Job No.: TCS00670/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report (No.5)
¡V December 2013 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
15
January 2014 |
TCS00670/13/600/R00111v1 |
|
|
Ben Tam (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
8 January 2014 |
First
Submission |
2 |
15 January 2014 |
Revised against RE requirement on 12 January 2014 |
|
|
|
executive summary
ES01
This is the 5th monthly EM&A report presenting the monitoring
results and inspection findings for the reporting period from 1 to 31 December 2013
(hereinafter ¡¥the Reporting Period¡¦).
Environmental Monitoring
and Audit Activities
ES02
Environmental monitoring activities under the
EM&A programme in the Reporting Period are
summarized in the following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
4 |
60 |
24-hour TSP |
4 |
(*)23 |
|
Construction Noise |
Leq(30min) Daytime |
5 |
25 |
Water Quality |
Water sampling |
5 |
12 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing |
Contract 3 |
5 |
Contract 5 |
4 |
Remarks: (*) Power failure was occurred
at AM2 on 20 December 2013.
Breach of Action and Limit (A/L) Levels
ES03
No exceedances of air quality, construction
noise were registered in the Reporting Period. For water quality monitoring, a total of
two (2) Limit Level exceedances were recorded on 17 December 2013. The summary of breach of environmental
performance is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
||
NOE Issued |
Investigation |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
24-hour TSP |
0 |
0 |
0 |
0 |
0 |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
0 |
0 |
Water Quality |
DO |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
1 |
1 |
1 |
0 |
|
SS |
0 |
1 |
1 |
1 |
0 |
Environmental
Complaint
ES04
No environmental
complaints were received in the
Reporting Period.
Notification of Summons and Successful Prosecutions
ES05
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
ES06
No reporting changes were made in the Reporting
Period.
ES07
In the Reporting Period, joint site
inspection for Contract 3 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 4, 11, 18, 23 and 30
December 2013. No
non-compliance was noted.
ES08
In the Reporting Period, joint site
inspection for Contract 5 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 5, 11, 19 and 24 December
2013. No non-compliance was
noted.
Future Key Issues
ES09
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
ES10
During dry season, special
attention should be paid on the potential construction dust impact since most
of the construction sites are adjacent to villages. The Contractor should fully implement
the construction dust mitigation measures properly.
ES11
In addition, the potential water quality impact at the nearby rivers should be highly
alerted. The Contractors including
Contract 3 and Contract 5 should prevent muddy water and other water pollutants
via site surface water runoff get into the Kong
Yiu Channel and Ma Wat Channel, water quality mitigation measures should be properly implemented.
Table of Contents
2 Project
Organization and Construction progress
2.1 Construction
Contract Packaging
2.5 Summary of Environmental Submissions
3 Summary
of Impact Monitoring Requirements
3.4 Monitoring
Frequency and Period
3.8 Derivation
of Action/Limit (A/L) Levels
3.9 Data
Management and Data QA/QC Control
4.2 Air
Quality Monitoring Results in Reporting Month
5 Construction
Noise Monitoring
5.2 Noise
Monitoring Results in Reporting Month
6.2 Results
of Water Quality Monitoring
7.2 Records
of Waste Quantities
8.2 Findings
/ Deficiencies During the Reporting Month
9 Environmental
Complaint and Non-Compliance
9.1 Environmental
Complaint, Summons and Prosecution
10 Implementation
Status of Mitigation Measures
10.2 Tentative
Construction Activities in the Coming Month
10.3 Key
Issues for the Coming Month
11 Conclusions
and Recommendations
List
of TABLES
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Impact
Monitoring Stations - Air Quality
Table 3-3 Impact
Monitoring Stations - Construction Noise
Table 3-4 Impact
Monitoring Stations - Water Quality
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Construction
Noise Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action
and Limit Levels for Water Quality
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Table 5-1 Summary
of Construction Noise Monitoring Results
Table 6-1 Summary
of Water Quality Monitoring Results for Contract 3
Table 6-2 Summary
of Water Quality Monitoring Results for Contract 5
Table 6-3 Breaches
of Water Quality Monitoring Criteria in Reporting Period
Table 7-1 Summary
of Quantities of Inert C&D Materials
Table 7-2 Summary
of Quantities of C&D Wastes
Table 8-1 Site
Observations for Contract 3
Table 8-2 Site
Observations for Contract 5
Table 9-1 Statistical
Summary of Environmental Complaints
Table 9-2 Statistical
Summary of Environmental Summons
Table 9-3 Statistical
Summary of Environmental Prosecution
Table 10-1 Environmental
Mitigation Measures
List of Appendices
Appendix A Layout
Plan of the Project
Appendix B Organization
Chart
Appendix C Master
Construction Programme
Appendix D Designated
Monitoring Locations as Recommended in the Approved EM&A Manual
Appendix E Monitoring
Locations for Impact Monitoring
Appendix F Calibration
Certificate of Monitoring Equipment and HOKLAS-accreditation Certificate of the
Testing Laboratory
Appendix G Event
and Action Plan
Appendix H Impact
Monitoring Schedule
Appendix I Database
of Monitoring Result
Appendix J Graphical
Plots for Monitoring Result
Appendix K Meteorological
Data
Appendix L Waste
Flow Table
Appendix M Implementation
Schedule for Environmental Mitigation Measures
1.1.1
Civil Engineering and Development Department is the Project Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE) Liantang / Heung Yuen Wai Boundary Control Point and
Associated Works, which is a Designated Project to be implemented under
Environmental Permit number EP-404/2011/A issued on 28 October 2013.
1.1.2
The Project consists of two main components: Construction of a Boundary
Control Point (hereinafter referred as ¡§BCP¡¨); and Construction of a connecting
road alignment. Layout plan of the Project is shown in Appendix A.
1.1.3
The proposed BCP is located at the boundary with Shenzhen near the
existing Chuk Yuen Village, comprising a main
passenger building with passenger and cargo processing facilities and the
associated customs, transport and ancillary facilities. The connecting road alignment consists
of six main sections:
1)
Lin Ma Hang to Frontier Closed Area (FCA) Boundary ¡V this section
comprises at-grade and viaducts and includes the improvement works at Lin Ma
Hang Road;
2)
Ping Yeung to Wo Keng
Shan ¡V this section stretches from the Frontier Closed Area Boundary to the
tunnel portal at Cheung Shan and comprises at-grade and viaducts including an
interchange at Ping Yeung;
3)
North Tunnel ¡V this section comprises the tunnel segment at Cheung Shan
and includes a ventilation building at the portals on either end of the tunnel;
4)
Sha Tau Kok Road ¡V this section stretches from the
tunnel portal at Wo Keng
Shan to the tunnel portal south of Loi Tung and
comprises at-grade and viaducts including an interchange at Sha
Tau Kok and an administration building;
5)
South Tunnel ¡V this section comprises a tunnel segment that stretches from
Loi Tung to Fanling and
includes a ventilation building at the portals on either end of the tunnel as
well as a ventilation building in the middle of the tunnel near Lau Shui Heung;
6)
Fanling ¡V this section comprises the at-grade, viaducts
and interchange connection to the existing Fanling
Highway.
1.1.4
Action-United Environmental Services & Consulting has been commissioned as an Independent ET to implement the
relevant EM&A program in accordance
with the approved EM&A Manual, as well as the associated duties. As part of the EM&A program, the
baseline monitoring has carried out between 13 June 2013 and 12 July 2013
for all parameters including air quality, noise and water quality before
construction work commencement. The Baseline
Monitoring Report summarized the key findings and the rationale behind
determining a set of Action and Limit Levels (A/L Levels) from the baseline
data. Also, the Project baseline
monitoring report which verified by the IEC has been submitted to EPD on 16 July 2013 for endorsement. The major construction works of the
Project was commenced on 16 August 2013
in accordance with the EP Section 5.3 stipulation.
1.1.5
This is 5th
monthly EM&A report presenting the monitoring results and inspection
findings for reporting period from 1 to 31 December 2013.
1.2.1
The Monthly Environmental Monitoring and
Audit (EM&A) Report is structured into the following sections:-
Section 1 Introduction
Section 2 Project
Organization and Construction Progress
Section 3 Summary
of Impact Monitoring Requirements
Section 4 Air
Quality Monitoring
Section 5 Construction
Noise Monitoring
Section 6 Water
Quality Monitoring
Section 7 Waste
Management
Section 8 Site
Inspections
Section 9 Environmental
Complaints and Non-Compliance
Section 10 Implementation
Status of Mitigation Measures
Section 11 Conclusions
and Recommendations
2.1.1
To facilitate the project management and
implementation, the Project would be divided by the following contracts:
¡P
Contract 2 (CV/2012/08)
¡P
Contract 3 (CV/2012/09)
¡P
Contract 4 (TCSS)
¡P
Contract 5 (CV/2013/03)
¡P
Contract 6 (CV/2013/08)
2.1.2
The
details of each contracts is summarized below and the delineation of each contracts is shown in Appendix
A.
