|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00670/13 |
|
|
||
|
|
|
|
|
||
|
|
Agreement No. CE 45/2008
(CE) Liantang/Heung Yuen Wai Boundary Control Point
and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
Monthly Environmental Monitoring and Audit Report (No.10)
¡V May 2014 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Civil Engineering and Development Department (CEDD) |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
13
June 2014 |
TCS00670/13/600/R0184v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental Team Leader) |
Version |
Date |
Remarks |
1 |
11 June 2014 |
First
Submission |
2 |
13 June 2014 |
Amended
according to IEC¡¦s comments on 12 June 2014 |
|
|
|
executive summary
ES01
This is the 10th monthly EM&A report presenting the monitoring
results and inspection findings for the reporting period from 1 to 31 May 2014
(hereinafter ¡¥the Reporting Period¡¦).
Environmental
Monitoring and Audit Activities
ES02
The construction work for Contract 2 under
the Project was commenced on 19 May 2014 and monitoring work at relevant monitoring
location including 2 air quality and
3 noise have been activated in this Reporting
Period. Environmental monitoring
activities under the EM&A programme in the
Reporting Period are summarized in the following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Reporting Period |
|
Number of Monitoring
Locations to undertake |
Total Occasions |
||
Air Quality |
1-hour TSP |
6 |
90 |
24-hour TSP |
6 |
29 |
|
Construction Noise |
Leq(30min) Daytime |
8 |
39 |
Water Quality |
Water sampling |
5 |
13(*) |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and
Auditing |
Contract 2 |
2 |
Contract 3 |
4 |
||
Contract 5 |
4 |
(*) Monitoring day
Breach of Action and Limit (A/L) Levels
ES03
In the Reporting Period, no exceedance of air quality and construction noise was registered. However, ten (10) Limit Level exceedances for water quality monitoring were recorded. The summary of breach of environmental
performance is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
||
NOE Issued |
Investigation |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
- |
- |
24-hour TSP |
0 |
0 |
0 |
- |
- |
|
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
- |
- |
Water Quality |
DO |
0 |
0 |
0 |
- |
- |
Turbidity |
0 |
5 |
5 |
Not project
related |
NA |
|
SS |
0 |
5 |
5 |
Not project
related |
NA |
Environmental
Complaint
ES04
In this Reporting Period, no environmental
complaint was lodged for Contracts 3 and 5. However, one (1) environmental complaint
was received for Contract 2 on 16 May 2014 regarding direct discharge of muddy
water. Investigation report for the
complaint has completed and it reveals that no direct discharge of muddy water from
Contract 2 was found.
Notification of Summons and Successful Prosecutions
ES05
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
ES06
The construction work for Contract 2 under
the Project was commenced on 19 May 2014 and monitoring work at relevant monitoring
locations including 2 air quality and
3 noise have been activated in this Reporting
Period. The monitoring results of
these locations have incorporated in the report. Moreover, proposal for the change of air
quality monitoring location from AM7a to AM7b was submitted to EPD on 4 June 2014
after verified by the IEC and it has approved by the EPD (EPD¡¦s ref.: (7) in EP
2/N7/A/52 Pt.12 dated 9 Jun 2014).
ES07
In this Reporting Period, joint site inspection to evaluate the site
environmental performance at Contract 2 has been carried out by
the RE, IEC, ET and the Contractor on 23 and 30 May 2014. No
non-compliance was noted.
ES08
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
3 has been carried out by the RE, IEC, ET and the Contractor on 9, 14, 19 and 26 May 2014. No non-compliance was noted.
ES09
In the Reporting Period, joint site
inspection to evaluate the site environmental performance at Contract
5 has been carried out by the RE, IEC, ET and the Contractor on 8, 15, 22 and 29 May 2014. No non-compliance was noted.
Future Key Issues
ES10
Construction noise would
be a key environmental issue during construction work of the Project. Noise mitigation measures such as using
quiet plants should be implemented in accordance with the EM&A requirement.
