|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00694/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report (No.45)
¡V April 2017 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
15 May 2017 |
TCS00694/13/600/R0969v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
10 May 2017 |
First
Submission |
2 |
15 May 2017 |
Amended against the IEC¡¦s comments on 12 May 2017 |
|
|
|
executive summary
ES01
This is the 45th monthly EM&A
report presenting the monitoring results and inspection findings for the reporting
period from 1 to 30 April 2017 (hereinafter ¡¥the Reporting Period¡¦).
Environmental Monitoring
and Audit Activities
ES02
To facilitate the project management and
implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08),
Contract 3 (CV/2012/09), Contract 4 (NE/2014/02),
Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and
an ArshSD contract (Contract SS C505).
ES03
In the Reporting Period, the major construction
works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the
Project included Contract 2, Contract 3, Contract 6, Contract 7 and Contract SS
C505. Environmental monitoring
activities under the EM&A programme in the Reporting Period are summarized
in the following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
9 |
150 |
24-hour TSP |
9 |
45 |
|
Construction Noise |
Leq(30min) Daytime |
10 |
40 |
Water Quality |
Water in-situ
measurement and/or sampling |
WM1 & WM1-C |
12 Scheduled & 3 extra |
WM2A(a) & WM2A-Cx |
12 Scheduled & 3 extra |
||
WM2B & WM2B-C |
12 Scheduled & 0 extra |
||
WM3x &WM3-C |
12 Scheduled & 3 extra |
||
WM4, WM4-CA &WM4-CB |
12 Scheduled & 1 extra |
||
Ecology |
Woodland compensation i) General Health condition of planted species ii) Survival of planted species |
9 Quadrats |
1 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and
Auditing |
Contract 2 |
4 |
Contract 3 |
4 |
||
Contract 6 |
4 |
||
Contract 7 |
4 |
||
Contract SS C505 (#) |
4 |
Note: Extra monitoring day was due to measurement
results exceedance
# IEC only joined
one (1) event of site inspection for Contract SS C505.
Action and Limit (A/L) Levels exceedance
ES04
In the Reporting Period, no air quality and construction noise exceedances were recorded. For water quality monitoring, twenty-two (22) Limit Level
exceedances were recorded under the Project. The summary of exceedance in the
Reporting Period is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
|||
NOE Issued |
Investigation Result |
Project related exceedance |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
24-hour TSP |
0 |
0 |
0 |
-- |
-- |
-- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
- |
-- |
-- |
Turbidity |
0 |
10 |
10 |
-
exceedances
recoded on 8, 10, 12, 13 and 14 April 2017 were concluded as non-project
related -
exceedances 22, 25 and 26 April 2017 were under investigation. |
0 |
The Contractors were reminded to implement water quality mitigation
measures in accordance with ISEMM of the EM&A Manual requirements |
|
SS |
0 |
12 |
12 |
0 |
Environmental
Complaint
ES05
In
this Reporting Period, two (2) documented environmental complaints were received
regarding noise issue for Contract 2 and wastewater issue related to Contracts
2 and 6. Investigation report (IR)
for complaints revealed that all the complaints were not related to the
Contract.
ES06
The summary of complaint received in the
Reporting Period is summarized below.
Reporting Period |
Contract No |
Environmental Complaint |
||
Frequency |
Complaint Nature |
Project related complaint |
||
1 ¡V 30 April 2017 |
Contract 2 |
2 |
Noise (1) Wastewater (1) |
0 |
Contract 3 |
1 |
wastewater |
0 |
|
Contract 6 |
0 |
NA |
NA |
|
Contract 7 |
0 |
NA |
NA |
|
SS C505 |
0 |
NA |
NA |
Notification of
Summons and Successful Prosecutions
ES07
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
ES08
In the Reporting Period, EPD has approved the
revised EM&A Programme (Rev.7) which included the proposal for not necessary
to perform noise measurement during restricted hours periods. Therefore, noise measurement during
restricted hours periods will be ceased on 7 April 2017 in accordance with the
updated EM&A Programme (Rev. 07) (Section 3.1.5) (EPD ref.: ( ) in
EP2/N7/A/52 Ax(1) Pt.20 dated 7 April 2017)
ES09
Moreover, EPD has
approved the revised EM&A Programme (Rev.7) which proposed that (1) if the
measured water depth of the monitoring station is lower than 150 mm,
alternative location based on the criteria were selected to perform water
monitoring; and (2) If no
suitable alternative location could be found within 15m far from the original
location, the sampling at that location will be cancelled since sampling at too
far from the designated location could not make a representative sample in
accordance with the updated EM&A Programme (Rev. 07) (Section 4.1.4) (EPD
ref.: ( ) in EP2/N7/A/52 Ax(1) Pt.20 dated 7 April 2017)
ES10
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 7, 12, 21 and 28
April 2017. No non-compliance was noted during the
site inspection.
ES11
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 3, 10, 19 and 24
April 2017. No non-compliance was noted during the site
inspection.
ES12
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
6 has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 20 and 27 April 2017. No non-compliance was noted during the site
inspection.
ES13
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
SS C505 has been carried out by the RE, IEC, ET and the Contractor on 5, 12, 19 and 26
April 2017. No non-compliance was noted during the site
inspection.
ES14
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
7 has been carried out by the RE, IEC, ET and the Contractor on 3, 11, 18 and 25 April
2017. No non-compliance
was noted during the site inspection.
Future Key Issues
ES15
During wet season, preventive measures for
muddy water or other water pollutants from site surface flow to local stream such
as Kong Yiu Channel, Ma Wat Channel, Ping
Yuen River, Kwan Tei River or public area should be
properly maintained. The Contractors should paid special
attention on water quality
mitigation measures and fully implement according ISEMM of the EM&A Manual,
in particular for working areas near Ma Wat Channel and Ping Yuen River.
ES16
In addition, all effluent
discharge shall be ensure to fulfill Technical Memorandum of Effluent
Discharged into Drainage and Sewerage Systems, inland and Coastal Waters
criteria or discharge permits stipulation.
ES17
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
ES18
Since most of construction sites under the Project are
located adjacent to villages, the Contractors should fully
implement air quality mitigation measures to reduce construction dust emission.