|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00670/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008 (CE) Liantang/Heung Yuen Wai Boundary Control Point and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Baseline
Monitoring Report |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
16
August 2013 |
TCS00670/13/600/R0030v3 |
|
|
|
|
Version |
Date |
Remarks |
1 |
15 July 2013 |
First Submission |
2 |
16 July 2013 |
Amended
against IEC’s comments on 15 July 2013 |
3 |
16 August 2013 |
Amended
against EPD’s comments on 2 August 2013 |
|
|
|
executive summary
ES.01 Civil Engineering and Development Department (hereafter referred as “CEDD”)
is the Project Proponent and the Permit Holder of Agreement
No. CE 45/2008 (CE) Liantang / Heung Yuen Wai Boundary Control Point and
Associated Works (hereinafter referred as “the Project”),
which is a Designated Project to be implemented under Environmental Permit
number EP-404/2011 (hereinafter
referred as “the EP-404/2011” or “the EP”).
ES.02 Action-United
Environmental Services & Consulting (hereinafter
referred as “AUES”) has been commissioned as the Environmental Team for the
Project (hereinafter referred as “the ET”) to perform relevant EM&A
programme, including baseline and impact environmental monitoring in accordance
with the EM&A Manual approved
under the Environmental Impact Assessment Ordinance (EIAO).
ES.03 According to the Approved
EM&A Manual, air quality, noise and water quality monitoring should be required to be
monitored during the construction phase of the Project. Pursuant to
the EP, baseline environmental
monitoring is required to be conducted prior to commencement of the
construction works under the Project.
For the EP stipulation, baseline monitoring including air quality, noise and
water quality was conducted from 13 June 2013 to 12 July 2013. During the baseline monitoring period, no
construction activities under the Project or other external influencing factors
of significant concern were observed.
ES.04 This report summarizes the key findings and presents the
process and rationale behind determining a set of Action and Limit Levels (A/L
Levels) of air quality, construction noise and water quality based on the
baseline data. These A/L Levels will
serve as the yardsticks for assessing the acceptability of the environmental impact
during construction phase of the Project Works impact monitoring. They are statistical in nature and derived
according to the criteria set out in the Approved EM&A Manual.
ES.05 Results of the derived Action and Limit
Levels for the air quality, noise and water quality are given in Tables
ES-1, ES-2 and ES-3 as follows.
Table ES-1 Action
and Limit Levels of Air Quality Monitoring
Monitoring Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
AM1 |
265 |
143 |
500 |
260 |
AM2 |
268 |
149 |
500 |
260 |
AM3 |
269 |
145 |
500 |
260 |
AM4a |
267 |
148 |
500 |
260 |
AM5 |
268 |
143 |
500 |
260 |
AM6 |
269 |
148 |
500 |
260 |
AM7a |
275 |
156 |
500 |
260 |
AM8 |
269 |
144 |
500 |
260 |
AM9a |
271 |
151 |
500 |
260 |
Table ES-2 Action and Limit Levels of Construction
Noise Monitoring
Monitoring Location |
Action Level |
Limit Level in dB(A) |
Time Period: 0700-1900 hours
on normal weekdays |
||
NM1, NM2, NM3, NM4, NM5, NM6, NM7, NM8,
NM9, NM10 |
When one or more documented
complaints are received |
75 dB(A)Note 1 |
Note 1: Acceptable Noise Levels for school should be
reduced to 70 dB(A)
and65 dB(A) during examination period
Note 2: If works are to be carried out during restricted hours, the conditions
stipulated in the construction noise permit issued by the NCA
have to be followed.
Table ES-3 Action
and Limit Levels of Water Quality Monitoring
Parameter |
Performance criteria |
Monitoring Location |
|||||
WM1 |
WM2A |
WM2B |
WM3 |
WM4 |
|||
DO (mg/L) |
Action Level |
(*)4.23 |
(**)4.00 |
(*)4.74 |
(**)4.00 |
(*)4.14 |
|
Limit Level |
(#)4.19 |
(**)4.00 |
(#)4.60 |
(**)4.00 |
(#)4.08 |
||
Turbidity (NTU) |
Action Level |
51.3 |
24.9 |
11.4 |
13.4 |
35.2 |
|
AND 120% of upstream control station of the
same day |
|||||||
Limit Level |
67.6 |
33.8 |
12.3 |
14.0 |
38.4 |
||
AND 130% of upstream control station of the same day |
|||||||
SS (mg/L) |
Action Level |
54.5 |
14.6 |
11.8 |
12.6 |
39.4 |
|
AND 120% of upstream control station of the same
day |
|||||||
Limit Level |
64.9 |
17.3 |
12.4 |
12.9 |
45.5 |
||
AND 130% of upstream control station of the same day |
|||||||
Remarks: (*) The Proposed
Action Level of Dissolved Oxygen
is adopted to be used 5%-ile of baseline data (**) The
Proposed Action & Limit Level of Dissolved Oxygen
is used 4mg/L (#) The Proposed Limit Level of Dissolved Oxygen is
adopted to be used 1%-ile of baseline data Notes: All the figures given in the
table are used for reference only and the EPD may amend the figures whenever
it is considered necessary. |
|||||||
ES.6 In cases where exceedance of these criteria occurs, actions
should be carried out in accordance with the Event Action Plan as shown the
Approved EM&A Manual.
Table of Contents
2 Summary of
Baseline Monitoring Requirement
2.4 Monitoring Frequency and
Period
2.6 Derivation of
Action/Limit (A/L) Levels
3 Baseline
monitoring methdology
3.2 Location of Baseline
Monitoring
3.3 Monitoring Equipment at
Baseline Monitoring
3.5 Data Management and Data QA/QC Control
4.2 Results of Air Quality
Monitoring
4.3 Results of Noise
Monitoring
4.4 Results of Water Quality
Monitoring
4.5 Discussion and
Recommendations
5 Conclusions
and Recommentations
List of TABLES
Table 2-1 Summary of EM&A Requirements
Table 2-2 Proposed Alternative Location of Air
Quality Monitoring
Table 2-3 Baseline Monitoring Stations - Air
Quality
Table 2-4 Baseline Monitoring Stations -
Construction Noise
Table 2-5 Baseline Monitoring Stations - Water
Quality
Table 2-6 Air Quality Monitoring Equipment
Table 2-7 Construction Noise Monitoring Equipment
Table 2-8 Water Quality Monitoring Equipment
Table 2-9 Derivation of Action and Limit Levels
for Air Quality
Table 2-10 Derivation of Action and Limit Levels for
Construction Noise
Table 2-11 Derivation of Action and Limit Levels for
Water Quality
Table 4-1 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM1
Table 4-2 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM2
Table 4-3 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM3
Table 4-4 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM4a
Table 4-5 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM5
Table 4-6 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM6
Table 4-7 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM7a
Table 4-8 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM8
Table 4-9 Summary of 24-hour and 1-hour TSP
Monitoring Results – AM9a
Table 4-10 Action and Limit Levels for Air Quality
Monitoring for all Stations
Table 4-11 Summaries of Noise Monitoring Results
Table 4-12 Action and Limit Levels of Construction
Noise Monitoring
Table 4-13 Summary of Water Quality Monitoring
Results - Dissolved Oxygen, mg/L
Table 4-14 Summary of Water Quality Monitoring
Results - Turbidity, NTU
Table 4-15 Summary of Water Quality Monitoring
Results – Suspended Solids, mg/L
Table 4-16 Action and Limit Levels for Water Quality
Monitoring
List
of Appendices
Appendix A Layout Plan of the Project
Appendix B Designated Monitoring Locations as
Recommended in the Approved EM&A Manual
Appendix C Sensitive Receivers Location for Baseline
Monitoring
Appendix D Valid Calibration Certificate of Monitoring
Equipment
Appendix E HOKLAS-accreditation Certificate of the
Testing Laboratory.
Appendix F Baseline Monitoring Schedules
Appendix G Meteorological Data during Baseline
Monitoring (Ta Kwu Ling Station)
Appendix H Monitoring Results Data of the air quality
(24-hour TSP), Noise and Water Quality
Appendix I Laboratory Data Report
1.1.1
Civil Engineering
and Development Department (hereafter referred as “CEDD”) is the Project
Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE)
Liantang / Heung Yuen Wai Boundary Control Point and Associated Works (hereinafter
referred as “the Project”), which is a Designated Project to be implemented
under Environmental Permit number EP-404/2011 (hereinafter
referred as “the EP-404/2011” or “the EP”).
1.1.2
The Project
consists of two main components: Construction of a Boundary Control Point (hereinafter referred as “BCP”); and Construction of a connecting road alignment. Layout
plan of the Project is shown in Appendix A.
1.1.3
The proposed BCP is
located at the boundary with Shenzhen near the existing Chuk Yuen Village,
comprising a main passenger building with passenger and cargo processing
facilities and the associated customs, transport and ancillary facilities. The connecting road alignment consists of six
main sections:
1)
Lin Ma Hang to
Frontier Closed Area (FCA) Boundary – this section comprises at-grade and
viaducts and includes the improvement works at Lin Ma Hang Road;
2)
Ping Yeung to Wo
Keng Shan – this section stretches from the Frontier Closed Area Boundary to
the tunnel portal at Cheung Shan and comprises at-grade and viaducts including
an interchange at Ping Yeung;
3)
North Tunnel – this
section comprises the tunnel segment at Cheung Shan and includes a ventilation
building at the portals on either end of the tunnel;
4)
Sha Tau Kok Road –
this section stretches from the tunnel portal at Wo Keng Shan to the tunnel
portal south of Loi Tung and comprises at-grade and viaducts including an
interchange at Sha Tau Kok and an administration building;
5)
South Tunnel – this
section comprises a tunnel segment that stretches from Loi Tung to Fanling and
includes a ventilation building at the portals on either end of the tunnel as
well as a ventilation building in the middle of the tunnel near Lau Shui Heung;
6)
Fanling – this
section comprises the at-grade, viaducts and interchange connection to the
existing Fanling Highway.