ES11
During wet season, muddy
water or other water pollutants from sites surface flow to local stream such as
Kong Yiu Channel and Ma Wat Channel or public area will be
key environment issue. Water
quality mitigation measures to prevent surface runoff into nearby water bodies
or public areas should be fully implemented.
ES12
Special attention should
also be paid on the potential construction dust impact since most of the
construction sites are adjacent to villages. The Contractor should fully implement
the construction dust mitigation measures properly.
Table of Contents
2 Project
Organization and Construction progress
2.1 Construction
Contract Packaging
2.5 Summary of Environmental Submissions
3 Summary
of Impact Monitoring Requirements
3.4 Monitoring
Frequency and Period
3.8 Derivation
of Action/Limit (A/L) Levels
3.9 Data
Management and Data QA/QC Control
4.2 Air
Quality Monitoring Results in Reporting Month
5 Construction
Noise Monitoring
5.2 Noise
Monitoring Results in Reporting Month
6.2 Results
of Water Quality Monitoring
7.2 Records
of Waste Quantities
8.2 Findings
/ Deficiencies During the Reporting Month
9 Environmental
Complaint and Non-Compliance
9.1 Environmental
Complaint, Summons and Prosecution
10 Implementation
Status of Mitigation Measures
10.2 Tentative
Construction Activities in the Coming Month
10.3 Key
Issues for the Coming Month
11 Conclusions
and Recommendations
List
of TABLES
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Impact
Monitoring Stations - Air Quality
Table 3-3 Impact
Monitoring Stations - Construction Noise
Table 3-4 Impact
Monitoring Stations - Water Quality
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Construction
Noise Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action
and Limit Levels for Water Quality
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1a
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM7a
Table 4-5 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM8
Table 4-6 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Table 5-1 Summary
of Construction Noise Monitoring Results
Table 6-1 Summary
of Water Quality Monitoring Results for Contract 3
Table 6-2 Summary
of Water Quality Monitoring Results for Contract 5
Table 6-3 Breaches
of Water Quality Monitoring Criteria in Reporting Period
Table 7-1 Summary
of Quantities of Inert C&D Materials
Table 7-2 Summary
of Quantities of C&D Wastes
Table 8-1 Site
Observations for Contract 2
Table 8-2 Site
Observations for Contract 3
Table 8-3 Site
Observations for Contract 5
Table 9-1 Statistical
Summary of Environmental Complaints
Table 9-2 Statistical
Summary of Environmental Summons
Table 9-3 Statistical
Summary of Environmental Prosecution
Table 10-1 Environmental
Mitigation Measures
List of Appendices
Appendix
A Layout
Plan of the Project
Appendix
B Organization
Chart
Appendix
C Master
Construction Programme
Appendix
D Designated
Monitoring Locations as Recommended in the Approved EM&A Manual
Appendix
E Monitoring
Locations for Impact Monitoring
Appendix
F Calibration
Certificate of Monitoring Equipment and HOKLAS-accreditation Certificate of the
Testing Laboratory
Appendix
G Event
and Action Plan
Appendix
H Impact
Monitoring Schedule
Appendix
I Database
of Monitoring Result
Appendix
J Graphical
Plots for Monitoring Result
Appendix
K Meteorological
Data
Appendix
L Waste
Flow Table
Appendix
M Implementation
Schedule for Environmental Mitigation Measures
1.1.1
Civil Engineering and Development Department is the Project Proponent and the Permit Holder of Agreement No. CE 45/2008 (CE) Liantang / Heung Yuen Wai
Boundary Control Point and Associated Works, which is a
Designated Project to be implemented under Environmental Permit number EP-404/2011/A issued on 28 October
2013.
1.1.2
The Project consists of two main components: Construction of a Boundary
Control Point (hereinafter referred as ¡§BCP¡¨); and Construction of a connecting
road alignment. Layout plan of the Project is shown in Appendix A.
