|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report (No.43)
¡V February 2017 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
14 March 2017 |
TCS00694/13/600/R0887v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
8 March 2017 |
First
Submission |
2 |
14 March 2017 |
Amended against the IEC¡Šs comments on 11 March
2017 |
|
|
|
executive summary
ES01
This is the 43rd monthly EM&A
report presenting the monitoring results and inspection findings for the reporting
period from 1 to 28 February 2017 (hereinafter ¡¥the Reporting Period¡Š).
Environmental Monitoring
and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08),
Contract 3 (CV/2012/09), Contract 4 (TCSS),
Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and
an ArshSD contract (Contract SS C505).
ES03
In the Reporting Period, the major construction
works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project included Contract 2, Contract 3, Contract 6, Contract 7 and Contract SS
C505. Environmental monitoring
activities under the EM&A programme in the
Reporting Period are summarized in the following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
135 |
24-hour TSP |
9 |
45 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
40 |
Water Quality |
Water in-situ
measurement and/or sampling |
WM1 & WM1-C |
12 Scheduled & 1 extra |
WM2A(a) & WM2A-Cx |
12 Scheduled & 2 extra |
||
WM2B & WM2B-C |
12 Scheduled & 0 extra |
||
WM3x &WM3-C |
12 Scheduled & 1 extra |
||
WM4, WM4-CA &WM4-CB |
12 Scheduled & 0 extra |
||
Ecology |
Woodland compensation i) General Health condition of planted species ii) Survival of planted species |
9 Quadrats |
1 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and
Auditing |
Contract 2 |
4 |
Contract 3 |
5 |
||
Contract 6 |
4 |
||
Contract 7 |
5 |
||
Contract SS C505 |
4 |
Note: Extra monitoring day was due to measurement
results exceedance
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no air quality and construction noise exceedances
were recorded. For water quality monitoring, a total of thirteen (13) Limit
Level exceedances were recorded. The
summary of exceedance in the Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
|||
NOE Issued |
Investigation Result |
Project related exceedance |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
0 |
4 |
4 |
- Exceedances
recorded at WM1 are under investigation. - All other NOEs were concluded as non-project
related |
0 |
The Contractors were reminded to implement water quality mitigation
measures in accordance with ISEMM of the EM&A Manual requirements |
|
SS |
0 |
9 |
9 |
0 |
Environmental
Complaint
ES05
In
this Reporting Period, one (1) documented environmental complaint regarding noise
issue for Contract 6 in January 2017 was received. Investigation report for the complaint
is in progress.
ES06
The summary of complaint received in the Reporting Period is summarized below.
Reporting Period |
Contract No |
Environmental Complaint |
||
Frequency |
Complaint Nature |
Project related complaint |
||
1 ¡V 28 Feb 2017 |
Contract 2 |
0 |
NA |
NA |
Contract 3 |
0 |
NA |
NA |
|
Contract 6 |
1 |
Noise (1) |
# |
|
Contract 7 |
0 |
NA |
NA |
|
SS C505 |
0 |
NA |
NA |
# The complaint is
under investigation.
Notification of
Summons and Successful Prosecutions
ES07
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
ES08
In the Reporting period, no reporting changes
were made.
ES09
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 3, 10, 17 and 24
February 2017. No non-compliance was noted during the
site inspection.
ES10
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 2, 6, 15, 20 and
27 February 2017. No non-compliance was noted during the site
inspection.
ES11
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 2, 9, 16 and 23 February 2017. No non-compliance was noted during the site
inspection.
ES12
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 15 and 22 February 2017. No non-compliance was noted during the site
inspection.
ES13
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
7 has been carried out by the RE, IEC, ET and the Contractor on 1, 7, 14, 21 and
28 February 2017. No non-compliance
was noted during the site inspection.
Future Key Issues
ES14
During dry season,
special attention should be paid on the potential construction dust impact
since most of the construction sites
are adjacent to villages. The Contractor should fully implement the
construction dust mitigation measures.
ES15
Preventive measures for muddy water or other water
pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping
Yuen River, Kwan Tei River or public area should
be properly maintained. The Contractors should paid special attention on
water quality mitigation measures and fully implement according ISEMM of the
EM&A Manual, in particular for working areas near Ma Wat Channel and Ping
Yuen River. Moreover, all effluent discharge shall
be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage
and Sewerage Systems, inland and Coastal Waters criteria or discharge permits
stipulation.
ES16
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.