1.1.4
Action-United
Environmental Services & Consulting (hereinafter
referred as “AUES”) has been commissioned as an Independent Environmental Team
(hereinafter referred as “the ET”) to implement the relevant EM&A
program in accordance with the approved
EM&A Manual, as well as the associated duties. As part of the EM&A program,
baseline monitoring is required to determine the ambient environmental
conditions. Therefore, baseline
monitoring was carried out between 13
June 2013 and 12 July 2013 for
all parameters including air quality, noise and water quality before
construction work commencement.
1.1.5
14 consecutive days of air quality and noise
monitoring requirements had been undertaken at the all designated locations
from 13 June 2013 to 12 July 2013; also a 4-weeks water quality
monitoring had been carried out at eleven locations as designated in the
EM&A Manual from 14 June 2013 to
10 July 2013. During the baseline monitoring period, there
were no construction activities of this project or other external influencing
factors of significant concern observed by the ET.
1.1.6
This Baseline Monitoring Report presents the
details of the baseline study including project background, monitoring
methodology, monitoring results, summary of findings, and Action/Limit (A/L)
Levels established for subsequent use in the Project construction phase
EM&A program.
1.2.1
The Baseline Monitoring Report is structured
into the following sections:-
Section 1 Introduction
Section 2 Summaries of Baseline
Monitoring Requirement.
Section 3 Baseline Monitoring
Methodology
Section 4 Baseline Monitoring
Results
Section 5 Conclusion and
Recommendation
2.1.1
The Environmental Monitoring and Audit requirements are set out in
the Approved EM&A manual. Environmental issues such as air quality,
construction noise and water quality were identified as the key issues during
the construction phase of the Project.
2.1.2
This report presents the results obtained during the baseline
monitoring program of air, noise and steam/river water between 13 June 2013 and 12 July 2013. A summary of
the baseline EM&A requirements for air, noise and water monitoring are
presented in the sub-sections below.
2.2.1
The EM&A baseline monitoring program shall cover the following
environmental issues:
•
Air quality;
•
Construction noise; and
•
Water quality.
2.2.2
A summary of the monitoring parameters is presented in Table
2-1 below
Table 2-1 Summary of EM&A
Requirements
Environmental Issue |
Parameters |
Air
Quality |
1-hour TSP by Real-Time
Portable Dust Meter; and 24-hour TSP by High Volume
Air Sampler. |
Noise |
Leq (30min) in normal working
days (Monday to Saturday) 07:00-19:00 except public holiday; and 3 sets of consecutive Leq (5min)
on restricted hours i.e. 19:00 to 07:00 next day, and whole day of public
holiday or Sunday |
Water
Quality |
In-situ
Measurements Dissolved Oxygen
Concentration (mg/L); Dissolved Oxygen Saturation
(% ); Turbidity (NTU); pH unit; Water depth (m); and Temperature (℃). |
Laboratory Analysis Suspended Solids (mg/L) |
2.3.1
The designated monitoring locations as recommended in the EM&A Manual are shown in Appendix
B. As access to some of the
designated monitoring locations was questionable due to safety reason or denied
by the landlords, alternative locations have been proposed. The proposal of
alternative monitoring locations has been updated in the revised EM&A
Programme which verified by IEC and certified by ET prior submitted to EPD on
10 July 2013.
Air Quality
2.3.2
Baseline monitoring for air quality should be conducted at nine
air sensitive receivers (hereinafter referred as “ASR”) as designated in the
approved EM&A Manual. During site visit by the Contractor and ET, access to
three designated air monitoring locations namely AM4, AM7 and AM9 were denied
by the landlords of the ASR for HVS installation. Therefore, alternative
locations namely AM4a, AM7a and AM9a are proposed based on the following
criteria:
1)
At the site boundary or such locations close
to the major dust emission source;
2)
Close to the sensitive receptors;
3)
Take into account the prevailing
meteorological conditions;
4)
For monitoring location located in the vicinity
of the ASRs, care shall be taken to cause minimal disturbance to the occupants
during monitoring.
5)
When positioning the HVS, the following
points shall be
noted:
a.
a horizontal platform with appropriate
support to secure the samples against gusty wind shall be provided;
b.
no two samplers shall be placed less than 2m
apart;
c.
the distance between the HVS and an obstacle,
such as buildings, must be at least twice the height that the obstacle
protrudes above the HVS;
d.
a minimum of 2 m separation from walls, parapets and
penthouses is required for HVS at the rooftop;
e.
a minimum of 2 m separation from any supporting structure,
measures horizontally is required;
f.
no furnace or incinerator flue is nearby;
g.
airflow around the sampler is unrestricted;
h.
the HVS is more than 20 m from the dripline;
i.
any wire fence and gate to protect the HVS,
shall not cause any obstruction during monitoring;
j.
permission must be obtained to set up the HVS
and to obtain access to the monitoring stations; and
k.
a secured supply of electricity is needed to
operate the HVS.
2.3.3
The proposed alternative locations of air quality monitoring are
detailed in Table 2-2 below.
Table 2-2 Proposed Alternative
Location of Air Quality Monitoring
Station ID |
Location nearby the
Work Area |
Conclusion and Consideration during site visit |
AM4a |
LMH to Frontier Closed Area |
Alternative location is a village house located at about 160m east side of
the original point AM4 in figure
2.1. AM4a is recommended as it is the
closest residential location with secured electric access and covering the
construction work at east side. |
AM7a |
Sha Tau Kok Road |
Alternative location is the front yard of another
village (nameless) aligns to Sha Tau Kok Road – Wo Hang Section
proximity to Tai Tong Wu Village. AM7a is about 140m away from the original
point AM7 in figure 2.1 but it is more close
to the site area. AM7a is recommended
as it is located just at the front of the residential area with secured
electric access. It is more close to
the construction site than original point, i.e. more sensitive. |
AM9a |
Fanling |
Alternative location Nam Wa Po Village House No. 71 is located about 29m away from the original point AM9. AM9a is recommended as it is the closest residential
location with secured electric access and covering the construction work
area. |
2.3.4
The proposed alternative locations are considered capable of
effectively representing the baseline conditions at the impact monitoring
locations. The proposal on alternative
monitoring locations has been submitted to EPD upon agreement of the Engineer
and certification by the IEC as stated in previous Section 2.3.1.
2.3.5
Hence, the sensitive receivers conducted the baseline air
monitoring under the Project is listed in Table 2-3 and shown in Appendix
C.
Table 2-3 Baseline Monitoring
Stations - Air Quality
Station ID |
ASR ID in EM&A Manual |
Description |
Works Area |
AM1 |
TYH |
Tsung Yuen Ha Village House No. 63 |
BCP |
AM2 |
V1 |
Village House near Lin Ma Hang Road |
LMH to Frontier Closed Area |
AM3 |
TKL2 |
Ta Kwu Ling Fire Service Station of
Ta Kwu Ling Village. |
LMH to Frontier Closed Area |
AM4a |
KTW4 |
A village
house located at about 160m east side of the original point AM4 |
LMH to Frontier Closed Area |
AM5 |
PY1 |
Ping Yeung Village House |
Ping Yeung to Wo Keng Shan |
AM6 |
WKS7 |
Wo Keng Shan Village House |
Ping Yeung to Wo Keng Shan |
AM7a |
NA |
Another village
(nameless) aligns to Sha Tau Kok Road – Wo Hang Section
proximity to Tai Tong Wu Village. The location is about 140m away from the original point AM7 |
Sha Tau Kok Road |
AM8 |
PKT2 |
Po Kat Tsai Village No. 4 |
Po Kat Tsai |
AM9a |
NWP1 |
Nam Wa Po Village House No. 71 |
Fanling |
Construction
Noise
2.3.6
Ten noise sensitive receivers (hereinafter referred “the NSR”) are
designated to be the monitoring stations in the EM&A Manual. They are
listed in Table 2-4 and shown in Appendix C.
Table 2-4 Baseline Monitoring
Stations - Construction Noise
Station ID |
ASR ID in EM&A Manual |
Description |
Works Area |
NM1 |
TYH |
Tsung
Yuen Ha Village House No. 63 |
BCP |
NM2 |
V2 |
Village
House near Lin Ma Hang Road |
Lin Ma
Hang to Frontier Closed Area |
NM3 |
PY2 |
Ping
Yeung Village House (facade facing northeast) |
Ping
Yeung to Wo Keng Shan |
NM4 |
WKS6 |
Wo Keng
Shan Village House |
Ping
Yeung to Wo Keng Shan |
NM5 |
LT1 |
Village
House, Loi Tung |
Sha Tau
Kok Road |
NM6 |
TTW2 |
Tai Tong
Wu Village House 2 |
Sha Tau
Kok Rpad |
NM7 |
PKT2 |
Po Kat
Tsai Village |
Po Kat
Tsai |
NM8 |
TH1 |
Village
House, Tong Hang |
Fanling |
NM9 |
KT3 |
Village
House, Kiu Tau Village |
Fanling |
NM10 |
NWP1 |
Nam Wa
Po Village House No. 78 |
Fanling |
Water Quality
2.3.7
The water quality baseline monitoring should be conducted at
monitoring stations recommended in the EM&A Manual. Total eleven water quality monitoring
locations including control stations and impact stations were designated for
the Project.