1.1.3
The proposed BCP is located at the boundary with Shenzhen near the
existing Chuk Yuen Village, comprising a main
passenger building with passenger and cargo processing facilities and the
associated customs, transport and ancillary facilities. The connecting road alignment consists
of six main sections:
1)
Lin Ma Hang to Frontier Closed Area (FCA) Boundary ¡V this section
comprises at-grade and viaducts and includes the improvement works at Lin Ma
Hang Road;
2)
Ping Yeung to Wo Keng
Shan ¡V this section stretches from the Frontier Closed Area Boundary to the
tunnel portal at Cheung Shan and comprises at-grade and viaducts including an
interchange at Ping Yeung;
3)
North Tunnel ¡V this section comprises the tunnel segment at Cheung Shan
and includes a ventilation building at the portals on either end of the tunnel;
4)
Sha Tau Kok Road ¡V this section stretches from the
tunnel portal at Wo Keng
Shan to the tunnel portal south of Loi Tung and
comprises at-grade and viaducts including an interchange at Sha
Tau Kok and an administration building;
5)
South Tunnel ¡V this section comprises a tunnel segment that stretches from
Loi Tung to Fanling and
includes a ventilation building at the portals on either end of the tunnel as
well as a ventilation building in the middle of the tunnel near Lau Shui Heung;
6)
Fanling ¡V this section comprises the at-grade, viaducts
and interchange connection to the existing Fanling
Highway.
1.1.4
Action-United
Environmental Services & Consulting has
been commissioned as an Independent ET to implement the relevant
EM&A program in accordance with the
approved EM&A Manual, as well as the associated duties. As part of the EM&A program, the
baseline monitoring has carried out between 13 June 2013 and 12 July
2013 for all parameters including air quality, noise and water quality
before construction work commencement.
The Baseline Monitoring Report summarized the key findings and the
rationale behind determining a set of Action and Limit Levels (A/L Levels) from
the baseline data. Also, the
Project baseline monitoring report which verified by the IEC has been submitted
to EPD on 16 July 2013 for endorsement. The major construction works of the
Project was commenced on 16 August 2013
in accordance with the EP Section 5.3 stipulation.
1.1.5
This is 10th
monthly EM&A report presenting the monitoring results and inspection
findings for reporting period from 1 to 31 May 2014.
1.2.1
The Monthly Environmental Monitoring and
Audit (EM&A) Report is structured into the following sections:-
Section 1 Introduction
Section 2 Project
Organization and Construction Progress
Section 3 Summary
of Impact Monitoring Requirements
Section 4 Air
Quality Monitoring
Section 5 Construction
Noise Monitoring
Section 6 Water
Quality Monitoring
Section 7 Waste
Management
Section 8 Site
Inspections
Section 9 Environmental
Complaints and Non-Compliance
Section 10 Implementation
Status of Mitigation Measures
Section 11 Conclusions
and Recommendations
2.1.1
To facilitate the project management and
implementation, the Project would be divided by the following contracts:
¡P
Contract 2 (CV/2012/08)
¡P
Contract 3 (CV/2012/09)
¡P
Contract 4 (TCSS)
¡P
Contract 5 (CV/2013/03)
¡P
Contract 6 (CV/2013/08)
2.1.2
The
details of each contracts is summarized below and the delineation of each contracts is shown in Appendix
A.