Contract 2 (CV/2012/08)
2.1.3
Contract 2 has awarded in December 2013. Construction work is predicted to be commenced
in early 2014. Major Scope of Work
of the Contract 2 is listed below:
¡P
construction of
an approximately 5.2km long dual two-lane connecting road (with about 0.4km of
at-grade road and 4.8km of tunnel) connecting the Fanling
Interchange with the proposed Sha Tau Kok Interchange;
¡P
construction of a
ventilation adit tunnel and the mid-ventilation
building;
¡P
construction of
the north and south portal buildings of the Lung Shan Tunnel and their
associated slope works;
¡P
provision and
installation of ventilation system, E&M works and building services works
for Lung Shan tunnel and Cheung Shan tunnel and their portal buildings;
¡P
construction of
Tunnel Administration Building adjacent to Wo Keng Shan Road and the associated E&M and building
services works; and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 3 (CV/2012/09)
2.1.4
Contract 3 was awarded in July 2013 and
construction work was commenced on 5 November 2013. Major Scope of Work of the Contract 3 is
listed below:
¡P
construction of
four link roads connecting the existing Fanling
Highway and the south portal of the Lung Shan Tunnel;
¡P
realignment of
the existing Tai Wo Service Road West and Tai Wo Service Road East;
¡P
widening of the
existing Fanling Highway (HyD¡¦s
entrustment works);
¡P
demolishing
existing Kiu Tau vehicular bridge and Kiu Tau footbridge and reconstruction of the existing Kiu Tau Footbridge (HyD¡¦s
entrustment works); and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 4 (Contract number to be
assigned)
2.1.5
Contract 4 has not yet awarded. The work of the Contract 4 includes provision and installation of
Traffic Control and Surveillance System and the associated electrical and
mechanical works for the Project.
Contract 5 (CV/2013/03)
2.1.6
Contract 5 has awarded in April 2013 and construction
work was commenced in August 2013.
Major Scope of Work of the Contract 5 is listed below:
¡P
site formation of about 23
hectares of land for the development of the BCP;
¡P
construction of an
approximately 1.6 km long perimeter road at the BCP including a 175m long
depressed road;
¡P
associated
diversion/modification works at existing local roads and junctions including
Lin Ma Hang Road;
¡P
construction of pedestrian
subway linking the BCP to Lin Ma Hang Road;
¡P
provision of resite area with supporting infrastructure for reprovisioning of the affected village houses; and
¡P
construction of associated footpath, slopes, retaining structures, drainage,
sewerage, waterworks, landscaping works and other ancillary works.
Contract 6 (CV/2013/08)
2.1.7
Contract 6 has not yet awarded. Major Scope of Work of the Contract 6
will be included below:
construction of an approximately 4.6km long dual two-lane connecting
road (with about 0.6km of at-grade road, 3.3km of viaduct and 0.7km of tunnel)
connecting the BCP with the proposed Sha Tau Kok Road Interchange and the associated ventilation
buildings;
associated diversion/modification works at access roads to the resite of Chuk Yuen Village;
provision of sewage collection, treatment and disposal facilities for
the BCP and the resite of Chuk
Yuen Village;
construction of a pedestrian subway linking the BCP to Lin Ma Hang
Road;
provisioning of the affected facilities including Wo
Keng Shan Road garden; and
construction of associated footpath, slopes, retaining
structures, drainage, sewerage, waterworks, landscaping works and other
ancillary works.
2.2.1
The project organization is shown in Appendix
B. The responsibilities of
respective parties are:
Civil
Engineering and Development Department (CEDD)
2.2.2
CEDD is the Project Proponent and the Permit Holder of the EP of the development
of the Project and will assume overall responsibility for the project. An
Independent Environmental Checker (IEC) shall be employed by CEDD to audit the
results of the EM&A works carried out by the ET.
Environmental
Protection Department (EPD)
2.2.3
EPD is the statutory enforcement body for
environmental protection matters in Hong Kong.
Engineer
or Engineers Representative (ER)
2.2.4
The ER is responsible for overseeing the
construction works and for ensuring that the works are undertaken by the
Contractor in accordance with the specification and contract requirements. The
duties and responsibilities of the ER with respect to EM&A are:
¡P
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the
environmental mitigation measures and their effectiveness
¡P
Monitor Contractors¡¦s,
ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental Permit
(EP) and EM&A Manual
¡P
Facilitate ET¡¦s implementation of the
EM&A programme
¡P
Participate in joint site inspection by the
ET and IEC
¡P
Oversee the implementation of the agreed
Event / Action Plan in the event of any exceedance
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with DSD, Engineer/Engineer¡¦s
Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s Regulaiton of Shenzhen River Stage 4 (RSR 4)¡¨ Project
discussing regarding the cumulative impact issues.
The
Contractor(s)
2.2.5
There will be one contractor for each
individual works contract. The
Contractor(s) should report to the ER. The duties and responsibilities of the
Contractor are:
¡P
Comply with the relevant contract conditions
and specifications on environmental protection
¡P
Employ an Environmental Team (ET) to
undertake monitoring, laboratory analysis and reporting of EM &A Facilitate
ET¡¦s monitoring and site inspection activities
¡P
Participate in the site inspections by the ET
and IEC, and undertake any corrective actions
¡P
Provide information / advice to the ET
regarding works programme and activities which may
contribute to the generation of adverse environmental impacts
¡P
Submit proposals on mitigation measures in
case of exceedances of Action and Limit levels in accordance with the Event /
Action Plans
¡P
Implement measures to reduce impact where
Action and Limit levels are exceeded
¡P
Adhere to the procedures for carrying out
complaint investigation
Environmental Team (ET)
2.2.6
One ET will be employed for this Project. The ET shall not be in any way an
associated body of the Contractor(s), and shall be employed by the Project
Proponent/Contractor to conduct the EM&A programme.
The ET should be managed by the ET
Leader. The ET Leader shall be a person who has at least 7 years¡¦ experience in
EM&A and has relevant professional qualifications. Suitably qualified staff
should be included in the ET, and resources for the implementation of the
EM&A programme should be allocated in time under
the Contract(s), to enable fulfillment of the Project¡¦s EM&A requirements
as specified in the EM&A Manual during construction of the Project. The ET shall report to the Project
Proponent and the duties shall include:
¡P
Monitor and audit various environmental
parameters as required in this EM&A Manual
¡P
Analyse the
environmental monitoring and audit data, review the success of EM&A programme and the adequacy of mitigation measures
implemented, confirm the validity of the EIA predictions and identify any adverse
environmental impacts arising
¡P
Carry out regular site inspection to
investigate and audit the Contractors¡¦ site practice, equipment/plant and work
methodologies with respect to pollution control and environmental mitigation,
and effect proactive action to pre-empt problems
¡P
Monitor compliance with conditions in the EP,
environmental protection, pollution prevention and control regulations and
contract specifications
¡P
Audit environmental conditions on site
¡P
Report on the environmental monitoring and audit
results to EPD, the ER, the lEC and Contractor(s) or their delegated representatives
¡P
Recommend suitable mitigation measures to the
Contractor in the case of exceedance of Action and Limit levels in accordance
with the Event and Action Plans
¡P
Liaise with the IEC on all environmental
performance matters and timely submit all relevant EM&A proforma
for approval by IEC
¡P
Advise the Contractor(s) on environmental
improvement, awareness, enhancement measures etc., on site
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, ET, lEC and the
Contractor(s) of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
Independent Environmental Checker (IEC)
2.2.7
One IEC will be employed for this Project. The Independent Environmental Checker
(IEC) should not be in any way an associated body of the Contractor(s) or the
ET for the Project. The IEC should
be employed by the Permit Holder (i.e., CEDD) prior to
the commencement of the construction of the Project. The IEC should have at least 10 years¡¦
experience in EM&A and have relevant professional qualifications. The duty of IEC should be:
¡P
Provide proactive advice to the ER and the
Project Proponent on EM&A matters related to the project, independent from
the management of construction works, but empowered to audit the environmental
performance of construction
¡P
Review and audit all aspects of the EM&A programme implemented by the ET
¡P
Review and verify the monitoring data and all
submissions in connection with the EP and EM&A Manual submitted by the ET
¡P
Arrange and conduct regular, at least monthly
site inspections of the works during construction phase, and ad hoc inspections
if significant environmental problems are identified
¡P
Check compliance with the agreed Event /
Action Plan in the event of any exceedance
¡P
Check compliance with the procedures for
carrying out complaint investigation
¡P
Check the effectiveness of corrective
measures
¡P
Feedback audit results to ET by signing off
relevant EM&A proforma
¡P
Check that the mitigation measures are
effectively implemented
¡P
Report the works conducted, the findings,
recommendation and improvement of the site inspections, after reviewing ET¡¦s
and Contractor¡¦s works, and advices to the ER and Project Proponent on a
monthly basis
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, ET, lEC and the
Contractor(s) of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
2.3.1
The concurrent construction works that may be
carried out include, but not limited to, the following:
(a)
Regulation of Shenzhen River Stage IV
(Environmental Permit EP-430/2011);
(b)
Building works and road works by contractors
of Architectural Services Department (ArchSD)
(Environmental Permit EP-404/2011/A);
(c)
Widening of Fanling
Highway ¡V Tai Hang to Wo Hop
Shek Interchange ¡V Contract No. HY/2012/06;
(d)
Construction of cross-boundary vehicular and
pedestrian bridges (total 5 numbers) across the Shenzhen River; and
(e)
Construction of BCP
facilities in Shenzhen.
2.4.1
In the Reporting Period, the major
construction activity conducted under the Project is located in Contracts 3 and
5 and they are summarized in below.
Moreover, the master construction program of both Contracts 3 and 5 is
enclosed in Appendix C.