2.3.8
Water
quality monitoring stations WM1-Control, WM2B and WM3 have been identified and
confirmed. However, access to other
monitoring stations is questionable due to safety reason. Alternative monitoring
locations are proposed according to the following criteria:
1)
at locations close to and preferably at the
boundary of the mixing zone of the major site activities as indicated in the
EIA report, which are likely to have water quality impacts;
2)
close to the sensitive receptors which are
directly or likely to be affected;
3)
for monitoring locations located in the
vicinity of the sensitive receptors, care should be taken to cause minimal
disturbance during monitoring;
4)
two or more control stations which should be
at locations representative of the project site in its undisturbed condition.
Control stations should be located, as far as is practicable, both upstream and
down-stream of the works area.
2.3.9
Moreover, control stations are necessary to compare the water
quality from potentially impacted sites with the ambient water quality. Control
stations shall be located within the same body of water as the impact
monitoring stations but shall be outside the area of influence of the works
and, as far as practicable, not affected by any other works.
2.3.10
The actual location (coordinate) was carried out baseline water
quality monitoring are listed in Table2-5 and shown in Appendix
C.
Table 2-5 Baseline Monitoring
Stations - Water Quality
Station ID |
Description |
Location Designated in EM&A Manual |
Proposed Location |
Nature of the location |
||
Coordinates |
Coordinates |
|||||
Easting |
Northing |
Easting |
Northing |
|||
WM1 |
Downstream of Kong
Yiu Channel |
833669 |
845371 |
833679 |
845421 |
upstream 51m |
WM1-Control |
Upstream of Kong
Yiu Channel |
834185 |
845917 |
834185 |
845917 |
NA |
WM2A |
Downstream of River
Ganges |
834132 |
844433 |
834204 |
844471 |
downstream 81m |
WM2A-Control |
Upstream of River
Ganges |
835205 |
844200 |
835270 |
844243 |
upstream 78m |
WM2B |
Downstream of River
Ganges |
835435 |
843395 |
835433 |
843397 |
NA |
WM2B-Control |
Upstream of River
Ganges |
835846 |
843344 |
835835 |
843351 |
downstream 31m |
WM3 |
Downstream of River
Indus |
836324 |
842405 |
836324 |
842407 |
NA |
WM3-Control |
Upstream of River
Indus |
836763 |
842426 |
836763 |
842400 |
downstream 26m |
WM4 |
Downstream of Ma
Wat Channel |
833841 |
838345 |
833850 |
838338 |
upstream 11m |
WM4–Control A |
Kau Lung Hang
Stream |
834039 |
837669 |
834028 |
837695 |
downstream 28m |
WM4–Control B |
Upstream of Ma Wat
Channel |
833769 |
837406 |
833760 |
837395 |
upstream 15m |
2.3.11
The water quality at
both original and alternative locations is not anticipated to have significant
difference. The proposal of alternative monitoring locations has been submitted
to EPD upon agreement of the RE and verified by the IEC as stated in previous
Section 2.3.1.
2.3.12
Since the changes of
water monitoring locations were not significant (less than 100m), Figure 4.1 of
the EM&A Manual would remain unchanged.
The
requirements of baseline monitoring are stipulated in Sections 2.1.5, 3.1.4 and
4.1.5 of the approved EM&A Manual
and presented as follows.
Air Quality Monitoring
2.4.1
Monitoring frequency for air quality
baseline monitoring is as follows:
1-Hour TSP |
3 sets of 1-Hour TSP monitoring shall be
carried out daily for a period of at least two weeks. |
24-Hour TSP |
Continuous monitoring of 24-Hour shall
be carried out daily for a period of at least two weeks. |
Noise Monitoring
2.4.2
The baseline noise monitoring shall be carried out daily for a
period of at least two weeks. The baseline noise levels for the time period
between 0700 and 1900 hours on normal weekdays will be measured in terms of Leq
(30 minutes). For all other time
periods, i.e. restricted time period (19:00 to 07:00 the next morning and whole
day on public holidays) (hereinafter referred as “the restricted hours”) will
not be included in the baseline monitoring as they do not carry significance
with the following rationales:
• Setting
A/L Levels for construction noise is not based on baseline noise levels at any
monitoring stations (refer to the following Section
3.6: Action/Limit
Levels and Event Action Plan); and
• No
construction activities are to be undertaken during the restricted hours, no
construction noise impacts related to the works under the Project are therefore
envisaged during the restricted hours.
Water Quality Monitoring
2.4.3
The baseline monitoring frequency shall be 3 days per week, for at
least 4 weeks prior to the commencement of construction works. The interval between two sets of monitoring
shall not be less than 36 hours.
Air Quality Monitoring
2.5.1
The 24-hour and 1-hour TSP levels shall be measured by following
the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. If the ET proposes to use a direct reading
dust meter to measure 1-hour TSP levels, it shall submit sufficient information
to the IEC to approve.
2.5.2
The filter paper
of 24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.
2.5.3
All equipment to be used for baseline air quality monitoring is
listed in Table 2-6.
Table 2-6 Air Quality Monitoring Equipment
Equipment |
Model |
24-Hr TSP |
|
High
Volume Air Sampler |
TISCH High Volume
Air Sampler, HVS Model TE-5170 |
Calibration
Kit |
TISCH Model
TE-5028A |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3 Laser
Dust monitor Particle Mass Profiler & Counter |
Wind
Data Monitoring Equipment
2.5.4
According to the approved EM&A Manual, wind data monitoring
equipment shall also be provided and set up for logging wind speed and wind
direction near the dust monitoring locations.
The equipment installation location shall be proposed by the ET and
agreed with the IEC. For installation
and operation of wind data monitoring equipment, the following points shall be
observed:
1)
The wind sensors should be installed 10 m above ground so that
they are clear of obstructions or turbulence caused by buildings.
2)
The wind data should be captured by a data logger. The data shall
be downloaded for analysis at least once a month.
3)
The wind data monitoring equipment should be re-calibrated at
least once every six months.
4)
Wind direction should be divided into 16 sectors of 22.5 degrees
each.
2.5.5
In order to do so, ET has liaised with the landlords of the
successful granted HVS installation premises.
However, the owners rejected to provide premises for wind data
monitoring equipment installation.
2.5.6
In under this situation, the ET proposed alternative methods to
obtain representative wind data.
Meteorological information as extracted from “the Hong Kong Observatory
Ta Kwu Ling Station” is alternative method to obtain representative wind
data. For Ta Kwu Ling Station, it is
located nearby the Project site.
Moreover, this station is situated the sea level above 15mPD. The station’s wind data monitoring equipment
is set above the existing ground ten meters in compliance with the general
setting up requirement. Furthermore,
this station also can be to provide the humidity, rainfall, and air pressure
and temperature etc. meteorological information. In Hong Kong of a lot development projects,
weather information extracted from Hong Kong Observatory is common alternative
method if weather station installation not allowed.
Noise Monitoring
2.5.7
Sound level meter in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring. The sound level meter shall be checked using
an acoustic calibrator. The wind speed
shall be checked with a portable wind speed meter capable of measuring the wind
speed in m s-1.
2.5.8
Noise monitoring equipment to be used for baseline monitoring is
listed in Table 2-7.
Table 2-7 Construction Noise Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
B&K
Type 2238 or Rion NL-14 |
Calibrator |
Rion
NC-73 / B&K Type 4231 |
Portable Wind Speed Indicator |
Testo
Anemometer |
2.5.9
Sound level meters listed above comply with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and
804: 1985 (Type 1) specifications, as recommended in TM issued under the
NCO. The acoustic calibrator and sound
level meter to be used in the baseline monitoring will be calibrated yearly..
Water Quality Monitoring
2.5.10
DO and water temperature should be
measured in-situ by a DO/temperature meter. The instrument should be portable
and weatherproof using a DC power source. It should have a membrane electrode
with automatic temperature compensation complete with a cable. The equipment
should be capable of measuring:
• a DO level in the range of 0-20
mg/l and 0-200% saturation; and
• a temperature of between 0 and
45 degree Celsius.
2.5.11
A portable pH meter capable of measuring a
range between 0.0 and 14.0 should be provided to measure pH under the specified
conditions accordingly to the APHA Standard Methods.
2.5.12
The instrument should be portable and
weatherproof using a DC power source. It should have a photoelectric sensor
capable of measuring turbidity between 0-1000 NTU.
2.5.13
A portable, battery-operated echo sounder or tape measure will be used
for the determination of water depth at each designated monitoring station as
appropriate.
2.5.14
A water sampler e.g. Kahlsico Water Sampler, which is a
transparent PVC cylinder with capacity not less than 2 litres, will be used for
water sampling if water depth over than 0.5m.
For sampling from very shallow water depths e.g. <0.5 m, water sample
collection will be directly from water surface below 100mm use sampling plastic
bottle to avoid inclusion of bottom sediment or humus. Moreover, Teflon/stainless steel bailer or
self-made sampling buckets maybe used for water sampling. The equipment used for sampling will be
depended the sampling location and depth situations.
2.5.15
Water samples for laboratory measurement of SS will be collected
in high density polythene bottles, packed in ice (cooled to 4 ºC without being
frozen), and delivered to the laboratory in the same day as the samples were
collected.
2.5.16
Analysis of suspended solids should be carried out in a HOKLAS or
other accredited laboratory. Water samples of about 1L should be collected at
the monitoring stations for carrying out the laboratory suspended solids
determination. The SS determination work
should start within 24 hours after collection of the water samples. The SS
analyses should follow the APHA Standard
Methods 2540D with Limit of Reporting of 2 mg/L.
2.5.17
Water quality monitoring equipment used in the baseline monitoring
is listed in Table 2-8. Suspended
solids (SS) analysis is carried out by a local HOKLAS-accredited laboratory,
namely ALS Technichem (HK) Pty Ltd.