Contract 2 (CV/2012/08)
2.1.3
Contract 2 has awarded in December 2013 and
construction work was commenced on 19 May 2014. Major Scope of Work of the Contract 2 is
listed below:
¡P
construction of
an approximately 5.2km long dual two-lane connecting road (with about 0.4km of
at-grade road and 4.8km of tunnel) connecting the Fanling
Interchange with the proposed Sha Tau Kok Interchange;
¡P
construction of a
ventilation adit tunnel and the mid-ventilation
building;
¡P
construction of
the north and south portal buildings of the Lung Shan Tunnel and their
associated slope works;
¡P
provision and
installation of ventilation system, E&M works and building services works
for Lung Shan tunnel and Cheung Shan tunnel and their portal buildings;
¡P
construction of
Tunnel Administration Building adjacent to Wo Keng Shan Road and the associated E&M and building
services works; and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks,
landscaping works and other ancillary works.
Contract 3 (CV/2012/09)
2.1.4
Contract 3 was awarded in July 2013 and
construction work was commenced on 5 November 2013. Major Scope of Work of the Contract 3 is
listed below:
¡P
construction of four
link roads connecting the existing Fanling Highway
and the south portal of the Lung Shan Tunnel;
¡P
realignment of
the existing Tai Wo Service Road West and Tai Wo Service Road East;
¡P
widening of the
existing Fanling Highway (HyD¡¦s
entrustment works);
¡P
demolishing
existing Kiu Tau vehicular bridge and Kiu Tau footbridge and reconstruction of the existing Kiu Tau Footbridge (HyD¡¦s
entrustment works); and
¡P
construction of associated
footpath, slopes, retaining structures, drainage, sewerage, waterworks, landscaping
works and other ancillary works.
Contract 4 (Contract number to be
assigned)
2.1.5
Contract 4 has not yet been awarded. The work of the Contract 4 includes provision and installation of
Traffic Control and Surveillance System and the associated electrical and
mechanical works for the Project.
Contract 5 (CV/2013/03)
2.1.6
Contract 5 has awarded in April 2013 and construction
work was commenced in August 2013.
Major Scope of Work of the Contract 5 is listed below:
¡P
site formation of about 23
hectares of land for the development of the BCP;
¡P
construction of an
approximately 1.6 km long perimeter road at the BCP including a 175m long
depressed road;
¡P
associated
diversion/modification works at existing local roads and junctions including
Lin Ma Hang Road;
¡P
construction of pedestrian
subway linking the BCP to Lin Ma Hang Road;
¡P
provision of resite area with supporting infrastructure for reprovisioning of the affected village houses; and
¡P
construction of associated footpath, slopes, retaining structures, drainage,
sewerage, waterworks, landscaping works and other ancillary works.
Contract 6 (CV/2013/08)
2.1.7
Contract 6 is still yet awarded. Major Scope of Work of the Contract 6 would
be included below:
construction of an approximately 4.6km long dual two-lane connecting
road (with about 0.6km of at-grade road, 3.3km of viaduct and 0.7km of tunnel)
connecting the BCP with the proposed Sha Tau Kok Road Interchange and the associated ventilation
buildings;
associated diversion/modification works at access roads to the resite of Chuk Yuen Village;
provision of sewage collection, treatment and disposal facilities for
the BCP and the resite of Chuk
Yuen Village;
construction of a pedestrian subway linking the BCP to Lin Ma Hang
Road;
provisioning of the affected facilities including Wo
Keng Shan Road garden; and
construction of associated footpath, slopes, retaining
structures, drainage, sewerage, waterworks, landscaping works and other ancillary
works.
2.2.1
The project organization is shown in Appendix
B. The responsibilities of
respective parties are:
Civil
Engineering and Development Department (CEDD)
2.2.2
CEDD is the Project Proponent and the Permit Holder of the EP of the development
of the Project and will assume overall responsibility for the project. An
Independent Environmental Checker (IEC) shall be employed by CEDD to audit the
results of the EM&A works carried out by the ET.
Environmental
Protection Department (EPD)
2.2.3
EPD is the statutory enforcement body for
environmental protection matters in Hong Kong.