Contract 2 (CV/2012/08)
The
contract has not yet commenced.
Contract 3 (CV/2012/09)
The Contract
commenced in November 2013. In this
Reporting Period, construction activities conducted is listed below:
Cable detection and
trail trenches
Tree Felling Works
Trial Pit Excavation
Pre-drilling works and
piling works
Extension of box culvert
Bored pile wall construction
Erection of site office
Construction of haul road and temporary soil
platform for geotechnical works
Contract 4 (Contract number to be assigned)
The
contract has not yet awarded.
Contract 5 (CV/2013/03)
The Contract
commenced in April 2013. In this
Reporting Period, construction activities conducted is listed below:
Construction of
Retaining Wall No.1
Eastern Lift shaft¡¦s piling works
Piling works at life shaft, Bridge J &
footbridge
Construction of pedestrian subway and pump room
at LMH
Pipe jacking across Kong Yuen River
Transplantation, Pruning/felling of existing
tree
Drainage works at LMH Road
Formation Works at BCP Area
Construction of Depressed Road at BCP3
Contract 6 (CV/2013/08)
The
contract is still yet awarded
2.5.1
In according to the EP, the required documents
have submitted to EPD for retention which listed in below:
Project Layout Plans of Contracts 3 and 5
Landscape Plan
Topsoil Management Plan
Environmental Monitoring and Audit Programme
Baseline Monitoring Report (TCS00690/13/600/R0030v3) for the Project
Waste Management Plan of the Contracts 3 and
5
2.5.2
Summary of
the relevant permits, licenses, and/or notifications on environmental
protection for the Project of each contracts are presented in Table 2-1.
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Description |
License/Permit
Status |
|||
Contract 3 |
Contract 5 |
Contract 2, 4 & 6 |
||
1 |
Air
pollution Control (Construction Dust) Regulation |
Ref. No: 362101 Notification received by EPD on 17
Jul 2013 |
Ref. No: 359338 Notified EPD on 13 May 2013 |
-- |
2 |
Chemical Waste Producer Registration - Waste Producers
Number |
No.:5113-634-C3817-01
Valid form 7 Oct 2013 till the end of Contract |
No.:
5213-642-S3735-01 Valid form 8 Jun
2013 till the end of Contract |
-- |
3 |
Water Pollution Control Ordinance - Discharge
License |
No.:WT00016832 ¡V
2013 Valid from 28
Aug 13 to 31 Aug 2018 |
No.: W5/1G44/1 Valid from 8 Jun
13 to 30 Jun 2018 |
-- |
4 |
Waste Disposal Regulation - Billing Account
for Disposal of Construction Waste |
Account No. 7017914 Valid form 2 Aug
13 till the end of Contract |
Account No. 7017351 Valid form 29
Apr 13 till the end of Contract |
-- |
5 |
Construction Noise Permit |
GW-RN0747-13 Valid on 4 Dec 13 till 19 Jan 14 |
NA |
-- |
3.1.1
The Environmental Monitoring and Audit
requirements are set out in the Approved EM&A manual. Environmental issues
such as air quality, construction noise and water quality were identified as
the key issues during the construction phase of the Project.
3.1.2
A summary of construction phase EM&A
requirements are presented in the
sub-sections below.
3.2.1
The EM&A program of construction phase
monitoring shall cover the following environmental issues:
•
Air quality;
•
Construction noise; and
•
Water quality
3.2.2
A summary of the monitoring parameters is
presented in Table 3-1.
Table 3-1 Summary
of EM&A Requirements
Environmental Issue |
Parameters |
Air Quality |
1-hour
TSP by Real-Time Portable Dust Meter; and 24-hour
TSP by High Volume Air Sampler. |
Noise |
Leq(30min) in
normal working days (Monday to Saturday) 07:00-19:00 except public holiday;
and 3 sets
of consecutive Leq(5min) on restricted
hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday Supplementary
information for data auditing, statistical results such as L10 and
L90 shall also be obtained for reference. |
Water Quality |
In-situ Measurements Dissolved
Oxygen Concentration (mg/L); Dissolved
Oxygen Saturation (% ); Turbidity
(NTU); pH unit; Water
depth (m); and Temperature
(¢J). |
Laboratory Analysis
Suspended
Solids (mg/L) |
3.3.1
The designated monitoring locations as
recommended in the EM&A Manual are
shown in Appendix D. As the access to some of the designated
monitoring locations was questionable due to safety reason or denied by the
landlords, alternative locations therefore have had proposed. The proposed
alternative monitoring locations has updated in the revised EM&A Programme which verified by IEC and certified by ET Leader
prior submitted to EPD on 10 July 2013. Table 3-2, Table 3-3 and Table
3-4 are respectively listed the air quality, construction noise and
water quality monitoring locations for the Project and a map showing these
monitoring stations is presented in Appendix
E.
Table 3-2 Impact
Monitoring Stations - Air Quality
Station ID |
Description |
Works Area |
Related to the Work Contract |
AM1 |
Tsung Yuen Ha Village House No. 63 |
BCP |
Contract 5 |
AM2 |
Village House near
Lin Ma Hang Road |
LMH to Frontier
Closed Area |
Contract 5, Contract 6 |
AM3 |
Ta Kwu Ling Fire Service Station of Ta Kwu
Ling Village. |
LMH to Frontier
Closed Area |
Contract 5, Contract 6 |
AM4a |
A village house located at about
160m east side of the original point AM4 |
LMH to Frontier
Closed Area |
Contract 6 |
AM5 |
Ping Yeung
Village House |
Ping Yeung to Wo Keng Shan |
Contract 6 |
AM6 |
Wo Keng Shan Village House |
Ping Yeung to Wo Keng Shan |
Contract 6 |
AM7a |
Another village (nameless) aligns
to Sha Tau Kok Road ¡V Wo Hang Section proximity to Tai Tong Wu
Village. The location is about 140m
away from the original point AM7 |
Sha Tau Kok Road |
Contract 2 |
AM8 |
Po Kat Tsai
Village No. 4 |
Po Kat Tsai |
Contract 2 |
AM9b# |
Nam Wa Po Village House No. 80 |
Fanling |
Contract 3 |
# Proposal for the change of air quality monitoring location from AM9a
to AM9b was submitted to EPD on 4 Nov 2013 after verified by the IEC and it was
approved by EPD (EPD¡¦s ref.: (15) in EP 2/N7/A/52 Pt.10 dated 8 Nov 2013).
Table 3-3 Impact
Monitoring Stations - Construction Noise
Station ID |
Description |
Works Area |
Related to the Work Contract |
NM1 |
Tsung Yuen Ha Village House No. 63 |
BCP |
Contract 5 |
NM2 |
Village House near Lin Ma Hang
Road |
Lin Ma Hang to Frontier Closed
Area |
Contract 5, Contract 6 |
NM3 |
Ping Yeung Village House (facade
facing northeast) |
Ping Yeung to Wo
Keng Shan |
Contract 6 |
NM4 |
Wo Keng Shan Village House |
Ping Yeung to Wo
Keng Shan |
Contract 6 |
NM5 |
Village House, Loi
Tung |
Sha Tau Kok Road |
Contract 2, Contract 6 |
NM6 |
Tai Tong Wu Village House 2 |
Sha Tau Kok Rpad |
Contract 2, Contract 6 |
NM7 |
Po Kat Tsai Village |
Po Kat Tsai |
Contract 2 |
NM8 |
Village House, Tong Hang |
Fanling |
Contract 2 Contract 3 |
NM9 |
Village House, Kiu
Tau Village |
Fanling |
Contract 3 |
NM10 |
Nam Wa
Po Village House No. 80 |
Fanling |
Contract 3 |
Table 3-4 Impact
Monitoring Stations - Water Quality
Station ID |
Description |
Designated / Alternative Location |
Nature of the
location |
Related to the Work Contract |
|
Coordinates |
|||||
Easting |
Northing |
||||
WM1 |
Downstream of Kong Yiu Channel |
833679 |
845421 |
Alternative location located at upstream 51m of the designated location |
Contract 5 |
WM1-Control |
Upstream of Kong Yiu Channel |
834185 |
845917 |
NA |
Contract 5 |
WM2A |
Downstream of River Ganges |
834204 |
844471 |
Alternative location located at downstream 81m of the designated
location |
Contract 6 |
WM2A-Control |
Upstream of River Ganges |
835270 |
844243 |
Alternative location located at upstream 78m of the designated location |
Contract 6 |
WM2B |
Downstream of River Ganges |
835433 |
843397 |
NA |
Contract 6 |
WM2B-Control |
Upstream of River Ganges |
835835 |
843351 |
Alternative location located at downstream 31m of the designated
location |
Contract 6 |
WM3 |
Downstream of River Indus |
836324 |
842407 |
NA |
Contract 6 |
WM3-Control |
Upstream of River Indus |
836763 |
842400 |
Alternative location located at downstream 26m of the designated
location |
Contract 6 |
WM4 |
Downstream of Ma Wat Channel |
833850 |
838338 |
Alternative location located at upstream 11m of the designated location |
Contract 3 |
WM4¡VControl A |
Kau Lung Hang
Stream |
834028 |
837695 |
Alternative location located at downstream 28m of the designated
location |
Contract 3 |
WM4¡VControl B |
Upstream of Ma Wat Channel |
833760 |
837395 |
Alternative location located at upstream 15m of the designated location |
Contract 3 |
The requirements of impact monitoring are stipulated in Sections 2.1.6, 3.1.5 and 4.1.6 of the approved EM&A Manual and presented as
follows.
