (1) Dust

Ÿ  (2) Water quality

Ÿ  (1) Noise

Contract 5

2

4

Ÿ  (3) Dust

Ÿ  (1) Noise

Contract 6

3

17

Ÿ  (12) Water Quality

Ÿ  (4) Dust

Ÿ  (1) Noise

Contract 7

2

2

       (1) Dust

       (1) Noise

SS C505

2

2

       (1) Dust

       (1) Noise

 

Table 9-2           Statistical Summary of Environmental Summons

Reporting Period

Contract No

Environmental Summons Statistics

Frequency

Cumulative

Complaint Nature

19 May 2014 ¡V

31 May 2016

Contract 2

0

0

NA

06 Nov 2013 ¡V

31 May 2016

Contract 3

0

0

NA

16 Aug 2013 ¡V

31 May 2016

Contract 5

0

0

NA

16 Aug 2013 ¡V

31 May 2016

Contract 6

0

0

NA

15 Feb 2016 ¡V

31 May 2016

Contract 7

0

0

NA

16 Aug 2013 ¡V

31 May 2016

SS C505

0

0

NA

1 ¡V 30 June 2016

Contract 2

0

0

NA

Contract 3

0

0

NA

Contract 5

0

0

NA

Contract 6

0

0

NA

Contract 7

0

0

NA

SS C505

0

0

NA

 

 

Table 9-3           Statistical Summary of Environmental Prosecution

Reporting Period

Contract No

Environmental Prosecution Statistics

Frequency

Cumulative

Complaint Nature

19 May 2014 ¡V

31 May 2016

Contract 2

0

0

NA

06 Nov 2013 ¡V

31 May 2016

Contract 3

0

0

NA

16 Aug 2013 ¡V

31 May 2016

Contract 5

0

0

NA

16 Aug 2013 ¡V

31 May 2016

Contract 6

0

0

NA

15 Feb 2016 ¡V

31 May 2016

Contract 7

0

0

NA

16 Aug 2013 ¡V

31 May 2016

SS C505

0

0

NA

1 ¡V 30 June 2016

Contract 2

0

0

NA

Contract 3

0

0

NA

Contract 5

0

0

NA

Contract 6

0

0

NA

Contract 7

0

0

NA

SS C505

0

0

NA

 

The Other Contracts

9.1.68             Since the construction works at the Contract 4 has not yet commenced, no environmental complaint, summons and prosecution under the EM&A Programme are registered in the Reporting Period.

 


10                         Implementation Status of Mitigation Measures

10.1                   General Requirements

10.1.1             The environmental mitigation measures that recommended in the Implementation Schedule for Environmental Mitigation Measures (ISEMM) in the approved EM&A Manual covered the issues of dust, noise, water and waste and they are summarized presented in Appendix M.

 

10.1.2             All contracts under the Project shall be implementing the required environmental mitigation measures according to the approved EM&A Manual as subject to the site condition.  Environmental mitigation measures generally implemented by Contracts 2, 3, 5, 6, 7 and Contract SS C505 in this Reporting Period are summarized in Table 10-1.  

 

Table 10-1         Environmental Mitigation Measures

Issues

Environmental Mitigation Measures

Water Quality

¡P       Wastewater to be treated by the wastewater treatment facilities i.e. sedimentation tank or similar facility before discharge.

Air Quality

¡P       Maintain damp / wet surface on access road

¡P       Low vehicular speed within the works areas.

¡P       All vehicles must use wheel washing facility before off site

¡P       Sprayed water during breaking works

¡P       A cleaning truck was regularly performed on the public road to prevent fugitive dust emission

Noise

¡P       Restrain operation time of plants from 07:00 to 19:00 on any working day except for Public Holiday and Sunday.

¡P       Keep good maintenance of plants

¡P       Place noisy plants away from residence or school

¡P       Provide noise barriers or hoarding to enclose the noisy plants or works

¡P       Shut down the plants when not in used.

Waste and Chemical Management

¡P       On-site sorting prior to disposal

¡P       Follow requirements and procedures of the ¡§Trip-ticket System¡¨

¡P       Predict required quantity of concrete accurately

¡P       Collect the unused fresh concrete at designated locations in the sites for subsequent disposal

General

¡P       The site was generally kept tidy and clean.

 

10.2                   Tentative Construction Activities in the Coming Month

10.2.1             Construction activities as undertaken in the coming month for the Project lists below:

Contract 2

Mid-Vent Portal

Ÿ    Tube excavation (NB+SB)

Ÿ    Adit waterproofing, lining and post-excavation grouting

Ÿ    Ventilation building superstructure

North Portal

Ÿ    Southbound TBM excavation

Ÿ    Northbound bottom bench excavation and tunnel enlargement

Ÿ    Ventilation building superstructure

Ÿ    Retaining walls and slope stabilization

South Portal

Ÿ    Southbound and Northbound D&B excavation

Ÿ    South ventilation building superstructure

Admin Building

Ÿ    Building superstructure

 

Contract 3

Ÿ   Cable detection and trial trenches

Ÿ   Filling works at Tong Hang East

Ÿ   Storm Drains Laying

Ÿ   Noise barrier construction

Ÿ   Pier / Pier Table construction

Ÿ   Pile cap works

Ÿ   Portal beam construction

Ÿ   Pre-drilling works and piling works for viaduct

Ÿ   Pre-drilling works for noise barrier and piling works for noise barrier

Ÿ   Retaining Wall construction

Ÿ   Road works

Ÿ   Sewer works

Ÿ   Slope works

Ÿ   Socket H-pile installation

Ÿ   Tree felling works

Ÿ   Utilities duct laying

Ÿ   Viaduct segment erection

Ÿ   Water works

Contract 5

Ÿ   Testing and commissioning of rising main (VO061) at LMH road

Ÿ   Bituminous laying at existing LMH road.