Engineer
or Engineers Representative (ER)
2.2.4
The ER is responsible for overseeing the
construction works and for ensuring that the works are undertaken by the Contractor
in accordance with the specification and contract requirements. The duties and
responsibilities of the ER with respect to EM&A are:
¡P
Monitor the Contractors¡¦ compliance with
contract specifications, including the implementation and operation of the
environmental mitigation measures and their effectiveness
¡P
Monitor Contractors¡¦s,
ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental Permit
(EP) and EM&A Manual
¡P
Facilitate ET¡¦s implementation of the
EM&A programme
¡P
Participate in joint site inspection by the
ET and IEC
¡P
Oversee the implementation of the agreed
Event / Action Plan in the event of any exceedance
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with DSD, Engineer/Engineer¡¦s
Representative, ET, IEC and the Contractor of the ¡§Construction of the DSD¡¦s Regulaiton of Shenzhen River Stage 4 (RSR 4)¡¨ Project
discussing regarding the cumulative impact issues.
The
Contractor(s)
2.2.5
There will be one contractor for each
individual works contract. The
Contractor(s) should report to the ER.
The duties and responsibilities of the Contractor are:
¡P
Comply with the relevant contract conditions
and specifications on environmental protection
¡P
Employ an Environmental Team (ET) to
undertake monitoring, laboratory analysis and reporting of EM &A Facilitate
ET¡¦s monitoring and site inspection activities
¡P
Participate in the site inspections by the ET
and IEC, and undertake any corrective actions
¡P
Provide information / advice to the ET
regarding works programme and activities which may
contribute to the generation of adverse environmental impacts
¡P
Submit proposals on mitigation measures in
case of exceedances of Action and Limit levels in
accordance with the Event / Action Plans
¡P
Implement measures to reduce impact where
Action and Limit levels are exceeded
¡P
Adhere to the procedures for carrying out
complaint investigation
Environmental Team (ET)
2.2.6
One ET will be employed for this
Project. The ET shall not be in any
way an associated body of the Contractor(s), and shall be employed by the
Project Proponent/Contractor to conduct the EM&A programme.
The ET should be managed by the ET
Leader. The ET Leader shall be a person who has at least 7 years¡¦ experience in
EM&A and has relevant professional qualifications. Suitably qualified staff
should be included in the ET, and resources for the implementation of the
EM&A programme should be allocated in time under
the Contract(s), to enable fulfillment of the Project¡¦s EM&A requirements
as specified in the EM&A Manual during construction of the Project. The ET shall report to the Project
Proponent and the duties shall include:
¡P
Monitor and audit various environmental
parameters as required in this EM&A Manual
¡P
Analyse the
environmental monitoring and audit data, review the success of EM&A programme and the adequacy of mitigation measures
implemented, confirm the validity of the EIA predictions and identify any
adverse environmental impacts arising
¡P
Carry out regular site inspection to
investigate and audit the Contractors¡¦ site practice, equipment/plant and work
methodologies with respect to pollution control and environmental mitigation,
and effect proactive action to pre-empt problems
¡P
Monitor compliance with conditions in the EP,
environmental protection, pollution prevention and control regulations and
contract specifications
¡P
Audit environmental conditions on site
¡P
Report on the environmental monitoring and
audit results to EPD, the ER, the lEC and Contractor(s) or their delegated representatives
¡P
Recommend suitable mitigation measures to the
Contractor in the case of exceedance of Action and
Limit levels in accordance with the Event and Action Plans
¡P
Liaise with the IEC on all environmental
performance matters and timely submit all relevant EM&A proforma
for approval by IEC
¡P
Advise the Contractor(s) on environmental
improvement, awareness, enhancement measures etc., on site
¡P
Adhere to the procedures for carrying out
complaint investigation
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, ET, lEC and the
Contractor(s) of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
Independent Environmental Checker (IEC)
2.2.7
One IEC will be employed for this
Project. The Independent
Environmental Checker (IEC) should not be in any way an associated body of the
Contractor(s) or the ET for the Project.
