|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report
(No.54) ¡V January 2018 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
12 February 2018 |
TCS00694/13/600/R1448v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
8 February 2018 |
First
Submission |
2 |
12 February 2018 |
Amended according to the IEC¡¦s comments on 8
February 2018 |
|
|
|
executive summary
ES01
This is the 54th monthly EM&A
report presenting the monitoring results and inspection findings for the
reporting period from 1 to 31 January 2018 (hereinafter ¡¥the
Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract
3 (CV/2012/09), Contract 4 (NE/2014/02),
Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03)
and an ArshSD contract (Contract SS C505).
ES03
In the Reporting Period, the major
construction works under Liantang/Heung Yuen Wai Boundary
Control Point and Associated Works of the Project included Contract 2,
Contract 3, Contract 4, Contract
6, Contract 7 and Contract SS C505.
Environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the
following table.
Environmental Aspect |
Environmental Monitoring Parameters /
Inspection |
Reporting Period |
|
Number of Monitoring Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour
TSP |
9 |
147 |
24-hour
TSP |
9 |
54 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
45 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1
& WM1-C |
14 Scheduled & 0 extra |
WM2A(a)
& WM2A-Cx |
14 Scheduled & 4 extra |
||
WM2B
& WM2B-C |
14 Scheduled & 0 extra (*) |
||
WM3x
&WM3-C |
14 Scheduled & 2 extra |
||
WM4,
WM4-CA &WM4-CB |
14 Scheduled & 0 extra |
||
Ecology |
Woodland
compensation i)
General Health condition of planted species ii) Survival
of planted species |
9
Quadrats and transect |
0 |
Joint Site Inspection / Audit |
IEC, ET,
the Contractor and RE joint site Environmental Inspection and Auditing |
Contract
2 |
4 |
Contract
3 |
4 |
||
Contract
4 |
4 |
||
Contract
6 |
4 |
||
Contract
7 |
4 |
||
Contract
SS C505 (#) |
5 |
Remark:
(#) IEC only joined one (1) event of site inspection for Contract SS
C505.
(*) In
the whole Reporting Period, water sampling was unable to carry out at WM2B and WM2B-C due to shallow
water (water depth under 150mm)
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no air quality and construction noise exceedance and valid noise
complaint was recorded. For water quality monitoring, a total of
sixteen (16) Action/ Limit Level exceedances were recorded under the Project. The summary of exceedance in the
Reporting Period is shown below.
Environmental Aspect |
Monitoring
Parameters |
Action Level |
Limit Level |
Event
& Action |
|||
NOE
Issued |
Investigation
Result |
Project
related exceedance |
Corrective
Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
1 |
7 |
8 |
-
All exceedances were
not project related. |
0 |
The Contractor should fully implement water quality mitigation measure. |
|
SS |
0 |
8 |
8 |
0 |
ES05
Investigation
Reports for all water quality exceedances were completed by ET. Investigation
results revealed that the Contractor had properly implemented water quality mitigation
measures such as covering the expose area with tarpaulin sheet and provided
bunds align the watercourse. It
was concluded that the exceedances recorded at WM2A(a)
on 8 to 13 January 2018 and WM3x on 8 January 2018 were completed were related
to the impact of rainstorm and not caused by the works under the Project. For exceedances recorded atWM3x on 27 January
2018, it was concluded that the exceedances were related to the external source
of turbid water and not project related.
Environmental
Complaint
ES06
In this Reporting
Period, one (1) documented environmental complaint was received regarding the
waste management under the EM&A Programme. Investigation for the
complaint is underway and site inspection at complaint location is arranged on
9 February 2018 for investigation.
Notification of
Summons and Successful Prosecutions
ES07
No environmental summons
and prosecutions were recorded in the Reporting Period.
Reporting Change
ES08
No reporting changes
were made in the Reporting Period.
ES09
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 5, 12, 19 and 25
January 2018.
No non-compliance was noted during the site inspection.
ES10
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 4, 11, 17 and 25 January 2018. No non-compliance was noted during the site
inspection.
ES11 In the Reporting Period, joint site inspection to