Table 2-8 Water Quality Monitoring Equipment
Equipment |
Model |
Water Depth Detector |
Eagle
Sonar or tape measures |
Water
Sampler |
A
2-litre transparent PVC cylinder with latex cups at both ends or teflon/stainless
steel bailer or self-made sampling bucket |
Thermometer
& DO meter |
YSI 550A Handheld Dissolved Oxygen Instrument |
pH
meter |
The EcoSense ®
pH10A pen-style instrument |
Turbidimeter |
Hach 2100Q |
Sample
Container |
High
density polythene bottles (provided by laboratory) |
Storage Container |
‘Willow’ 33-liter plastic
cool box with Ice pad |
2.6.1
The baseline results form the basis for determining the environmental
acceptance criteria for the impact monitoring.
A summary of derivation of Action/Limit (A/L) Levels for air quality,
construction noise and water quality are shown in Table 2-9, 2-10
and 2-11 respectively.
Table 2-9 Derivation of Action and Limit Levels for Air Quality
Parameter |
Action Level |
Limit Level |
24-hour
TSP |
For
baseline level £ 200 mg/m3:
Action
level = (Baseline × 1.3 + Limit
level)/2 |
>
260 mg/m3 |
For
baseline level > 200 mg/m3: Action
level = Limit level |
||
1-hour
TSP |
For
baseline level £ 384 mg/m3:
Action
level = (Baseline × 1.3 + Limit
level)/2 |
>
500 mg/m3 |
For
baseline level > 384 mg/m3: Action
level = Limit level |
Table 2-10 Derivation
of Action and Limit Levels for Construction Noise
Time Period |
Action Level in dB(A) |
Limit Level in dB(A) |
0700-1900
hours on normal weekdays |
When one documented complaint
is received |
>
75* dB(A) |
Note: (*) Reduces to 70 dB(A) for
schools and 65 dB(A) during the school examination periods.
Table 2-11 Derivation of Action and Limit Levels for
Water Quality
Parameters |
Action |
Limit |
DO in mg/l |
5 percentile of baseline data |
4 mg/L or 1 percentile of baseline data |
SS in mg/l |
95 percentile of baseline data or 120% of upstream control station of the same day |
99 percentile of baseline data or 130% of upstream control station of the same day |
Turbidity in NTU |
95 percentile of baseline data or 120% of upstream control station of the same day |
99 percentile of baseline data or 130% of upstream control station of the same day |
Notes:
1.
For DO
measurement, non-compliance occurs when monitoring result is lower than the
limits.
2.
For SS and
turbidity, non-compliance of water quality results when monitoring results is
higher than the limits.
3.
All the
figures given in the table are used for reference only and the EPD may amend
the figures whenever necessary.
3.1.1
The baseline monitoring program of air, noise and water were
conducted between 13 June 2013 and 12 July 2013. During the baseline monitoring period,
there were no construction activities of this project or other external influencing
factors of significant concern observed by the ET.
3.2.1
Baseline air quality, noise and water quality monitoring has been
undertaken at the all monitoring stations between 13 June 2013 and 12 July
2013; also a 4-week baseline water quality monitoring program has been
carried out at eleven designated locations from 14 June 2013 to 10 July 2013. The detailed information of monitoring
stations to be referred to Tables 2-3, 2-4 and 2-5,
and the graphical plot of monitoring locations is shown in Appendix C in this
report.
3.3.1
All the monitoring equipment to be used in the EM&A program as
listed in Tables 2-6, 2-7 and 2-8 has been agreed with
the IEC prior to commencement of the baseline monitoring.
Air Quality
1-hour TSP
3.4.1
The 1-Hour TSP monitor, a Sibata LD-3 Laser Dust monitor Particle
Mass Profiler & Counter was used for baseline monitoring, which is a
portable, battery-operated laser photometer. The 1-hour TSP meter provides a
real time 1-hour TSP measurement based on 900 light scattering. The
1-hour TSP monitor consisted of the following:
a.
A pump to draw sample aerosol through the optic chamber where TSP
is measured;
b.
A sheath air system to isolate the aerosol in the chamber to keep
the optics clean for maximum reliability; and
c.
A built-in data logger compatible with Windows based program to
facilitate data collection, analysis and reporting.
3.4.2
The 1-hour TSP meter used is within the valid period, calibrated by
the manufacturer prior to purchasing. Zero response of the instrument was
checked before and after each monitoring event.
Operation of the 1-hour TSP meter was follow manufacturer’s Operation
and Service Manual. A valid calibration
certificate is attached in Appendix D.
24-hour TSP
3.4.3
The equipment used for 24-hour TSP measurement is a Tisch
Environmental, Inc. Model TE-5170 TSP high volume air sampling system, which
complied with EPA Code of Federal Regulation, Appendix B to Part 50. The High Volume Air Sampler (HVS) consists of
the following:
a.
An anodized aluminum shelter;
b.
A 8”x10” stainless steel filter holder;
c.
A blower motor assembly;
d.
A continuous flow/pressure recorder;
e.
A motor speed-voltage control/elapsed time indicator;
f.
A 7-day mechanical timer, and
g.
A power supply of 220v/50 hz
3.4.4
Prior of 24-hour TSP monitoring, the HVS was calibrated in
accordance with the manufacturer’s instruction using the NIST-certified
standard calibrator (Tisch Calibration Kit Model TE-5028A). The 24-hour TSP Monitoring using the HVS was
also processed in accordance with the manufacturer’s Operations Manual. A valid calibration certificate of the
calibration kit with the certificate of HVS calibrated is attached in Appendix
D.
3.4.5
24-hour TSP was collected by the ET on filters of HVS and
quantified by a local HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd
(ALS), upon receipt of the samples. The
ET keeps all the sampled 24-hour TSP filters in normal air conditioned room
conditions, i.e. 70% HR (Relative Humidity) and 25oC, for six months
prior to disposal.
Construction
Noise
3.4.6
Sound level meter listed above comply with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications, as recommended in Technical Memorandum (TM) issued under the
Noise Control Ordinance (NCO), which was used for baseline noise
monitoring. A valid of calibration
certificates including sound level meter and an acoustic were shown in Appendix
D.
3.4.7
The noise measurement was performed with the meter set to FAST
response and on the A-weighted equivalent continuous sound pressure level
(Leq). Leq(30min) in six
consecutive Leq(5 min) measurements were used as the monitoring parameter
throughout the baseline monitoring period.
3.4.8
During the baseline monitoring, the sound level meter was mounted
on a tripod at a height of about 1.2 m and placed at the monitoring locations
and oriented such that the microphone was pointed to the site with the
microphone facing perpendicular to the line of sight. The windshield was fitted
for the measurement. For the
baseline noise monitoring, all monitoring stations were conducted 1 m from the exterior of the
building façade.
3.4.9
Prior baseline noise measurement, the accuracy of the sound level
meter was checked using an acoustic calibrator generating a known sound
pressure level at a known frequency. The
calibration level from before and after the noise measurement agrees to within
1.0dB.
3.4.10
During the noise measurement, a portable wind speed meter was used
to check wind speed (m/s). For baseline
noise monitoring, no wind speed was exceeding 5m/s or gusts exceeding
10m/s. Also, noise measurement in time
was no fog and rain.
Water
Quality
3.4.11
Water quality monitoring was conducted at the eleven designated
locations. The sampling and in-situ measurement process are below:
Sampling
Procedure
3.4.12
A Digital Global Positioning System (GPS)
was used to identify the designated monitoring stations. Prior to water sampling, a portable,
battery-operated echo sounder or tape measure was used for the determination of
water depth at each station. At each
station, water samples were collected from 0.1m below water surface or water
surface to prevent the river bed sediment for stirring.
3.4.13
The sample container was rinsed with a portion of the water
sample. The water sample then was
transferred to the high-density polythene
bottles as provided by the laboratory, labeled with a unique sample
number and sealed with a screw cap.
3.4.14
Before commencement of the sampling, general information such as
the date and time of sampling and weather condition as well as the personnel
responsible for the monitoring were be recorded on the monitoring field data
sheet.
3.4.15
A ‘Willow’ 33-liter plastic cool box packed with ice was used to
preserve the collected water samples prior to arrival at the laboratory for
chemical determination. The water
temperature of the cool box was maintained at a temperature as close to 4℃ as
possible without being frozen. Samples
collected were delivered to the laboratory upon collection.
In-situ Measurement
3.4.16
YSI 550A Handheld Dissolved Oxygen Instrument was used for water in-situ measures,
which automates the measurements and data logging of temperature, dissolved
oxygen and dissolved oxygen saturation. Before each round of monitoring, the dissolved
oxygen probe was calibrated by the wet bulb method.
3.4.17
A portable EcoSense
® pH10A pen-style instrument was used for in-situ pH
measurement. The pH meter is capable of measuring pH in the range of 0 – 14 and
readable to 0.1. Standard buffer solutions of pH 7 and pH 10 are used for
calibration of the instrument before and after measurement.
3.4.18
A portable Hach 2100Q Turbidimeter was
used for in-situ turbidity measurement. The turbidity meter is capable of
measuring turbidity in the range of 0 – 1000 NTU. StablCal® Standards 10NTU and
100NTU are used for calibration of the instrument before and after
measurement.
3.4.19
The all in-situ measurement equipment was calibrated by HOKLAS
accredited laboratory of three month interval.
Valid certificates are shown in Appendix D.
Laboratory Analysis
3.4.20
All water samples were analyzed with Suspended Solids (SS) as
specified in the EM&A Manual by a
local HOKLAS-accredited testing laboratory (ALS Technichem (HK) Pty Ltd HOKLAS
registration no. 66). SS
analysis was
determined by the laboratory upon receipt of the water samples using APHA Standard Methods 2540D. HOKLAS-accreditation certificate of the
testing laboratory is provided in Appendix E. The SS determination is started
within 48 hours upon receipt,
which is well within the required maximum sample storage time of the parameter
of 7 days.