Air Quality Monitoring
3.4.1
Frequency of impact air
quality monitoring is as follows:
1-hour TSP |
3 times every six days during course of works |
24-hour TSP |
Once every 6 days during course of works. |
Noise Monitoring
3.4.2
One set of Leq(30min)
as 6 consecutive Leq(5min)
between 0700-1900 hours on normal weekdays and once every week during course of works. If construction work necessary to carry
out at other time periods, i.e. restricted time period (19:00 to 07:00 the next
morning and whole day on public holidays) (hereinafter referred as ¡§the
restricted hours¡¨), 3 consecutive Leq(5min) measurement will
depended CNP requirements to undertake.
Supplementary information for data
auditing, statistical results such as L10 and L90 shall
also be obtained for reference.
Water Quality Monitoring
3.4.3
The water quality monitoring frequency shall
be 3 days per week during course of works.
The interval between two sets of monitoring shall not be less than 36
hours.
Air Quality Monitoring
3.5.1
The 24-hour and 1-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B. If the ET proposes to use a direct
reading dust meter to measure 1-hour TSP levels, it shall submit sufficient
information to the IEC to approve.
3.5.2
The filter paper of 24-hour TSP measurement shall be determined by HOKLAS
accredited laboratory.
3.5.3
All equipment to be used for air quality
monitoring is listed in Table 3-5.
Table 3-5 Air
Quality Monitoring Equipment
Equipment |
Model |
24-Hr TSP |
|
High
Volume Air Sampler |
TISCH High Volume
Air Sampler, HVS Model TE-5170 |
Calibration
Kit |
TISCH Model TE-5025A |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3B
Laser Dust monitor Particle Mass Profiler & Counter |
Wind Data Monitoring Equipment
3.5.4
According to the approved EM&A Manual, wind
data monitoring equipment shall also be provided and set up for logging wind
speed and wind direction near the dust monitoring locations. The equipment installation location shall
be proposed by the ET and agreed with the IEC. For installation and operation of wind
data monitoring equipment, the following points shall be observed:
1)
The wind sensors should be installed 10 m
above ground so that they are clear of obstructions or turbulence caused by
buildings.
2)
The wind data should be captured by a data
logger. The data shall be downloaded for analysis at least once a month.
3)
The wind data monitoring equipment should be
re-calibrated at least once every six months.
4)
Wind direction should be divided into 16
sectors of 22.5 degrees each.
3.5.5
ET has liaised with the landlords of the successful
granted HVS installation premises.
However, the owners rejected to provide premises for wind data
monitoring equipment installation.
3.5.6
Under this situation, the ET proposed alternative
methods to obtain representative wind data. Meteorological information as extracted
from ¡§the Hong Kong Observatory Ta Kwu Ling Station¡¨
is alternative method to obtain representative wind data. For Ta Kwu
Ling Station, it is located nearby the Project site. Moreover, this station is located at 15m
above mean sea level while its anemometer is located at 13m above the existing
ground which in compliance with the general setting up requirement. Furthermore, this station also can be to
provide the humidity, rainfall, and air pressure and temperature etc.
meteorological information. In Hong
Kong of a lot development projects, weather information extracted from Hong
Kong Observatory is common alternative method if weather station installation
not allowed.
Noise Monitoring
3.5.7
Sound level meter in compliance with the
International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. The sound level meter shall be checked
using an acoustic calibrator. The
wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m s-1.
3.5.8
Noise monitoring equipment to be used for monitoring
is listed in Table 3-6.
Table 3-6 Construction
Noise Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
B&K Type 2238 or Rion
NL-14 or Rion NL-31 |
Calibrator |
B&K Type 4231 |
Portable Wind Speed Indicator |
Testo Anemometer |
3.5.9
Sound level meters listed above comply with
the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications, as recommended in TM issued
under the NCO. The acoustic
calibrator and sound level meter to be used in the impact monitoring will be
calibrated yearly.
Water Quality Monitoring
3.5.10
DO and water
temperature should be measured in-situ by a DO/temperature meter. The
instrument should be portable and weatherproof using a DC power source. It
should have a membrane electrode with automatic temperature compensation
complete with a cable. The equipment should be capable of measuring:
•
a DO level in the range of 0-20 mg/l and
0-200% saturation; and
•
a
temperature of between 0 and 45 degree Celsius.
3.5.11
A portable pH meter
capable of measuring a range between 0.0 and 14.0 should be provided to measure
pH under the specified conditions accordingly to the APHA Standard Methods.
3.5.12
The instrument should
be portable and weatherproof using a DC power source. It should have a
photoelectric sensor capable of measuring turbidity between 0-1000 NTU.
3.5.13
A portable, battery-operated echo sounder or
tape measure will be used for the determination of water depth at each
designated monitoring station as appropriate.
3.5.14
A water sampler e.g. Kahlsico
Water Sampler, which is a transparent PVC cylinder with capacity not less than
2 litres, will be used for water sampling if water
depth over than 0.5m. For sampling from very shallow water
depths e.g. <0.5 m, water sample collection will be directly from water
surface below 100mm use sampling plastic bottle to avoid inclusion of bottom
sediment or humus. Moreover, Teflon/stainless
steel bailer or self-made sampling buckets maybe used for water sampling. The equipment used for sampling will be
depended the sampling location and depth situations.
3.5.15
Water samples for laboratory measurement of
SS will be collected in high density polythene bottles, packed in ice (cooled
to 4 ºC without being frozen), and delivered to the laboratory in the same day
as the samples were collected.
3.5.16
Analysis of suspended solids should be
carried out in a HOKLAS or other accredited laboratory. Water samples of about
1L should be collected at the monitoring stations for carrying out the
laboratory suspended solids determination. The SS determination work should start
within 24 hours after collection of the water samples. The SS analyses should
follow the APHA Standard Methods 2540D
with Limit of Reporting of 2 mg/L.
3.5.17
Water quality monitoring equipment used in
the impact monitoring is listed in Table 3-7. Suspended solids (SS)
analysis is carried out by a local HOKLAS-accredited laboratory, namely ALS Technichem
(HK) Pty Ltd.
Table 3-7 Water
Quality Monitoring Equipment
Equipment |
Model |
Water
Depth Detector |
Eagle Sonar or tape measures |
Water Sampler |
A 2-litre transparent PVC cylinder with latex cups at
both ends or teflon/stainless steel bailer or
self-made sampling bucket |
Thermometer & DO meter |
YSI PRO20 Handheld Dissolved
Oxygen Instrument |
pH meter |
The EcoSense ® pH10A pen-style instrument |
Turbidimeter |
Hach 2100Q |
Sample Container |
High density polythene bottles (provided by laboratory) |
Storage
Container |
¡¥Willow¡¦
33-liter plastic cool box with Ice pad |
1-hour TSP
Monitoring
3.6.1
The 1-hour TSP monitor was a brand named ¡§Sibata LD-3B Laser Dust monitor Particle Mass Profiler
& Counter¡¨ which is a portable, battery-operated laser photometer. The 1-hour TSP meter provides a real
time 1-hour TSP measurement based on 90o light scattering. The 1-hour TSP monitor consists of the
following:
(a.)
A pump to draw sample aerosol through the
optic chamber where TSP is measured;
(b.)
A sheath air system to isolate the aerosol in
the chamber to keep the optics clean for maximum reliability; and
(c.)
A built-in data logger compatible with
Windows based program to facilitate data collection, analysis and reporting.
3.6.2
The 1-hour TSP meter is used within the valid
period as follow manufacturer¡¦s Operation and Service Manual.
3.6.3
The equipment used for 24-hour TSP
measurement is Thermo Andersen Model GS2310 TSP high volume air sampling
system, which complied with EPA Code of
Federal Regulation, Appendix B to Part 50. The High Volume Air Sampler
(HVS) consists of the following:
(a.)
An anodized aluminum shelter;
(b.)
A 8¡¨x10¡¨ stainless steel filter holder;
(c.)
A blower motor assembly;
(d.)
A continuous flow/pressure recorder;
(e.)
A motor speed-voltage control/elapsed time
indicator;
(f.)
A 7-day mechanical timer, and
(g.)
A power supply of 220v/50 Hz
3.6.4
The HVS is operated and calibrated on a
regular basis in accordance with the manufacturer¡¦s instruction using Tisch Calibration Kit Model TE-5025A. Calibration would carry out in two month
interval.
3.6.5
24-hour TSP is collected by the ET on filters
of HVS and quantified by a local HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd (ALS), upon receipt of the
samples. The ET keep all the
sampled 24-hour TSP filters in normal air conditioned room conditions, i.e. 70%
RH (Relative Humidity) and 25oC, for six months prior to disposal.
3.6.6
Noise measurements were taken in terms of the
A-weighted equivalent sound pressure level (Leq)
measured in decibels (dB). Supplementary statistical results (L10
and L90) were also obtained for reference.
3.6.7
During the monitoring, all noise measurements
would be performed with the meter set to FAST response and on the A-weighted
equivalent continuous sound pressure level (Leq). Leq(30min)
in six consecutive Leq(5min) measurements will
use as the monitoring parameter for the time period between 0700-1900 hours on
weekdays; and also Leq(15min) in three
consecutive Leq(5min) measurements would
be used as monitoring parameter for other time periods (e.g. during restricted
hours), if necessary.