Ÿ   Brick laying at footpath of LMH road

Ÿ   Road works (kerb and bituminous laying) at existing LMH road

Ÿ   Irrigation system at existing LMH Road

Ÿ   Installation of underground utilities at existing LMH road

Ÿ   Planting works at proposed & existing LMH road

Contract 6

Ÿ   Slope Works

Ÿ   Bored Piling

Ÿ   Abutment and Pier Construction

Ÿ   Tunnel Works

Ÿ   Segment Installation

Ÿ   Road Works

Ÿ   Sewage Treatment Plant Construction

Contract 7

Ÿ   Piling Works at Bridge A,C,E

Ÿ   Pile caps construction at Bridge B,C,D

Ÿ   Column construction at Bridge C

Contract SS C505

Ÿ   General Site Setup

Ÿ   CLP temporally sub-station works

Ÿ   Building number 4, 5, 6, 9, 11 and 36 construction

Ÿ   Excavation waterproofing works for Building number 4, 6 and 11

Ÿ   H-pile works and load test

Ÿ   Disassembly of crawler crane

Ÿ   Grouting and full core to completed bored piles

Ÿ   Underground drainage works

Ÿ   Erection of Welfare Shelter

Ÿ   Prototype ¡§A¡¨ Construction works

Ÿ   Formwork and falsework for PTB¡¦s slap construction

Ÿ   Construction PTB M/F flat slab

Ÿ   Steel beam works for maintenance platform for PTB

Ÿ   Pile cap construction for PTB, including excavation and backfilling works

Ÿ   Bridge deck construction for Bridges 1, 2 & 3

Ÿ   Mock up for south entrance double curve cladding

Ÿ   Tower Crane Operation and erection

Ÿ   Pile Cap construction for building number 4, 6 and 7

Ÿ   Bridge construction works including construction of bridge column, retaining wall, pile cap and pier

 

10.3                   Key Issues for the Coming Month

10.3.1             Key issues to be considered in the coming month for Contracts 2, 3, 5, 6, 7 and SS C505 include:

Ÿ    Implementation of control measures for rainstorm;

Ÿ    Regular clearance of stagnant water during wet season;

Ÿ    Implementation of dust suppression measures at all times;

Ÿ    Potential wastewater quality impact due to surface runoff;

Ÿ    Potential fugitive dust quality impact due from the dry/loose/exposure soil surface/dusty material;

Ÿ    Disposal of empty engine oil containers within site area;

Ÿ    Ensure dust suppression measures are implemented properly;

Ÿ    Sediment catch-pits and silt removal facilities should be regularly maintained;

Ÿ    Management of chemical wastes;

Ÿ    Discharge of site effluent to the nearby wetland, stockpiling or disposal of materials, and any dredging or construction area at this area are prohibited;

Ÿ    Follow-up of improvement on general waste management issues; and

Ÿ    Implementation of construction noise preventative control measures

 

10.3.2             Since the construction work of Contract 4 has not commenced, no environmental issue is presented.


11                         Conclusions and Recommendations

11.1                   Conclusions

11.1.1             This is the 35th monthly EM&A report presenting the monitoring results and inspection findings for the Reporting Period from 1 to 30 June 2016.

 

11.1.2             For air quality monitoring, no 1-hour and 24-hour TSP monitoring results triggered the Action or Limit Levels were recorded. No NOEs or the associated corrective actions were therefore issued.

 

11.1.3             One noise complaint (which is an Action Level exceedance) was received and no construction noise measurement results that exceeded the Limit Level were recorded in the Reporting Period. The associated investigation report was submitted to relevant parties. No NOEs or the associated corrective actions were issued.

 

11.1.4             For water quality monitoring, a total of thirty-two (32) Action/ Limit Levels (AL/LL) exceedances, namely fifteen (15) LL exceedances and one (1) AL exceedance of turbidity and sixteen (16) LL exceedances of Suspended Solids. The investigations for the cause of exceedances have been conducted by the ET and the associated investigation reports were submitted to relevant parties.

 

11.1.5             No environmental summons or successful prosecutions were recorded in the Reporting Period. 

 

11.1.6             In this Reporting Period, a total three (3) documented environmental complaint were received in the reporting month regarding to water, dust and noise issue. Upon receipt of the complaints, RE, IEC and ET with the relevant Contractors has immediately undertaken investigation. In the Reporting Period, one complaint is under investigation, the investigation result will be presented in the coming monthly report.

 

11.1.7             During the Reporting Period, weekly joint site inspection by the RE, IEC, ET with the relevant Main-contractor were carried out for Contracts 2, 3, 5, 6, 7 and SS C505 in accordance with the EM&A Manual stipulation.  No non-compliance observed during the site inspection. 

 

11.2                   Recommendations

11.2.1             As wet season has come, preventive measures for muddy water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River or public area would be the key issue.  The Contractors should paid special attention on water quality mitigation measures and fully implement according ISEMM of the EM&A Manual, in particular for working areas near Ma Wat Channel and Ping Yuen River.  Moreover, all effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland and Coastal Waters criteria or discharge permits stipulation.

 

11.2.2             Construction noise would be a key environmental issue during construction work of the Project.  Noise mitigation measures such as using quiet plants should be implemented in accordance with the EM&A requirement.

 

11.2.3             Since most of construction sites under the Project are located adjacent to villages, the Contractors should fully implement air quality mitigation measures to reduce construction dust emission.

 

11.2.4             Furthermore, daily cleaning and weekly tidiness shall be properly performed and maintained. In addition, mosquito control should be kept to prevent mosquito breeding on site.