3.5.1
The baseline monitoring data were handled by the
ET’s in-house data
recording and management system.
3.5.2
The monitoring data recorded in the equipment were downloaded
directly from the equipment at the end of each monitoring day. The downloaded monitoring data were input
into a computerized database properly maintained by the ET. The laboratory results were input directly
into the computerized database and checked by personnel other than those who
input the data.
3.5.3
For monitoring parameters that require laboratory analysis, the
local laboratory shall follow the QA/QC requirements as set out under the
HOKLAS scheme for the relevant laboratory tests
4.1.1
The baseline monitoring schedules are presented in Appendix
F and the monitoring results are detailed in the following
sub-sections.
4.2.1
Baseline air quality monitoring was carried out form 13 June 2013 to 12 July 2013. The results
for 24-hour and 1-hour TSP are summarized in Tables 4-1 to 4-9. The 24-hour TSP data are shown in Appendix
G.
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM1
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
29-Jun-13 |
19 |
27-Jun-13 |
12:13 |
27 |
28 |
31 |
30-Jun-13 |
23 |
28-Jun-13 |
13:15 |
30 |
33 |
31 |
1-Jul-13 |
20 |
29-Jun-13 |
10:15 |
27 |
29 |
30 |
2-Jul-13 |
17 |
30-Jun-13 |
12:45 |
23 |
22 |
21 |
3-Jul-13 |
16 |
1-Jul-13 |
10:55 |
20 |
21 |
23 |
4-Jul-13 |
22 |
2-Jul-13 |
10:00 |
22 |
24 |
26 |
5-Jul-13 |
20 |
3-Jul-13 |
13:41 |
29 |
23 |
21 |
6-Jul-13 |
17 |
4-Jul-13 |
13:45 |
19 |
21 |
25 |
7-Jul-13 |
16 |
5-Jul-13 |
14:30 |
13 |
17 |
19 |
8-Jul-13 |
14 |
6-Jul-13 |
13:14 |
12 |
13 |
14 |
9-Jul-13 |
19 |
7-Jul-13 |
14:30 |
14 |
15 |
17 |
10-Jul-13 |
18 |
8-Jul-13 |
10:10 |
25 |
27 |
29 |
11-Jul-13 |
28 |
9-Jul-13 |
14:30 |
25 |
27 |
30 |
12-Jul-13 |
24 |
10-Jul-13 |
10:50 |
24 |
26 |
29 |
Average (Range) |
20 (14-28) |
Average (Range) |
23 (12-33) |
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM2
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
27-Jun-13 |
32 |
27-Jun-13 |
12:25 |
22 |
23 |
25 |
28-Jun-13 |
25 |
28-Jun-13 |
13:22 |
33 |
35 |
37 |
29-Jun-13 |
30 |
29-Jun-13 |
10:21 |
22 |
24 |
25 |
30-Jun-13 |
24 |
30-Jun-13 |
12:40 |
19 |
20 |
21 |
1-Jul-13 |
22 |
1-Jul-13 |
10:45 |
18 |
20 |
21 |
2-Jul-13 |
26 |
2-Jul-13 |
10:15 |
19 |
21 |
22 |
3-Jul-13 |
22 |
3-Jul-13 |
13:54 |
27 |
24 |
29 |
4-Jul-13 |
23 |
4-Jul-13 |
13:30 |
15 |
16 |
18 |
5-Jul-13 |
40 |
5-Jul-13 |
14:50 |
39 |
40 |
42 |
6-Jul-13 |
26 |
6-Jul-13 |
13:00 |
25 |
28 |
29 |
7-Jul-13 |
34 |
7-Jul-13 |
14:39 |
18 |
20 |
20 |
8-Jul-13 |
37 |
8-Jul-13 |
10:00 |
31 |
33 |
36 |
9-Jul-13 |
33 |
9-Jul-13 |
14:21 |
33 |
34 |
36 |
10-Jul-13 |
31 |
10-Jul-13 |
11:15 |
33 |
33 |
36 |
Average (Range) |
29 (22-40) |
Average (Range) |
27 (15-42) |
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM3
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
27-Jun-13 |
23 |
27-Jun-13 |
12:30 |
25 |
26 |
28 |
28-Jun-13 |
20 |
28-Jun-13 |
13:30 |
48 |
50 |
48 |
29-Jun-13 |
18 |
29-Jun-13 |
10:30 |
35 |
37 |
33 |
30-Jun-13 |
20 |
30-Jun-13 |
12:30 |
14 |
15 |
13 |
1-Jul-13 |
20 |
1-Jul-13 |
10:40 |
15 |
17 |
18 |
2-Jul-13 |
17 |
2-Jul-13 |
13:17 |
13 |
15 |
16 |
3-Jul-13 |
19 |
3-Jul-13 |
14:15 |
28 |
24 |
32 |
4-Jul-13 |
25 |
4-Jul-13 |
10:20 |
17 |
18 |
18 |
5-Jul-13 |
20 |
5-Jul-13 |
09:35 |
22 |
27 |
29 |
6-Jul-13 |
24 |
6-Jul-13 |
10:00 |
21 |
22 |
22 |
7-Jul-13 |
19 |
7-Jul-13 |
15:00 |
32 |
37 |
35 |
8-Jul-13 |
29 |
8-Jul-13 |
11:20 |
53 |
49 |
41 |
9-Jul-13 |
30 |
9-Jul-13 |
14:15 |
39 |
42 |
44 |
10-Jul-13 |
34 |
10-Jul-13 |
11:24 |
30 |
33 |
34 |
Average (Range) |
23 (17-34) |
Average (Range) |
29 (13-53) |
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM4a
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
13-Jun-13 |
23 |
13-Jun-13 |
10:50 |
35 |
35 |
34 |
14-Jun-13 |
22 |
14-Jun-13 |
12:12 |
33 |
33 |
36 |
15-Jun-13 |
20 |
15-Jun-13 |
11:00 |
33 |
33 |
35 |
16-Jun-13 |
21 |
16-Jun-13 |
10:00 |
20 |
21 |
22 |
17-Jun-13 |
22 |
17-Jun-13 |
10:22 |
22 |
25 |
31 |
18-Jun-13 |
24 |
18-Jun-13 |
10:30 |
13 |
14 |
14 |
19-Jun-13 |
33 |
19-Jun-13 |
10:15 |
26 |
27 |
28 |
20-Jun-13 |
37 |
20-Jun-13 |
13:04 |
33 |
36 |
37 |
21-Jun-13 |
39 |
21-Jun-13 |
13:30 |
13 |
16 |
16 |
22-Jun-13 |
29 |
22-Jun-13 |
10:00 |
18 |
19 |
19 |
23-Jun-13 |
30 |
23-Jun-13 |
10:45 |
19 |
20 |
22 |
24-Jun-13 |
26 |
24-Jun-13 |
10:55 |
20 |
29 |
22 |
25-Jun-13 |
30 |
25-Jun-13 |
11:27 |
39 |
42 |
45 |
26-Jun-13 |
26 |
26-Jun-13 |
09:45 |
20 |
22 |
24 |
Average (Range) |
27 (20-39) |
Average (Range) |
26 (13-45) |
Table 4-5 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM5
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
13-Jun-13 |
24 |
13-Jun-13 |
10:45 |
31 |
33 |
33 |
14-Jun-13 |
16 |
14-Jun-13 |
11:00 |
35 |
36 |
35 |
15-Jun-13 |
15 |
15-Jun-13 |
13:09 |
35 |
37 |
38 |
16-Jun-13 |
17 |
16-Jun-13 |
10:09 |
22 |
24 |
23 |
17-Jun-13 |
14 |
17-Jun-13 |
10:35 |
31 |
33 |
28 |
18-Jun-13 |
15 |
18-Jun-13 |
13:35 |
16 |
17 |
17 |
19-Jun-13 |
33 |
19-Jun-13 |
13:20 |
16 |
18 |
19 |
20-Jun-13 |
31 |
20-Jun-13 |
09:58 |
24 |
27 |
29 |
21-Jun-13 |
21 |
21-Jun-13 |
10:24 |
17 |
19 |
20 |
22-Jun-13 |
20 |
22-Jun-13 |
09:54 |
16 |
18 |
19 |
23-Jun-13 |
17 |
23-Jun-13 |
10:53 |
22 |
25 |
26 |
24-Jun-13 |
18 |
24-Jun-13 |
10:47 |
28 |
30 |
31 |
25-Jun-13 |
21 |
25-Jun-13 |
11:30 |
40 |
46 |
47 |
26-Jun-13 |
19 |
26-Jun-13 |
09:47 |
24 |
25 |
25 |
Average (Range) |
20 (14-33) |
Average (Range) |
27 (16-47) |
Table 4-6 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM6
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
13-Jun-13 |
24 |
13-Jun-13 |
13:12 |
32 |
32 |
34 |
14-Jun-13 |
23 |
14-Jun-13 |
10:45 |
29 |
29 |
30 |
15-Jun-13 |
23 |
15-Jun-13 |
11:20 |
33 |
34 |
36 |
16-Jun-13 |
25 |
16-Jun-13 |
13:30 |
22 |
24 |
25 |
17-Jun-13 |
37 |
17-Jun-13 |
10:57 |
29 |
35 |
33 |
18-Jun-13 |
27 |
18-Jun-13 |
13:28 |
16 |
17 |
19 |
19-Jun-13 |
39 |
19-Jun-13 |
13:15 |
25 |
26 |
28 |
20-Jun-13 |
37 |
20-Jun-13 |
12:57 |
38 |
40 |
42 |
21-Jun-13 |
22 |
21-Jun-13 |
13:09 |
26 |
28 |
30 |
22-Jun-13 |
21 |
22-Jun-13 |
09:40 |
31 |
33 |
35 |
23-Jun-13 |
20 |
23-Jun-13 |
11:12 |
20 |
23 |
26 |
24-Jun-13 |
21 |
24-Jun-13 |
10:29 |
25 |
26 |
27 |
25-Jun-13 |
39 |
25-Jun-13 |
11:05 |
35 |
38 |