3.6.8
Prior of noise measurement, the accuracy of
the sound level meter is checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. The checking is performed before and
after the noise measurement.
Water
Quality
3.6.9
Water quality monitoring is conducted at the
designated locations. The sampling produce with the in-situ monitoring are
presented as below:
Sampling Procedure
3.6.10
A Digital Global
Positioning System (GPS) is used to identify the designated monitoring stations
prior to water sampling. A
portable, battery-operated echo sounder is used for the determination of water
depth at each station. At each
station, water sample would be collected from 0.1m below water surface or the
water surface to prevent the river bed sediment for stirring.
3.6.11
The sample container will be rinsed with a
portion of the water sample. The
water sample then will be transferred to the high-density polythene bottles as provided by the laboratory,
labeled with a unique sample number and sealed with a screw cap.
3.6.12
Before sampling, general information such as
the date and time of sampling, weather condition as well as the personnel
responsible for the monitoring would be recorded on the field data sheet.
3.6.13
A ¡¥Willow¡¦ 33-liter plastic cool box packed
with ice will be used to preserve the water samples prior to arrival at the
laboratory for chemical determination.
The water temperature of the cool box is maintained at a temperature as
close to 40C as possible without being frozen. Samples collected are delivered to the
laboratory upon collection.
In-situ Measurement
3.6.14
YSI PRO20 Handheld Dissolved Oxygen
Instrument is used for water in-situ
measures, which automates the measurements and data logging of
temperature, dissolved oxygen and dissolved oxygen saturation. Before
each round of monitoring, the dissolved oxygen probe would be calibrated by the
wet bulb method.
3.6.15
A portable EcoSense ® pH10A pen-style instrument is used for in-situ pH measurement. The pH meter is capable of measuring pH
in the range of 0 ¡V 14 and readable to 0.1. Standard buffer solutions of pH 7
and pH 10 are used for calibration of the instrument before and after measurement.
3.6.16
A portable Hach 2100Q Turbidimeter is used for in-situ turbidity measurement. The
turbidity meter is capable of measuring turbidity in the range of 0 ¡V 1000 NTU. StablCal®
Standards 10NTU and 100NTU are used for calibration of the instrument before and after measurement.
3.6.17
All in-situ measurement equipment are calibrated by HOKLAS accredited laboratory of three
month interval.
Laboratory Analysis
3.6.18
All water samples analyzed Suspended Solids
(SS) will be carried out by a local HOKLAS-accredited testing laboratory (ALS Technichem (HK) Pty Ltd HOKLAS registration no. 66). SS determination using APHA
Standard Methods 2540D as specified in the EM&A Manual will start within
48 hours of water sample receipt.
3.7.1
Calibration of the HVS is performed upon
installation and thereafter at bimonthly intervals in accordance with the
manufacturer¡¦s instruction using the certified standard calibrator (TISCH Model
TE-5025A).
Moreover, the Calibration Kit would be calibrated annually. The calibration data are properly
documented and the records are maintained by ET for future reference.
3.7.2
The 1-hour TSP
meter was calibrated by the supplier prior to purchase. Zero response of the equipment would be
checked before and after each monitoring event. Annually calibration with the High Volume
Sampler (HVS) in same condition would be undertaken by the Laboratory.
3.7.3
The sound level
meter and calibrator are calibrated and certified by a laboratory accredited
under HOKLAS or any other international accreditation scheme at yearly basis.
3.7.4
All water quality monitoring equipment would
be calibrated by HOKLAS accredited laboratory of three month intervals.
3.7.5
The calibration certificates of all monitoring
equipment used for the impact monitoring program in the Reporting Period and
the HOKLAS accredited certificate of laboratory are attached in Appendix F.
3.8.1
The baseline results form the basis for
determining the environmental acceptance criteria for the impact
monitoring. According to the approved
Environmental Monitoring and Audit Manual, the air quality, construction noise
and water quality criteria were set up, namely Action and Limit levels are
listed in Tables 3-8, 3-9 and 3-10.
Table 3-8 Action and
Limit Levels for Air Quality Monitoring
Monitoring
Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
AM1 |
265 |
143 |
500 |
260 |
AM2 |
268 |
149 |
||
AM3 |
269 |
145 |
||
AM4a |
267 |
148 |
||
AM5 |
268 |
143 |
||
AM6 |
269 |
148 |
||
AM7a |
275 |
156 |
||
AM8 |
269 |
144 |
||
AM9b |
271 |
151 |
Table 3-9 Action
and Limit Levels for Construction Noise
Monitoring Location |
Action Level |
Limit Level in
dB(A) |
Time Period:
0700-1900 hours on normal weekdays |
||
NM1, NM2, NM3, NM4,
NM5, NM6, NM7, NM8, NM9, NM10 |
When one
or more documented complaints are received |
75 dB(A)Note 1
& Note 2 |
Note 1: Acceptable Noise Levels
for school should be reduced to 70 dB(A)
and65 dB(A) during examination period
Note 2: If works are to be
carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the NCA have to be followed.
Table 3-10 Action and
Limit Levels for Water Quality
Parameter |
Performance
criteria |
Monitoring
Location |
|||||
WM1 |
WM2A |
WM2B |
WM3 |
WM4 |
|||
DO (mg/L) |
Action Level |
(*)4.23 |
(**)4.00 |
(*)4.74 |
(**)4.00 |
(*)4.14 |
|
Limit Level |
(#)4.19 |
(**)4.00 |
(#)4.60 |
(**)4.00 |
(#)4.08 |
||
Turbidity (NTU) |
Action Level |
51.3 |
24.9 |
11.4 |
13.4 |
35.2 |
|
AND 120% of upstream control station of
the same day |
|||||||
Limit Level |
67.6 |
33.8 |
12.3 |
14.0 |
38.4 |
||
AND 130% of upstream control station of the same day |
|||||||
SS (mg/L) |
Action Level |
54.5 |
14.6 |
11.8 |
12.6 |
39.4 |
|
AND 120% of upstream control station of the
same day |
|||||||
Limit Level |
64.9 |
17.3 |
12.4 |
12.9 |
45.5 |
||
AND 130% of upstream control station of the same day |
|||||||
Remarks: (*) The
Proposed Action Level of Dissolved
Oxygen is adopted to be used 5%-ile of
baseline data (**) The
Proposed Action & Limit Level of Dissolved
Oxygen is used 4mg/L (#) The
Proposed Limit Level of Dissolved
Oxygen is adopted to be used 1%-ile of
baseline data |
|||||||
3.8.2
Should non-compliance of the environmental
quality criteria occurs, remedial actions will be triggered according to the
Event and Action Plan which presented in Appendix G.
3.9.1
All monitoring data will be handled by the ET¡¦s in-house data recording and management system. The monitoring data
recorded in the equipment will be downloaded directly from the equipment at the
end of each monitoring day. The
downloaded monitoring data will input into a computerized database properly
maintained by the ET. The
laboratory results will be input directly into the computerized database and
checked by personnel other than those who input the data.
3.9.2
For monitoring parameters that require
laboratory analysis, the local laboratory shall follow the QA/QC requirements
as set out under the HOKLAS scheme for the relevant laboratory tests.
4.1.1
In the Reporting Period, construction works under the
project have been commenced in Contracts 3
and 5 and air quality monitoring was performed at 4 relevant designated
locations as below:
AM1 - Tsung Yuen Ha
Village House No. 63;
AM2 - Village House near Lin Ma Hang Road;
AM3 - Ta Kwu Ling
Fire Service Station of Ta Kwu Ling Village; and
AM9b - Nam Wa Po
Village House No. 80
4.1.2
The air quality monitoring schedule is presented
in Appendix H and the monitoring
results are summarized in the following sub-sections.
4.2.1
In the Reporting Period, a total of 60
events of 1-hour TSP and 23
events of 24-hours TSP monitoring were carried out and the monitoring results
are summarized in Tables 4-1 to 4-4.
The detailed 24-hour TSP monitoring data are presented in Appendix I and the relevant graphical
plots are shown in Appendix J.
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
03-Dec-13 |
58 |
05-Dec-13 |
11:07 |
130 |
97 |
81 |
09-Dec-13 |
113 |
11-Dec-13 |
10:53 |
211 |
220 |
212 |
14-Dec-13 |
141 |
17-Dec-13 |
11:09 |
134 |
105 |
137 |
20-Dec-13 |
109 |
23-Dec-13 |
10:32 |
227 |
230 |
220 |
24-Dec-13 |
109 |
28-Dec-13 |
09:50 |
173 |
222 |
177 |
30-Dec-13 |
134 |
|
|
|
|
|
Average (Range) |
111 (58 ¡V 141) |
Average (Range) |
172 (81 ¡V 230) |
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
03-Dec-13 |
85 |
05-Dec-13 |
11:01 |
118 |
116 |
92 |
09-Dec-13 |
117 |
11-Dec-13 |
10:42 |
220 |
215 |
203 |
14-Dec-13 |
86 |
17-Dec-13 |
12:00 |
101 |
112 |
120 |
*20-Dec-13 |
NA |
23-Dec-13 |
11:06 |
265 |
249 |
254 |
24-Dec-13 |
140 |
28-Dec-13 |
09:56 |
199 |
237 |
230 |
30-Dec-13 |
144 |
|
|
|
|
|
Average (Range) |
115 (85 ¡V 144) |
Average (Range) |
182 (92 ¡V 265) |
Remarks: (*)
Power failure was occurred on 20 December 2013.
