|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report
(No.55) ¡V February 2018 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
13 March 2018 |
TCS00694/13/600/R1481v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
8 March 2018 |
First
Submission |
2 |
13 March 2018 |
Amended according to the IEC¡¦s comments on 9
March 2018 |
|
|
|
executive summary
ES01
This is the 55th monthly EM&A
report presenting the monitoring results and inspection findings for the
reporting period from 1 to 28 February 2018 (hereinafter ¡¥the
Reporting Period¡¦).
Environmental Monitoring
and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai
Boundary Control Point and Associated Works of the Project is
divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03), Contract
6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD
contract (Contract SS C505).
ES03
In the Reporting Period, the major
construction works under Liantang/Heung
Yuen Wai Boundary Control Point and Associated Works of the Project
included Contract 2, Contract 3, Contract 4, Contract
6, Contract 7 and Contract SS C505.
Environmental monitoring activities under the EM&A programme in the
Reporting Period are summarized in the following table.
Environmental Aspect |
Environmental Monitoring Parameters /
Inspection |
Reporting Period |
|
Number of Monitoring Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour
TSP |
9 |
135 |
24-hour
TSP |
9 |
40 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
45 |
Water Quality |
Water in-situ measurement and/or sampling |
WM1
& WM1-C |
10 Scheduled & 0 extra |
WM2A(a)
& WM2A-Cx |
10 Scheduled & 2 extra |
||
WM2B
& WM2B-C |
10 Scheduled & 0 extra (*) |
||
WM3x
&WM3-C |
11 Scheduled & 0 extra |
||
WM4,
WM4-CA &WM4-CB |
11 Scheduled & 0 extra |
||
Ecology |
Woodland
compensation i)
General Health condition of planted species ii) Survival
of planted species |
9
Quadrats and transect |
1 |
Joint Site Inspection / Audit |
IEC, ET,
the Contractor and RE joint site Environmental Inspection and Auditing |
Contract
2 |
4 |
Contract
3 |
4 |
||
Contract
4 |
4 |
||
Contract
6 |
4 |
||
Contract
7 |
4 |
||
Contract
SS C505 (#) |
4 |
Remark:
(#) IEC only joined one (1) event of site inspection for Contract SS
C505.
(*) In
the whole Reporting Period, water sampling was unable to carry out at WM2B and WM2B-C due to shallow
water (water depth under 150mm)
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no construction noise exceedance
and valid noise complaint was recorded. For air quality
monitoring, one (1) Limit Level exceedance of 24-hour TSP was recorded. For water quality monitoring, a total of four (4) Limit Level exceedances were recorded under the Project. The summary of exceedance in the
Reporting Period is shown below.
Environmental Aspect |
Monitoring
Parameters |
Action Level |
Limit Level |
Event
& Action |
|||
NOE
Issued |
Investigation
Result |
Project
related exceedance |
Corrective
Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
1 |
1 |
Not project related |
NA |
NA |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
0 |
2 |
2 |
-
All exceedances
were not project related. |
0 |
The Contractor should fully implement water quality mitigation measure. |
|
SS |
0 |
2 |
2 |
0 |
ES05
Investigation report
for the 24-hour TSP monitoring was completed by ET. Investigation results
revealed that the Contractor had properly implemented dust mitigation measures
such covering of the stockpile and providing water spraying for dusty haul road
and dusty area. Since Joss paper burning
was suspected to be conducted during period of sampling, which affecting the monitoring
result, it was conducted that the exceedance was not caused by the works under
the Project.
ES06
Investigation
Report for all water quality exceedances was completed by ET. Investigation results revealed that the
Contractor had properly implemented water quality mitigation measures such as
covering the expose area with tarpaulin sheet and providing bunds align the
watercourse. It was concluded
that all the exceedances were not related to the works under the Project. Nevertheless,
the Contractor was reminded to fully implement the water
quality mitigation measure
throughout the constriction phase as far as practicable.
Environmental
Complaint
ES07
In this Reporting
Period, no documented environmental complaint was received under the EM&A
Programme.
Notification of
Summons and Successful Prosecutions
ES08
No environmental summons
and prosecutions were recorded in the Reporting Period.
Reporting Change
ES09
No reporting changes
were made in the Reporting Period.
ES10
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 2, 9, 15 and 23 February
2018.
No non-compliance was noted during the site inspection.
ES11
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 14 and 22 February 2018. No non-compliance was noted during the site
inspection.
ES12
In the Reporting Period, joint site
inspection to evaluate
the site environmental performance at Contract 4 has been
carried out by the RE, IEC, ET and
the Contractor on 2, 9, 12 and 22
February 2018. No non-compliance was noted.
ES13
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 14 and 23 February 2018. No non-compliance was noted during the site
inspection.
ES14
In the Reporting Period, joint site
inspection for Contract 7 to
evaluate the site environmental performance has been carried out by the RE,
IEC, ET and the Contractor on 2, 9, 13 and 22
February 2018. No non-compliance was noted during the site
inspection.
ES15
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, ET and the Contractor on 7, 14, 21 and 28
February 2018 in which IEC joined the site inspection on 21
February 2018. No non-compliance was noted during the site
inspection.
Future Key Issues
ES16
During dry season, special attention
should be paid on the potential construction dust impact since most of the construction sites are adjacent
to villages. The Contractor should fully implement the construction dust
mitigation measures as appropriately.
ES17
Preventive measures for
muddy water or other water pollutants from site surface flow to local stream such
as Kong Yiu Channel, Ma Wat Channel, Ping
Yuen River, Kwan Tei River or public area should be
properly maintained. The Contractors should paid special attention on water
quality mitigation measures and fully implement according ISEMM of the EM&A
Manual, in particular for working areas near Ma Wat Channel and Ping Yuen
River.
ES18
In addition, all effluent
discharge shall be ensure to fulfill Technical Memorandum of Effluent
Discharged into Drainage and Sewerage Systems, inland and Coastal Waters
criteria or discharge permits stipulation.
ES19
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.