The IEC should be employed by the Permit Holder (i.e., CEDD) prior to the commencement of the construction
of the Project. The IEC should have
at least 10 years¡¦ experience in EM&A and have relevant professional
qualifications. The duty of IEC
should be:
¡P
Provide proactive advice to the ER and the
Project Proponent on EM&A matters related to the project, independent from
the management of construction works, but empowered to audit the environmental
performance of construction
¡P
Review and audit all aspects of the EM&A programme implemented by the ET
¡P
Review and verify the monitoring data and all
submissions in connection with the EP and EM&A Manual submitted by the ET
¡P
Arrange and conduct regular, at least monthly
site inspections of the works during construction phase, and ad hoc inspections
if significant environmental problems are identified
¡P
Check compliance with the agreed Event /
Action Plan in the event of any exceedance
¡P
Check compliance with the procedures for
carrying out complaint investigation
¡P
Check the effectiveness of corrective
measures
¡P
Feedback audit results to ET by signing off
relevant EM&A proforma
¡P
Check that the mitigation measures are
effectively implemented
¡P
Report the works conducted, the findings,
recommendation and improvement of the site inspections, after reviewing ET¡¦s
and Contractor¡¦s works, and advices to the ER and Project Proponent on a
monthly basis
¡P
Liaison with the client departments,
Engineer/Engineer¡¦s Representative, ET, lEC and the
Contractor(s) of the concurrent projects as listed under Section 2.3 below
regarding the cumulative impact issues.
2.3.1
The concurrent construction works that may be
carried out include, but not limited to, the following:
(a)
Regulation of Shenzhen River Stage IV
(Environmental Permit EP-430/2011);
(b)
Building works and road works by contractors
of Architectural Services Department (ArchSD)
(Environmental Permit EP-404/2011/A);
(c)
Widening of Fanling
Highway ¡V Tai Hang to Wo Hop
Shek Interchange ¡V Contract No. HY/2012/06;
(d)
Construction of cross-boundary vehicular and
pedestrian bridges (total 5 numbers) across the Shenzhen River; and
(e)
Construction of BCP
facilities in Shenzhen.
2.4.1
In the Reporting Period, the major
construction activity conducted under the Project is located in Contracts 2, 3
and 5 and they are summarized in below.
Moreover, the master construction program of the Contracts 2, 3 and 5 is
enclosed in Appendix C.
Contract 2 (CV/2012/08)
The
contract commenced in May 2014. In this Reporting Period, construction
activities conducted are listed below:
Project wide ¡V Decontamination of Structures
with Asbestos
Project wide ¡V Minor Structures Demolition
Project wide ¡V Minor Structures Demolition
Project wide ¡V Asbestos Inspection (Phase 3)
SA01 ¡V Erection of Project Office
North Portal ¡V Excavation Works
North Portal ¡V Temporary Access Road
Mid Vent Portal ¡V Soil Nails Installation
Mid Vent Portal ¡V Excavation Works
Mid Vent Portal ¡V Erection of Workshop
South Portal ¡V Instrumentation and Monitoring
Works for Temporary Steel Bridge Construction
South Portal ¡V Instrumentation and Monitoring
Works for Temporary Steel Bridge Construction
South Portal ¡V Bridge Construction
South Portal ¡V Mini Piling Works
South Portal ¡V Instrumentation and Monitoring
Works for Temporary Steel Bridge Construction
Temporary Bridge - Trial Pit for Water Mains
Inspection
Site Office and Workshop Containers
Installation at CR6A
Hoarding and Fencing
Minor Structures Demolition
Road Improvement at Lau Shui
Heung Road
Removal of Boulders
Contract 3 (CV/2012/09)
The Contract
commenced in November 2013. In this
Reporting Period, construction activities conducted are listed below:
Cable detection and trial trenches
Tree Felling Works
Pre-drilling works and piling works
Bored pile and bored pile wall construction
Construction of haul road and temporary soil
platform for geotechnical works
Slope upgrading works
Noise barrier installation
Waterworks
Mini pile construction
Contract 4 (Contract number to be assigned)
The
contract has not yet been awarded.