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
03-Dec-13 |
93 |
05-Dec-13 |
12:23 |
84 |
69 |
74 |
09-Dec-13 |
133 |
11-Dec-13 |
10:34 |
244 |
234 |
229 |
14-Dec-13 |
79 |
17-Dec-13 |
12:03 |
98 |
92 |
119 |
20-Dec-13 |
139 |
23-Dec-13 |
11:21 |
236 |
254 |
240 |
24-Dec-13 |
114 |
28-Dec-13 |
10:14 |
221 |
244 |
268 |
30-Dec-13 |
136 |
|
|
|
|
|
Average (Range) |
116 (79 ¡V 139) |
Average (Range) |
180 (69 ¡V 268) |
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
03-Dec-13 |
104 |
05-Dec-13 |
13:11 |
80 |
72 |
76 |
09-Dec-13 |
42 |
11-Dec-13 |
11:32 |
208 |
211 |
232 |
14-Dec-13 |
56 |
17-Dec-13 |
10:22 |
86 |
154 |
121 |
20-Dec-13 |
78 |
23-Dec-13 |
15:15 |
244 |
267 |
258 |
24-Dec-13 |
69 |
28-Dec-13 |
10:45 |
134 |
192 |
220 |
30-Dec-13 |
58 |
|
|
|
|
|
Average (Range) |
68 (42 ¡V 104) |
Average (Range) |
170 (72 ¡V 267) |
4.2.2
In Reporting
period, AM2 power failure occurred on 20 December 2013. Power supply has resumed on 23 December
2013. So, only five events of
24-hour TSP monitoring conducted at AM2.
4.2.3
As shown in Tables 4-1 to 4-4,
the 24-hour and 1-hour TSP monitoring results were below the Action/ Limit
Level. No Notification of
Exceedances (NOE) of air quality criteria or corrective action was therefore
required.
4.2.4
Two months interval calibration has been
carried out at AM1, AM2 and AM3 in accordance with the EM&A Manual
requirements. The updated
calibration certificates are attached in Appendix F.
4.2.5
The meteorological data during the impact
monitoring days are summarized in Appendix
K.
5.1.1
In the Reporting Period, construction works under the
project have been commenced in Contracts
3 and 5 and noise monitoring was performed at 5 relevant designated locations
as below:
NM1 - Tsung Yuen Ha
Village House No. 63;
NM2 - Village House near Lin Ma Hang Road;
NM8 - Village House, Tong Hang;
NM9 - Village House, Kiu Tau Village; and
NM10 - Nam Wa Po Village House No. 80
5.1.2
The noise monitoring schedule is presented in
Appendix H and the monitoring
results are summarized in the following sub-sections.
5.2.1
In the Reporting Period, a total of 25
event noise measurements were carried out at the designated locations. The sound level meter was set in 1m from
the exterior of the building façade including noise monitoring locations NM1,
NM2, NM8 and NM9. Therefore, no
façade correction (+3 dB(A) is added according to
acoustical principles and EPD guidelines.
However, free-field status was performed at NM10. So, façade correction (+3 dB(A) has added according to the requirement in this
month. The noise monitoring results
at the designated locations are summarized in Tables 5-1. The detailed noise monitoring
data are presented in Appendix
I and the relevant graphical plots are shown in Appendix J.
Table 5-1 Summary of Construction Noise Monitoring Results
Date |
NM1 (Leq30min) |
NM2 (Leq30min) |
NM8 (Leq30min) |
NM9 (Leq30min) |
(*) NM10 (Leq30min) |
05-Dec-13 |
57
|
67 |
63 |
63 |
62 |
11-Dec-13 |
55
|
59 |
62 |
64 |
61 |
19-Dec-13 |
55
|
61
|
63
|
62 |
61 |
23-Dec-13 |
52
|
60
|
56
|
71 |
60 |
28-Dec-13 |
55
|
61 |
61 |
63 |
60 |
Limit Level |
75 dB(A) |
Remarks
(*) façade correction (+3 dB(A)
is added according to acoustical principles and EPD guidelines
5.2.2
As shown in Tables 5-1, the noise
level measured at five (5) designated monitoring locations were below 75dB(A).
Furthermore, there were no noise complaints (Action Level exceedance)
received by the RE, Contractor or CEDD in the Reporting Period. Therefore, no Action or Limit Level
exceedance was triggered and no corrective action was therefore required.
6.1.1
In the Reporting Period, construction works under the
project has been commenced in Contracts
3 and 5 and water quality monitoring was performed at 5 relevant designated
locations as below:
WM1 ¡V Contract 5 working site downstream at Kong
Yiu Channel;
WM1-Control ¡V Contract 5 working site upstream
at Kong Yiu Channel;
WM4 - Contract 3 working site Downstream of Ma Wat
Channel
WM4¡VControl A - Contract 3 working site Kau Lung Hang Stream
WM4¡VControl B - Contract 3 working site Upstream of Ma Wat
Channel
6.1.2
The water quality monitoring schedule is presented
in Appendix H. The monitoring results are summarized in
the following sub-sections.
6.2.1
In the Reporting Period, a total of 12
sampling days were performed for water quality monitoring at Contracts 3 and 5. The key monitoring parameters including Dissolved Oxygen, Turbidity and Suspended
Solids are summarized in Tables 6-1 and 6-2. Breaches of water
quality monitoring criteria are shown in Table 6-3. Detailed
monitoring database including in-situ measurements and laboratory analysis data
are shown in Appendix I and the relevant
graphical plot are shown in Appendix
J.
Table 6-1 Summary
of Water Quality Monitoring Results for Contract 3
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
||||||
WM4 |
WM4-CA |
WM4-CB |
WM4 |
WM4-CA |
WM4-CB |
WM4 |
WM4-CA |
WM4-CB |
|
3-Dec-13 |
8.8 |
7.0 |
7.2 |
18.5 |
3.5 |
3.8 |
19.0 |
4.0 |
8.0 |
5-Dec-13 |
7.2 |
7.8 |
6.7 |
7.0 |
43.9 |
4.2 |
7.0 |
43.5 |
5.5 |
7-Dec-13 |
9.1 |
6.3 |
9.5 |
16.2 |
8.0 |
13.5 |
17.5 |
5.5 |
15.5 |
9-Dec-13 |
11.4 |
6.4 |
10.1 |
12.4 |
8.8 |
4.8 |
15.5 |
8.5 |
5.0 |
11-Dec-13 |
8.7 |
6.6 |
8.1 |
7.4 |
3.0 |
4.9 |
8.0 |
2.0 |
3.5 |
13-Dec-13 |
9.2 |
8.8 |
7.1 |
7.9 |
7.3 |
3.8 |
8.0 |
16.0 |
3.5 |
17-Dec-13 |
10.4 |
11.3 |
6.8 |
25.5 |
10.5 |
16.5 |
25.0 |
10.5 |
13.5 |
19-Dec-13 |
7.0 |
9.0 |
6.1 |
13.0 |
2.6 |
5.9 |
10.5 |
2.0 |
4.0 |
21-Dec-13 |
8.0 |
7.9 |
7.3 |
5.4 |
13.4 |
4.5 |
6.5 |
9.5 |
4.5 |
23-Dec-13 |
6.8 |
7.1 |
10.5 |
6.7 |
2.5 |
4.3 |
5.0 |
<2 |
8.0 |
28-Dec-13 |
11.8 |
11.2 |
8.7 |
16.6 |
3.4 |
4.1 |
12.5 |
<2 |
2.0 |
30-Dec-13 |
10.6 |
9.0 |
9.3 |
7.2 |
12.6 |
6.8 |
5.0 |
4.0 |
3.5 |
Table 6-2 Summary
of Water Quality Monitoring Results for Contract 5
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
|||
WM1 |
WM1- Control |
WM1 |
WM1- Control |
WM1 |
WM1- Control |
|
3-Dec-13 |
7.1 |
5.6 |
12.3 |
6.8 |
11.5 |
2.5 |
5-Dec-13 |
6.3 |
6.6 |
8.2 |
6.5 |
5.0 |
5.0 |
7-Dec-13 |
6.5 |
10.6 |
8.0 |
12.3 |
6.0 |
20.0 |
9-Dec-13 |
8.6 |
11.5 |
9.9 |
5.5 |
9.5 |
3.0 |
11-Dec-13 |
8.4 |
9.2 |
17.4 |
5.7 |
13.5 |
2.5 |
13-Dec-13 |
6.5 |
8.3 |
7.1 |
5.2 |
6.5 |
4.0 |
17-Dec-13 |
8.3 |
9.7 |
209.0 |
55.6 |
107.5 |
35.0 |
19-Dec-13 |
5.6 |
7.7 |
18.4 |
151.0 |
13.0 |
112.5 |
21-Dec-13 |
7.2 |
6.7 |
8.1 |
8.7 |
10.5 |
5.5 |
23-Dec-13 |
7.9 |
7.8 |
8.4 |
5.6 |
6.0 |
3.0 |
28-Dec-13 |
7.4 |
8.1 |
15.6 |
6.5 |
12.0 |
<2 |
30-Dec-13 |
8.1 |
5.5 |
6.9 |
5.9 |
3.0 |
<2 |
Remark: Bold and underlined indicated Limit Level exceedance
Table 6-3 Breaches
of Water Quality Monitoring Criteria in Reporting Period
Location |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Total Exceedance |
||||
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
|
WM1 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
2 |
WM4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
No of Exceedance |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
2 |
6.2.2
In view of the monitoring results of Dissolved Oxygen (DO), all the measured results
were higher than Action Level exceedance and no exceedances were therefore
triggered.