40 |
26-Jun-13 |
32 |
26-Jun-13 |
10:00 |
26 |
27 |
29 |
Average (Range) |
28 (20-39) |
Average (Range) |
29 (16-42) |
Table 4-7 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM7a
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
13-Jun-13 |
46 |
13-Jun-13 |
13:27 |
35 |
37 |
35 |
14-Jun-13 |
55 |
14-Jun-13 |
13:00 |
30 |
31 |
33 |
15-Jun-13 |
43 |
15-Jun-13 |
11:34 |
33 |
33 |
35 |
16-Jun-13 |
36 |
16-Jun-13 |
13:15 |
17 |
18 |
19 |
17-Jun-13 |
38 |
17-Jun-13 |
11:16 |
31 |
42 |
34 |
18-Jun-13 |
41 |
18-Jun-13 |
10:15 |
18 |
19 |
21 |
19-Jun-13 |
34 |
19-Jun-13 |
09:55 |
56 |
58 |
58 |
20-Jun-13 |
36 |
20-Jun-13 |
09:45 |
54 |
56 |
59 |
21-Jun-13 |
38 |
21-Jun-13 |
09:51 |
33 |
35 |
38 |
22-Jun-13 |
33 |
22-Jun-13 |
09:24 |
48 |
52 |
52 |
23-Jun-13 |
34 |
23-Jun-13 |
11:30 |
34 |
38 |
39 |
24-Jun-13 |
41 |
24-Jun-13 |
10:12 |
30 |
32 |
33 |
25-Jun-13 |
38 |
25-Jun-13 |
10:58 |
36 |
40 |
42 |
26-Jun-13 |
40 |
26-Jun-13 |
10:09 |
43 |
45 |
46 |
Average (Range) |
40 (33-55) |
Average (Range) |
38 (17-59) |
Table 4-8 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM8
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
27-Jun-13 |
22 |
27-Jun-13 |
12:57 |
29 |
32 |
33 |
28-Jun-13 |
29 |
28-Jun-13 |
14:00 |
58 |
60 |
60 |
29-Jun-13 |
23 |
29-Jun-13 |
13:52 |
29 |
30 |
32 |
30-Jun-13 |
27 |
30-Jun-13 |
12:10 |
23 |
24 |
27 |
1-Jul-13 |
21 |
1-Jul-13 |
10:00 |
24 |
27 |
28 |
2-Jul-13 |
17 |
2-Jul-13 |
14:00 |
36 |
31 |
39 |
3-Jul-13 |
21 |
3-Jul-13 |
13:23 |
27 |
29 |
32 |
4-Jul-13 |
23 |
4-Jul-13 |
10:00 |
16 |
17 |
18 |
5-Jul-13 |
27 |
5-Jul-13 |
09:50 |
24 |
25 |
28 |
6-Jul-13 |
20 |
6-Jul-13 |
09:40 |
19 |
21 |
24 |
7-Jul-13 |
22 |
7-Jul-13 |
15:15 |
22 |
23 |
24 |
8-Jul-13 |
21 |
8-Jul-13 |
13:00 |
24 |
26 |
30 |
9-Jul-13 |
21 |
9-Jul-13 |
14:36 |
26 |
25 |
22 |
10-Jul-13 |
20 |
10-Jul-13 |
10:23 |
26 |
27 |
28 |
Average (Range) |
22 (17-29) |
Average (Range) |
29 (16-60) |
Table 4-9 Summary
of 24-hour and 1-hour TSP Monitoring Results – AM9a
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st Measurement |
2nd Measurement |
3rd Measurement |
||
13-Jun-13 |
55 |
13-Jun-13 |
10:30 |
29 |
29 |
30 |
14-Jun-13 |
45 |
14-Jun-13 |
09:15 |
35 |
35 |
35 |
15-Jun-13 |
35 |
15-Jun-13 |
13:52 |
33 |
35 |
36 |
16-Jun-13 |
36 |
16-Jun-13 |
09:30 |
16 |
17 |
18 |
17-Jun-13 |
28 |
17-Jun-13 |
09:41 |
31 |
37 |
33 |
18-Jun-13 |
24 |
18-Jun-13 |
10:00 |
36 |
29 |
31 |
19-Jun-13 |
20 |
19-Jun-13 |
09:30 |
33 |
36 |
37 |
20-Jun-13 |
23 |
20-Jun-13 |
10:00 |
35 |
36 |
38 |
21-Jun-13 |
42 |
21-Jun-13 |
09:30 |
29 |
31 |
26 |
22-Jun-13 |
21 |
22-Jun-13 |
09:00 |
33 |
30 |
34 |
23-Jun-13 |
22 |
23-Jun-13 |
12:00 |
24 |
27 |
21 |
24-Jun-13 |
27 |
24-Jun-13 |
10:00 |
26 |
29 |
30 |
25-Jun-13 |
43 |
25-Jun-13 |
10:45 |
65 |
67 |
69 |
26-Jun-13 |
38 |
26-Jun-13 |
10:15 |
30 |
32 |
36 |
Average (Range) |
33 (20-55) |
Average (Range) |
33 (16-69) |
4.2.2
The meteorological data during the baseline monitoring period are
summarized in Appendix H.
Action/Limit Levels for Air
Quality
4.2.3
Following the criteria shown in Table 2-9 of this report,
the proposed Action and Limit Levels for 24-hour and 1-hour TSP are listed in Table
4-10.
Table 4-10 Action
and Limit Levels for Air Quality Monitoring for all Stations
Monitoring
Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
AM1 |
265 |
143 |
500 |
260 |
AM2 |
268 |
149 |
500 |
260 |
AM3 |
269 |
145 |
500 |
260 |
AM4a |
267 |
148 |
500 |
260 |
AM5 |
268 |
143 |
500 |
260 |
AM6 |
269 |
148 |
500 |
260 |
AM7a |
275 |
156 |
500 |
260 |
AM8 |
269 |
144 |
500 |
260 |
AM9a |
271 |
151 |
500 |
260 |
Note: 1-hour
& 24-hour TSP Action Level = (Baseline × 1.3 + Limit level)/2
4.3.1
The baseline noise monitoring was undertaken form 13 June 2013 to 10 July 2013. The designated locations including NM3,
NM4, NM5, NM6, NM8, NM9 and NM10 is the first batch baseline noise monitoring,
those locations are commenced on 13 June 2013 and completed on 27 June
2013. Since whole daytime raining was on
15 June 2013, therefore no baseline noise measurement was undertaken at NM3,
NM4, NM5, NM6, NM8, NM9 and NM10 in accordance with the noise monitoring
criteria. The second batch baseline
monitoring for the other designated locations such as NM1, NM2 and NM7, was
commenced again on 27 June 2013 and
completed on 10 July 2013. The measurement data are shown
in Appendix
F and summarized in Table 4-11.
Table
4-11 Summaries of Noise Monitoring
Results
Monitoring
Station |
Normal day (Monday to
Saturday): Daytime 0700-1900, Leq(30min) |
Public Holiday or Sunday: Daytime 0700-1900, Leq(5min) |
||||
Mean |
Min |
Max |
Mean |
Min |
Max |
|
NM1 |
53 |
45 |
60 |
50 |
42 |
60 |
NM2 |
57 |
51 |
64 |
48 |
41 |
54 |
NM3 |
56 |
51 |
67 |
53 |
48 |
59 |
NM4 |
59 |
54 |
66 |
53 |
47 |
64 |
NM5 |
56 |
54 |
59 |
56 |
54 |
58 |
NM6 |
62 |
58 |
65 |
51 |
49 |
53 |
NM7 |
57 |
49 |
63 |
54 |
40 |
61 |
NM8 |
61 |
54 |
67 |
59 |
56 |
63 |
NM9 |
63 |
58 |
76 |
59 |
49 |
74 |
NM10 |
63 |
56 |
70 |
56 |
52 |
60 |
Note Figures refer to the
measurement recorded at the designated station during the entire baseline
period for general reference.
4.3.2
The baseline noise monitoring, sound pressure level exceeded the criteria
such as 75dB(A) normal daytime and 70dB(A) restricted hour is recorded at
monitoring station NM9 only. Review NM9
location, it is situated nearly train railway.
The train noise should impact the monitoring station.
Action/Limit Levels for Noise
4.3.3
The Action and Limit Levels for construction noise are illustrated
in Table
4-12.
Table 4-12 Action and Limit Levels of Construction
Noise Monitoring
Time Period |
Action Level |
Limit Level in dB(A) |
0700-1900 hours on normal
weekdays |
When one documented complaint is received |
> 75* dB(A) |
Note: *Reduces
to 70dB(A) for schools and 65dB(A) during the school examination periods.
4.4.1
The baseline water quality monitoring at eleven (11) designated
monitoring stations was performed a 4 weeks as between 14 June 2013 and 10 July
2013. The monitoring results
including Dissolved Oxygen, Turbidity,
Suspended Solids and pH at each designated monitoring station are
summarized in Tables 4-13 to 4-15. Detailed monitoring results including in-situ
measurements and laboratory analysis data are shown in Appendix H.