6.2.3
Two
(2) Limit Level exceedances including parameters turbidity and SS were recorded
at WM1 on 17 December 2013. The Notification
on Exceedances (NOEs) was issued to all relevant parties upon the results
confirmed. The investigation for the cause of exceedance
was completed and the result is presented as follow:
According to the site information provided by SRJV,
the site construction activities carried out on 17 Dec 2013 included sheet
piling and formworks erection of Retaining Wall No.1, and backfill at BCP Area.
All the active construction activities under the project
are land based and do not disturb the river environment.
On 14,
15 and 16 Dec before the sampling day, Hong Kong Observatory recorded has
raining; moreover the sampling date 17 December 2013 also has raining. As
reviewed baseline monitoring data, turbidity and
suspended solids of abnormally high result are obtained after rainfall or rainy
day. The condition of the river
water quality is highly influenced by the rainfall.
Upon receipt of the NOE, SRJV provided site photograph
records dated 17 Dec 2013.
Reviewing the provided photograph records, muddy water observed at
upstream on Tsung
Yuen Ha Village.
Addition, some soil strain/mark observed at other side
of Kong Yiu River of the DSD maintenance access and
slope surface which situated outside the Project site boundary.
SRJV have implemented water mitigation measures such
as erection of sand bags barrier along the edge of the river and works area to
prevent the storm runoff into the existing river.
6.2.4
Based on above investigation
and consider that the exceedance should not be due to
the Project works.
7.1.1
Waste management was carried out by an
on-site Environmental Officer or an Environmental Supervisor from time to time.
7.2.1
All types of waste arising from the
construction work are classified into the following:
l Construction
& Demolition (C&D) Material;
l Chemical
Waste;
l General
Refuse; and
l Excavated
Soil.
7.2.2
The quantities of waste for disposal in this
Reporting Period are summarized in Tables 7-1 and 7-2 and the Monthly
Summary Waste Flow Table is shown in Appendix L. Whenever possible, materials were reused
on-site as far as practicable.
Table 7-1 Summary
of Quantities of Inert C&D Materials for the Project
Type of Waste |
Contract 3 |
Contract 5 |
Total Quantity for the Project |
||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
||
C&D Materials (Inert) (in '000m3) |
0.177 |
- |
0 |
-- |
0.177 |
Reused in this Project (Inert) (in '000 m3) |
0.030 |
- |
0 |
-- |
0.030 |
Reused in other Projects (Inert) (in '000 m3) |
0 |
- |
0 |
-- |
0 |
Disposal as Public Fill (Inert) (in '000 m3) |
0.140 |
Tuen Mun 38 |
0 |
-- |
0.140 |
Table 7-2 Summary
of Quantities of C&D Wastes for
the Project
Type of Waste |
Contract 3 |
Contract 5 |
Total Quantity for the Project |
||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
||
Recycled Metal (kg) |
0 |
- |
11.53 |
-- |
11.53 |
Recycled
Paper / Cardboard Packing (kg) |
0 |
- |
0 |
-- |
0 |
Recycled Plastic (kg) |
0 |
- |
0 |
-- |
0 |
Chemical Wastes (kg) |
0 |
- |
0 |
-- |
0 |
General Refuses (in '000m3) |
0.055 |
NENT |
0.2 |
NENT |
0.255 |
8.1.1
According to the approved EM&A Manual, the
environmental site inspection shall be formulation by ET Leader. Weekly environmental site inspections should
carry out to confirm the environmental performance.
The Contract 3
8.2.1
In the Reporting Period, joint site
inspection for Contract 3 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 4, 11, 18, 23 and 30 December 2013. No non-compliance was noted.
8.2.2
The findings / deficiencies of Contract
3 that observed during the weekly site inspection are listed in Table
8-1.
Table 8-1 Site
Observations for Contract 3
Date |
Findings / Deficiencies |
Follow-Up Status |
27 Nov 2013 (last Reporting Period) |
Free standing chemical was observed at construction site,
the Contractor was reminded to provide enough drip tray for all free standing
chemical at the construction site. |
Free standing chemical container was removed from
construction site before site inspection on 4 December 2013 |
Fences for tree protection is not enough, the Contractor
was reminded to provide enough fence to protect all the trees retained on
site. |
Tree fence has erected to protect all trees
retained on site. |
|
The Contractor was reminded that the chemical container
should be located far from the U-channel to prevent contamination of the
riverbody |
During site inspection dated 4 December 2013, the chemical
container has located far from the U-channel. |
|
04 Dec 2013 |
Trees to be transplanted or retained should be protected by
durable fence and designated as no intrusion zone in Nam Wa Po. |
In
Nam Wa Po, all trees has
fenced off during site inspection on 18 December 2013. |
|
Oil stain observed at Tai Wo Service Road West. The Contractor is
reminded to clear-up and all the working plant used at site should
be regular carried out maintainance. |
No oil stain has observed at Tai Wo Service Road West during site inspection 11 December
2013. |
11 Dec 2013 |
The Contractor was reminded to prevent oil spilling and
clear the oil stain at Nam Wa Po near AM9b monitoring station |
No oil stain has observed at Nam Wa Po during site inspection 23
December 2013. |
18 Dec 2013 |
The Contractor should be improvement tree fences to
protect on site the retained tree. |
Tree
fences has improved before site inspection dated 30 December 2013 |
The
Contractor was recommended improve wheel washing bay to ensure all wastewater
collection and delivery to desilting facility. |
The improvement work is not yet undertaken and it will be
report in the coming month. |
|
Required
the Contractor to provide enough rubbish bins at Nam Wa Po. |
Extra rubbish bins or plastic bags has been provided at Nam
Wa Po. Also, daily cleaning has followed. |
|
23 Dec 2013 |
The Contractor is reminded to provide sand bag as water
mitigation measure at the drainage trench in Nam Wa Po near Tai Wo Service
Road West for desilting runoff from the road. |
A sand bag bund has provided at the
drainage trench as observed on 30 December 2013 during site inspection. |
30 Dec 2013 |
The construction materials were observed located within tree
protection zone. The Contractor
was required immediately remove those materials. |
Will be reported in the coming month |
Water overflow observed in water storage tank. To prevent the wastage, the Contractor should
be repaired it to stop the issue. |
||
The general refuse, C&D material and trunk waste should be
clean-up regular basis |
8.2.3
Moreover, the general housekeeping such as
tidiness of weekly and cleaniness of daily should be maintained in accordance
with the PS requirements.
The Contract 5
8.2.4
In the Reporting Period, joint site
inspection for Contract 5 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 5, 11, 19 and
24 December 2013. No
non-compliance was noted.
8.2.5
The findings / deficiencies of Contract
5 that observed during the weekly site inspection are listed in Table
8-2.
Table 8-2 Site
Observations for Contract 5
Date |
||
28 Nov 2013 (last Reporting Period) |
Muddy runoff through the gaps of the sandbag bund
was suspected at the Metal Bridge (A), the Contractor should maintain the
sandbag bund properly. |
Sand and cement mortar has been provided at the edge
of Metal Bridge (A) during site inspection on 5 December 2013. |
Muddy
water was observed on the public road at both Kaw Liu Village (Photo 3) and
Metal Bridge B area (Photo 4), the Contractor was reminded to clean to road
regularly to get rid of loose and mud tail. |
No muddy water or loose soil are observed at Kaw Liu Village during site
inspections. |
|
The
Contractor was reminded to apply mitigation measure to prevent potential
runoff of soil from metal pipe to the river at the Metal Bridge B. |
Sand bags has provided at the metal pipe. |
|
At
Area BCP7, the Contractor was reminded to treat lubricant oil as chemical
waste. |
The Contractor has followed compliance with
the chemical waste disposal requirements. |
|
05 Dec 2013 |
The Contractor was reminded to remove
the stagnant water. |
No stagnant water was observed during site
inspection 11 December 2013. |
Free standing chemical container was
observed, the Contractor was reminded to provide
drip tray to all chemical containers. |
During site inspection dated 19 December
2013, all chemical containers located on site has been provided drip tray to
prevent land contamination. |
|
11 Dec 2013 |
The Contractor was recommended to
build a rock bund or soil bund as desilting facilities around the discharging
steel pipeline to prevent water pollution. |
A rock bund has built-up during site
inspection on 24 December 2013. |
Uncover stockpile was observed, the
Contractor was reminded to cover the stockpile to prevent fugitive dust
emission. Moreover, the Contractor was recommended to build a three-sides
shelter, including the top cover, if the cement mixing works will be carried
out. |
During site inspection on 19 December 2013,
the stockpile of construction material observed is wet. |
|
Dry haul road was observed, the
Contractor was reminded to provide water spraying in regular basis. |
Water spraying frequency eight times per
day has followed in accordance with the dust mitigation measures stipulation. |
|
A soakaway
facility was observed during site inspection, the Contractor was recommended
to fence off this zone and provide notification board. |
Fences
and signage has been provided at the soakaway
facility observed during site inspection in 19 December 2013 |
|
19 Dec 2013 |
Stagnant water inside containers was
observed after rainfall, the Contractor was reminded to cover them or turn
the containers upside down to prevent accumulated water. |
During
site inspection on 24 December 2013, all not used containers located on site
were covered with plastic sheet or turned upside down to prevent accumulated
water. Moreover, no stagnant
water observed at the using containers. |
The Contractor was
reminded to provide proper labels for all chemical container. |
Relevant
label has been provided for chemical container during site inspection on 24
December 2013. |
|
Uncovered sand
stockpile was observed, the Contractor was reminded to cover the stockpile
with imprevios sheet or remove it to prevent fugitive dust. |
Still yet rectified and will be reported in the coming month. |
|
24 Dec 2013 |
At location
Lin Ma Hang, the Contractor should provide water quality mitigation measure
for discharge water, and proper mitigation measure has been provided
immediately to prevent water pollution.