Table
4-13 Summary of Water Quality
Monitoring Results - Dissolved Oxygen, mg/L
Date |
Sampling
Location |
||||||||||
WM1 |
WM1-
Control |
WM2A |
WM2A-
Control |
WM2B |
WM2B-
Control |
WM3 |
WM3-
Control |
WM4 |
WM4-
Control A |
WM4-
Control B |
|
14-Jun-13 |
4.28 |
4.64 |
4.51 |
5.62 |
4.96 |
4.68 |
4.08 |
3.66 |
4.62 |
4.78 |
4.62 |
17-Jun-13 |
4.29 |
3.70 |
4.07 |
4.05 |
4.90 |
5.47 |
3.77 |
3.39 |
4.07 |
4.08 |
4.28 |
19-Jun-13 |
4.18 |
4.27 |
3.34 |
5.40 |
4.57 |
4.16 |
4.27 |
4.12 |
4.20 |
4.82 |
4.73 |
21-Jun-13 |
4.73 |
4.48 |
4.14 |
3.86 |
4.88 |
4.82 |
4.19 |
4.02 |
4.65 |
4.28 |
5.20 |
24-Jun-13 |
4.76 |
4.76 |
5.38 |
5.52 |
6.72 |
6.91 |
6.50 |
5.88 |
7.01 |
7.22 |
5.16 |
26-Jun-13 |
6.53 |
6.43 |
6.07 |
5.62 |
6.47 |
4.50 |
5.92 |
4.89 |
6.60 |
6.60 |
6.61 |
29-Jun-13 |
6.49 |
6.66 |
7.85 |
6.51 |
7.88 |
5.92 |
6.91 |
5.63 |
7.22 |
7.01 |
5.54 |
2-Jul-13 |
5.61 |
4.91 |
6.35 |
6.37 |
7.22 |
6.11 |
7.33 |
5.39 |
7.25 |
6.62 |
6.03 |
4-Jul-13 |
4.72 |
5.83 |
5.94 |
5.10 |
7.76 |
7.81 |
5.81 |
6.84 |
6.73 |
5.88 |
6.12 |
6-Jul-13 |
5.54 |
5.97 |
5.64 |
4.40 |
6.90 |
5.93 |
6.13 |
3.92 |
6.15 |
6.13 |
5.61 |
8-Jul-13 |
4.99 |
5.12 |
5.45 |
5.31 |
6.11 |
3.64 |
5.54 |
4.92 |
5.66 |
5.76 |
4.95 |
10-Jul-13 |
5.40 |
5.48 |
5.07 |
6.46 |
6.25 |
4.45 |
5.78 |
5.06 |
6.03 |
6.00 |
5.48 |
5%-ile |
4.23 |
4.01 |
3.74 |
3.96 |
4.74 |
3.92 |
3.94 |
3.54 |
4.14 |
4.19 |
4.46 |
1%-ile |
4.19 |
3.76 |
3.42 |
3.88 |
4.60 |
3.69 |
3.80 |
3.42 |
4.08 |
4.10 |
4.31 |
Average |
5.12 |
5.18 |
5.32 |
5.35 |
6.22 |
5.36 |
5.52 |
4.81 |
5.85 |
5.76 |
5.36 |
Min |
4.18 |
3.70 |
3.34 |
3.86 |
4.57 |
3.64 |
3.77 |
3.39 |
4.07 |
4.08 |
4.28 |
Max |
6.53 |
6.66 |
7.85 |
6.51 |
7.88 |
7.81 |
7.33 |
6.84 |
7.25 |
7.22 |
6.61 |
Table
4-14 Summary of Water Quality
Monitoring Results – Turbidity, NTU
Date |
Sampling
Location |
||||||||||
WM1 |
WM1-
Control |
WM2A |
WM2A-
Control |
WM2B |
WM2B-
Control |
WM3 |
WM3-
Control |
WM4 |
WM4-
Control A |
WM4-
Control B |
|
14-Jun-13 |
16.30 |
6.90 |
4.31 |
56.30 |
49.35 |
60.30 |
26.95 |
43.60 |
7.20 |
40.95 |
61.45 |
17-Jun-13 |
14.20 |
5.92 |
4.66 |
2.38 |
2.16 |
5.25 |
3.27 |
6.38 |
13.90 |
2.48 |
9.00 |
19-Jun-13 |
19.15 |
7.65 |
9.25 |
7.41 |
10.01 |
0.96 |
14.10 |
11.20 |
26.10 |
21.75 |
30.15 |
21-Jun-13 |
11.50 |
12.30 |
3.00 |
3.13 |
2.82 |
2.16 |
2.39 |
4.23 |
39.20 |
2.51 |
9.68 |
24-Jun-13 |
321.00 |
689.50 |
61.50 |
68.70 |
53.35 |
44.05 |
94.05 |
77.85 |
53.65 |
88.75 |
146.50 |
26-Jun-13 |
11.15 |
10.05 |
10.55 |
4.48 |
12.50 |
3.00 |
2.64 |
3.30 |
27.90 |
7.56 |
49.30 |
29-Jun-13 |
17.10 |
9.02 |
2.39 |
34.50 |
9.44 |
0.45 |
1.41 |
4.74 |
10.15 |
1.29 |
14.10 |
2-Jul-13 |
26.45 |
15.35 |
11.40 |
20.75 |
0.18 |
2.00 |
0.92 |
2.91 |
30.20 |
9.61 |
22.50 |
4-Jul-13 |
17.45 |
11.35 |
9.63 |
13.60 |
1.12 |
0.87 |
6.64 |
12.25 |
18.30 |
6.65 |
11.00 |
6-Jul-13 |
17.80 |
17.25 |
3.91 |
20.45 |
3.08 |
1.01 |
12.55 |
11.30 |
17.85 |
12.55 |
19.10 |
8-Jul-13 |
15.80 |
10.35 |
36.00 |
15.25 |
1.90 |
1.29 |
1.64 |
4.85 |
15.05 |
9.95 |
12.75 |
10-Jul-13 |
71.65 |
26.50 |
10.95 |
18.65 |
2.08 |
1.42 |
1.96 |
2.01 |
19.85 |
6.78 |
14.40 |
95%-ile |
51.3 |
22.3 |
24.9 |
28.3 |
11.4 |
4.2 |
13.4 |
11.8 |
35.2 |
17.6 |
40.7 |
99%-ile |
67.6 |
25.7 |
33.8 |
33.3 |
12.3 |
5.0 |
14.0 |
12.2 |
38.4 |
20.9 |
47.6 |
Average |
22.2 |
12.6 |
10.2 |
14.1 |
4.5 |
1.8 |
4.7 |
6.3 |
21.9 |
8.1 |
19.2 |
Min |
11.2 |
5.9 |
2.4 |
2.4 |
0.2 |
0.5 |
0.9 |
2.0 |
10.2 |
1.3 |
9.0 |
Max |
71.7 |
26.5 |
36.0 |
34.5 |
12.5 |
5.2 |
14.1 |
12.3 |
39.2 |
21.8 |
49.3 |
Remark: The shaded data
are considered as
abnormal under the influence of rainstorm.
Table
4-15 Summary of Water Quality
Monitoring Results – Suspended Solids, mg/L
Date |
Sampling
Location |
||||||||||
WM1 |
WM1-
Control |
WM2A |
WM2A-
Control |
WM2B |
WM2B-
Control |
WM3 |
WM3-
Control |
WM4 |
WM4-
Control A |
WM4-
Control B |
|
14-Jun-13 |
34.5 |
7.5 |
7.5 |
86.0 |
72.5 |
99.5 |
46.0 |
91.5 |
12.0 |
62.0 |
89.0 |
17-Jun-13 |
38.5 |
18.5 |
18.0 |
10.0 |
7.5 |
6.5 |
7.0 |
22.5 |
23.5 |
6.5 |
7.5 |
19-Jun-13 |
20.0 |
5.5 |
4.5 |
4.5 |
6.5 |
7.5 |
12.0 |
8.5 |
19.5 |
13.0 |
20.5 |
21-Jun-13 |
23.5 |
25.5 |
5.5 |
10.0 |
2.5 |
3.0 |
6.0 |
5.5 |
47.0 |
5.0 |
17.0 |
24-Jun-13 |
270.0 |
447.0 |
46.5 |
44.5 |
27.5 |
28.0 |
44.5 |
34.5 |
32.0 |
49.5 |
188.0 |
26-Jun-13 |
12.0 |
8.0 |
7.0 |
4.5 |
9.5 |
2.5 |
4.0 |
4.0 |
19.5 |
9.5 |
55.0 |
29-Jun-13 |
18.5 |
7.5 |
3.5 |
75.0 |
11.0 |
2.0 |
3.5 |
3.0 |
14.0 |
3.5 |
16.5 |
2-Jul-13 |
31.5 |
9.5 |
7.5 |
5.5 |
3.5 |
2.0 |
2.0 |
2.5 |
18.5 |
9.0 |
15.5 |
4-Jul-13 |
16.0 |
4.0 |
4.5 |
4.0 |
2.0 |
2.0 |
5.5 |
4.5 |
20.5 |
8.0 |
13.5 |
6-Jul-13 |
21.0 |
30.0 |
10.0 |
62.5 |
12.5 |
3.0 |
13.0 |
10.0 |
30.0 |
27.0 |
19.5 |
8-Jul-13 |
27.0 |
5.0 |
10.5 |
7.0 |
2.0 |
2.0 |
2.5 |
7.5 |
20.5 |
15.0 |
18.5 |
10-Jul-13 |
67.5 |
8.5 |
9.5 |
7.5 |
2.0 |
2.0 |
3.0 |
3.5 |
26.5 |
4.5 |
17.0 |
95%-ile |
54.5 |
28.0 |
14.6 |
69.4 |
11.8 |
7.1 |
12.6 |
16.9 |
39.4 |
21.6 |
39.5 |
99%-ile |
64.9 |
29.6 |
17.3 |
73.9 |
12.4 |
7.4 |
12.9 |
21.4 |
45.5 |
25.9 |
51.9 |
Average |
27.6 |
12.2 |
8.1 |
19.1 |
5.9 |
3.2 |
5.9 |
7.2 |
24.0 |
10.1 |
20.1 |
Min |
12.0 |
4.0 |
3.5 |
4.0 |
2.0 |
2.0 |
2.0 |
2.5 |
14.0 |
3.5 |
7.5 |
Max |
67.5 |
30.0 |
18.0 |
75.0 |
12.5 |
7.5 |
13.0 |
22.5 |
47.0 |
27.0 |
55.0 |
Remark: The shaded data
are considered as
abnormal under the influence of rainstorm.