Disused de-silting
pool should be backfilled and also the soakaway path should be minimized or
limited to improve its formation. |
Will be reported in the coming month |
8.2.6
Moreover, the general housekeeping such as
tidiness of weekly and cleaniness of daily should be maintained in accordance
with the PS requirements. Addition,
regular basis cleaning the wheel washing bay is
reminder. Furthermore, works at
Bridge J Area, tree protected fences should be provided to protect all retained
tree.
Other Contracts
8.2.7
Since the construction works at the Contract
2 and Contract 4 and Contract 6 are not yet commenced, no site inspection is
performed for these Contracts.
The
Contract 3
9.1.1
The
Liantang/Heung
Yuen Wai Boundary Control Point and Associated Works, no environmental complaint, summons
and prosecution under the EM&A Programme was
received in the Reporting Period. The statistical summary table of environmental
complaint is presented in Tables 9-1, 9-2 and 9-3.
Table 9-1 Statistical
Summary of Environmental Complaints
Reporting Period |
Contract No |
Environmental
Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
6 Nov 2013 to 30 Nov 2013 |
Contract 3 |
0 |
0 |
NA |
16 Aug 2013 to 30 Nov 2013 |
Contract 5 |
0 |
0 |
NA |
1 ¡V 31 Dec 2013 |
Contract 3 |
0 |
0 |
NA |
Contract 5 |
0 |
0 |
NA |
Table 9-2 Statistical
Summary of Environmental Summons
Reporting Period |
Contract No |
Environmental
Summons Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
6 Nov 2013 to 30 Nov 2013 |
Contract 3 |
0 |
0 |
NA |
16 Aug 2013 to 30 Nov 2013 |
Contract 5 |
0 |
0 |
NA |
1 ¡V 31 Dec 2013 |
Contract 3 |
0 |
0 |
NA |
Contract 5 |
0 |
0 |
NA |
Table 9-3 Statistical
Summary of Environmental Prosecution
Reporting Period |
Contract No |
Environmental
Prosecution Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
6 Nov 2013 to 30 Nov 2013 |
Contract 3 |
0 |
0 |
NA |
16 Aug 2013 to 30 Nov 2013 |
Contract 5 |
0 |
0 |
NA |
1 ¡V 31 Dec 2013 |
Contract 3 |
0 |
0 |
NA |
Contract 5 |
0 |
0 |
NA |
The Other
Contracts
9.1.2
Since the construction works at the Contract
2, Contract 4 and Contract 6 are not yet commenced, no environmental complaint,
summons and prosecution under the EM&A Programme are
registered in the Reporting Period.
10.1.1
The environmental mitigation measures that
recommended in the Implementation Schedule for Environmental Mitigation
Measures (ISEMM) in the approved EM&A Manual covered the issues of dust,
noise, water and waste and they are summarized presented in Appendix
M.
10.1.2
All contracts under the Project shall be
implementing the required environmental mitigation measures according to the approved
EM&A Manual as subject to the site condition. Environmental mitigation measures
generally implemented by Contracts 3 and 5 in this Reporting Period are
summarized in Table 10-1.
Table 10-1 Environmental
Mitigation Measures
Issues |
Environmental
Mitigation Measures |
Water Quality |
¡P Wastewater to be treated by
filtration system; such as, silt curtain or sedimentation tank before
discharge. ¡P Replace silt curtain
materials if necessary |
Air Quality |
¡P Maintain damp / wet surface
on access road ¡P Keep slow speed in the sites ¡P All vehicles must use wheel
washing facility before off site ¡P Sprayed water during
breaking works |
Noise |
¡P Restrain operation time of
plants from 07:00 to 19:00 on any working day except for Public Holiday and
Sunday. ¡P Keep good maintenance of
plants ¡P Place noisy plants away from
residence or school ¡P Provide noise barriers or
hoarding to enclose the noisy plants or works ¡P Shut down the plants when
not in used. |
Waste and Chemical Management |
¡P On-site sorting prior to
disposal ¡P Follow requirements and
procedures of the ¡§Trip-ticket System¡¨ ¡P Predict required quantity of
concrete accurately ¡P Collect
the unused fresh concrete at designated locations in the sites for subsequent
disposal |
General |
¡P The site was generally kept
tidy and clean. |
10.2.1
Construction activities as undertaken in the
coming month for the Project lists below:
Contract 3
Erection of site office
Cable detection and trial trenches
Pre-drilling works and piling works
Tree felling works, waterworks and excavation
works
Dismantling works for abandoned houses
Slope upgrading works
Noise barrier installation
Extension of box culvert
Construction of haul road and temporary soil platform
for geotechnical works
Laying of concrete pipe works
Contract 5
Construction
of retaining wall No.1
Piling
works at life shaft, Bridge J & footbridge
Construction
of pedestrian subway and pump room at LMH
Pipe
jacking across Kong Yuen River
Formation
Works at BCP Area
Construction
of Depressed Road at BCP3
Transplantation,
Pruning/felling of existing tree
Drainage
and Sewerage works at LMH Road
10.3.1
Key issues to be considered in the coming
month for Contracts 3 and 5 include:
Implementation of dust
suppression measures at all times;
Potential wastewater
quality impact due to surface runoff;
Potential fugitive
dust quality impact due from the dry/loose/exposure soil surface/dusty
material;
Disposal of empty
engine oil containers within site area;
Ensure dust suppression measures are
implemented properly;
Sediment catch-pits and silt removal
facilities should be regularly maintained;
Management of chemical wastes;
Discharge of site effluent to the nearby
wetland, stockpiling or disposal of materials, and any dredging or construction
area at this area are prohibited;
Follow-up of improvement on general waste
management issues; and
Implementation of construction noise
preventative control measures
10.3.2
For other Contracts, no environmental issue
is considered due to these contracts still yet to commence.
11.1.1
This is 5th
monthly EM&A report presenting the monitoring results and inspection
findings for the Reporting Period from 1 to 31 December 2013.
11.1.2
No 24-hour or 1-hour TSP monitoring results
that triggered the Action or Limit Levels were recorded. No NOEs or the
associated corrective actions were therefore issued.
11.1.3
No noise complaint (which is an Action Level
exceedance) was received and no construction noise measurement results that
exceeded the Limit Level were recorded in the Reporting Period. No NOEs or the
associated corrective actions were therefore issued.
11.1.4
For
water quality monitoring, two (2) Limit Level exceedances were recorded on 17
December 2013 at W1.
The Notification on Exceedances (NOEs) was
issued to all relevant parties. Based on investigation
findings to conclude that the exceedance should not be
due to the Project works.
11.1.5
No environmental complaint, notification of
summons or successful prosecution under the EM&A Programme
of the Liantang/Heung
Yuen Wai Boundary Control Point and Associated Works was received in the reporting period.
11.1.6
Four (4) and five (5) events of joint site
inspection by the RE, IEC, ET and main-contractor were respectively carried out
for Contracts 3 and 5. No
non-compliance observed during the site inspection. During dry season, air quality
mitigation measures such as increase the water spray frequency (at least eight
times per day) in haul road to prevent construction dust emission is
reminded. The environmental
performance of the Project of Contracts 3 and 5 was therefore considered as satisfactory.
11.1.7
Joint site inspection during Reporting
Period, five events for Contract 3 and four events for Contract 5 were carried
out the RE, IEC, ET and Main-contractor in accordance with the EM&A Manual
stipulation. No non-compliance
observed during the site inspection.
During dry season, air quality mitigation measures such as increase the
water spray frequency (at least eight times per day) in haul road to prevent
construction dust emission is reminded.
The environmental performance of the Project of Contracts 3 and 5 was
therefore considered as satisfactory.
11.2.1
During dry season,
special attention should be paid on the potential construction dust impact
since most of the construction sites are adjacent to villages. The Contractor should fully implement
the construction dust mitigation measures properly.
11.2.2
Moreover, muddy water
and other water quality pollutants via site surface water runoff get into Kong Yiu Channel and Ma Wat Channel to public
areas should be avoided. Mitigation measures for water quality
should be properly implemented.
11.2.3
Construction noise
should be a key environmental impact during the works. The noise mitigation measures such as
use of quiet plants or temporary noise barrier installation at the construction
noise predominate area should be implemented as accordance with the EM&A
requirement.
11.2.4
Mosquito control measures should be continued
to prevent mosquito breeding on site.