4.4.2
Having reviewed on the monitoring
results during the baseline period, abnormally
high Turbidity and
SS results were found on 14 and 24 June
2013 in which Black Rainstorm Warning and severe rainstorm was hoisted
respectively. According to statistics, these “distant” results may indicate faulty
data, erroneous procedures, or areas where a certain theory might not be valid,
and should be treated as the “outliers” and excluded from statistical
calculation of the percentiles for establishment of the Action/ Limit Levels. In order to
set up a more stringent limit, these two days data would be discarded before
determining the Action/ Limit Level, i.e. when calculating the 95%-ile and
99%-ile of baseline data.
4.4.3
According to the EM&A Manual, EITHER the 95%-ile and 99%-ile of
baseline data OR the 120% and 130%
of upstream control station of the same day would trigger ‘Exceedance Actions’
of the Event and Action Plan. It is
important to point out that the Turbidity and SS data in both control and
impact stations may synchronic increase
significantly under rainy or typhoon
conditions, due to significant increase of the water flow in the monitoring
streams to stir up the sediment and significant increase of soil erosion
resulting in subsequent increase of Turbidity and SS brought by rain water to
the streams etc. In this situation, even
though the upstream SS and Turbidity levels indicate full compliance with the
120% and 130% criteria, the exceedances of Action and Limit levels will inevitably
trigger ‘Exceedance Actions’. It is
considered that the EM&A Manual poses extremely stringent ‘OR’ requirements for establishment of
environmental performance criteria for SS and turbidity especially during rainy
day.
4.4.4
It is therefore proposed that that the
‘OR’ requirement in the EM&A Manual
for Turbidity and
SS be relaxed to an ‘AND’ condition
as follows:
‘95%-ile of baseline data AND
120% of upstream control station of the same day’ and
‘99%-ile of baseline data AND
130% of upstream control station of the same day.’
4.4.5
Moreover, the baseline SS and turbidity
conditions at the monitoring locations may differ significantly during season
changes and the environmental performance criteria may need to be reviewed
regularly or even re-established if it is evident that the baseline conditions have
changed significantly. It is beneficial
to the project if the proposed ‘AND’
condition is adopted as the environmental performance criteria would also cater
to the season changes.
Action/Limit
Levels for Water Quality
4.4.6
The Action and Limit Levels for water quality are illustrated in Table
4-16. The proposed environmental
performance criteria are recommended according to Table 2-11 of this
report.
Table
4-16 Action and Limit Levels for
Water Quality Monitoring
Parameter |
Performance criteria |
Monitoring Location |
|||||
WM1 |
WM2A |
WM2B |
WM3 |
WM4 |
|||
DO (mg/L) |
Action Level |
(*)4.23 |
(**)4.00 |
(*)4.74 |
(**)4.00 |
(*)4.14 |
|
Limit Level |
(#)4.19 |
(**)4.00 |
(#)4.60 |
(**)4.00 |
(#)4.08 |
||
Turbidity (NTU) |
Action Level |
51.3 |
24.9 |
11.4 |
13.4 |
35.2 |
|
AND 120% of upstream control station of the
same day |
|||||||
Limit Level |
67.6 |
33.8 |
12.3 |
14.0 |
38.4 |
||
AND 130% of upstream control station of the same day |
|||||||
SS (mg/L) |
Action Level |
54.5 |
14.6 |
11.8 |
12.6 |
39.4 |
|
AND 120% of upstream control station of the same
day |
|||||||
Limit Level |
64.9 |
17.3 |
12.4 |
12.9 |
45.5 |
||
AND 130% of upstream control station of the same day |
|||||||
Remarks: (*) The Proposed
Action Level of Dissolved Oxygen is adopted to be used 5%-ile of baseline data (**) The
Proposed Action & Limit Level of Dissolved Oxygen is used 4mg/L (#) The
Proposed Limit Level of Dissolved Oxygen is adopted to be used 1%-ile of baseline data Notes: All the figures given in the table are used for reference only
and the EPD may amend the figures whenever it is considered necessary. |
|||||||
Air Quality
Possible Influence of Seasonal Changes
4.5.1
The baseline monitoring was conducted from 13 June 2013 to 12 July 2013
during typical Hong Kong wet seasons.
The baseline data so collected therefore represent the baseline air
quality of the wet season immediately prior to commencement of the
Project. They may not reflect the air
quality conditions of dry seasons in Hong Kong, which are normally
significantly different.
4.5.2
It is therefore recommended that the interpretation of the air
quality monitoring data should take into account the influence of the seasonal
changes, and the baseline conditions should be regularly reviewed, in
particular during seasonal changes.
Water Quality
Environmental
Performance Criteria of DO, SS, and turbidity
4.5.3
The baseline suspended solids (SS) and turbidity levels reflect
typical water quality at the monitoring locations during wet seasons (April to
October). The established environmental
performance criteria, i.e. Action & Limit Levels, are therefore applicable
to the Event and Action Plan in Hong Kong during rainy season immediately prior
to the commencement of the construction activities of the Project. Similarly, this applies to dissolved oxygen
(DO) which is influenced by the same seasonable changes as SS and turbidity.
5.1.1
The baseline monitoring program was carried out during the period
between 13 June 2013 and 12 July 2013 at the designated
monitoring locations by the ET according to the approved EM&A Manual. During the baseline monitoring, there were no
construction activities undertaken under this Project.
5.1.2
Based on the baseline monitoring results, the recommended
environmental performance criteria for air quality, construction noise and
water quality are summarized as follows:
Recommended Action & Limit Levels of Air Quality |
||||
Monitoring Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
AM1 |
265 |
143 |
500 |
260 |
AM2 |
268 |
149 |
500 |
260 |
AM3 |
269 |
145 |
500 |
260 |
AM4a |
267 |
148 |
500 |
260 |
AM5 |
268 |
143 |
500 |
260 |
AM6 |
269 |
148 |
500 |
260 |
AM7a |
275 |
156 |
500 |
260 |
AM8 |
269 |
144 |
500 |
260 |
AM9a |
271 |
151 |
500 |
260 |
Recommended Action &
Limit Levels of Construction Noise |
||
Monitoring Location |
Action Level |
Limit Level |
0700-1900 hours on normal weekdays |
||
NM1, NM2, NM3, NM4, NM5, NM6, NM7, NM8, NM9, NM10 |
When one
or more documented complaints are received |
75 dB(A) of Leq(30min) during normal hours from 0700 to 1900
hours on normal weekdays, reduced to 70 dB(A) of Leq(30min) for schools and 65 dB(A) during school
examination periods |
Recommended Action &
Limit Levels of Water Quality |
|||||||
Parameter |
Performance criteria |
Monitoring Location |
|||||
WM1 |
WM2A |
WM2B |
WM3 |
WM4 |
|||
DO (mg/L) |
Action Level |
(*)4.23 |
(**)4.00 |
(*)4.74 |
(**)4.00 |
(*)4.14 |
|
Limit Level |
(#)4.19 |
(**)4.00 |
(#)4.60 |
(**)4.00 |
(#)4.08 |
||
Turbidity (NTU) |
Action Level |
51.3 |
24.9 |
11.4 |
13.4 |
35.2 |
|
AND 120% of upstream control station of the
same day |
|||||||
Limit Level |
67.6 |
33.8 |
12.3 |
14.0 |
38.4 |
||
AND 130% of upstream control station of the same day |
|||||||
SS (mg/L) |
Action Level |
54.5 |
14.6 |
11.8 |
12.6 |
39.4 |
|
AND 120% of upstream control station of the same
day |
|||||||
Limit Level |
64.9 |
17.3 |
12.4 |
12.9 |
45.5 |
||
AND 130% of upstream control station of the same day |
|||||||
Remarks: (*) The Proposed
Action Level of Dissolved Oxygen is adopted to be used 5%-ile of baseline data (**) The
Proposed Action & Limit Level of Dissolved Oxygen is used 4mg/L (#) The
Proposed Limit Level of Dissolved Oxygen is adopted to be used 1%-ile of baseline data Notes: All the figures given in the table are used for reference only
and the EPD may amend the figures whenever it is considered necessary. |
|||||||
5.2.1
The baseline monitoring of air quality, noise and water quality was
conducted during typical wet season (April to October) in Hong Kong. It is important to note that influence of
seasonal changes should be taken into account when interpreting monitoring data
obtained during dry season. Review of
the baseline conditions may need to be conducted regularly, in particular
during seasonal changes. If the changes
in baseline conditions are evident, the environmental performance criteria
should be re-established by agreement of the ER and IEC and submitted for EPD
endorsement.
5.2.2
Due to the
Project Liantang/Heung Yuen Wai Boundary Control Point and Associated Works
will be divided several contracts and separated different time
commencement. Therefore, the all
designated stations i.e. air quality, construction noise and water quality
performed impact monitoring will depend on the construction to be undertaken
working areas.