Contract 5 (CV/2013/03)
The Contract
awarded in April 2013 and commenced on August 2013. In this Reporting Period, construction
activities conducted are listed below:
Construction
of Western pedestrian subway at Lin Ma Hang
Construction
of Eastern pedestrian subway and pump room at Lin Ma Hang
Western
lift shaft¡¦s construction
Pile cap
construction works at Bridge J
Construction
of retaining wall No.1
Drainage
works at Lin Ma Hang Road
Water
works at Lin Ma Hang Road
Transplantation,
Pruning/felling of existing tree
Formation
Works at BCP Area
Contract 6 (CV/2013/08)
The
contract has not yet been awarded
2.5.1
In according to the EP, the required documents
have submitted to EPD for retention which listed in below:
Project Layout Plans of Contracts 2, 3 and 5
Landscape Plan
Topsoil Management Plan
Environmental Monitoring and Audit Programme
Baseline Monitoring Report (TCS00690/13/600/R0030v3) for the Project
Waste Management Plan of the Contracts 3 and
5
Contamination Assessment Plan (CAP) for Po
Kat Tsai, Loi Tung and the workshops in Fanling
Vegetation Survey Report
2.5.2
Summary of
the relevant permits, licenses, and/or notifications on environmental
protection for the Project of each contracts are presented in Table 2-1.
Table 2-1 Status of Environmental
Licenses and Permits of the Contracts
Item |
Description |
License/Permit
Status |
|
Contract 2 |
|||
1 |
Air
pollution Control (Construction Dust) Regulation |
Ref No.: 368864 |
31 Dec 2013 |
2 |
Chemical Waste Producer Registration |
North Portal Waste
Producers Number: No. 5213-652-D2523-01 Mid-Vent Portal Waste
Producers Number: No. 5213-634-D2524-01 South Portal Waste
Producers Number: No. 5213-634-D2526-01 |
Valid from 25 Mar 2014 Valid from 25 Mar 2014 Valid from 9 Apr 2014 |
3 |
Water Pollution Control Ordinance - Discharge License |
No.WT00018374-2014 |
Valid from 3 Mar 2014 to 28 Feb 2019 |
No.: W5/1I389 |
Valid from 28 Mar 2014 to 31 Mar 2019 |
||
No.: W5/1I390 |
Valid from 24 Mar 2014 to 31 Mar 2019 |
||
No.: W5/1I391 |
Valid from 28 Mar 2014 to 31 Mar 2019 |
||
No.: W5/1I392 |
Valid from 28 Mar 2014 to 31 Mar 2019 |
||
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Acc no. 7019105 |
Valid from 8 Jan 2014 |
5 |
Construction Noise Permit |
GW-RN0268-14 GW-RN0244-14 GW-RN0303-14 |
Valid 24 Apr 2014- 22 Oct 2014 Valid 1 May 2014- 30 Oct 2014 Valid 21 May 2014 ¡V 6 Nov 2014 |
Contract 3 |
|||
1 |
Air
pollution Control (Construction Dust) Regulation |
Ref. No: 362101 |
Notification received by EPD
on 17 Jul 2013 |
2 |
Chemical Waste Producer Registration |
Waste Producers Number: No.:5113-634-C3817-01 |
Valid
form 7 Oct 2013 till the end of Contract |
3 |
Water Pollution Control Ordinance - Discharge License |
No.:WT00016832 ¡V 2013 |
Valid
from 28 Aug 13 to 31 Aug 2018 |
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7017914 |
Valid
form 2 Aug 13 till the end of Contract |
5 |
Construction Noise Permit |
GW-RN0109-14 |
Valid on 24 Feb 2014 till 17 May
2014 |
GW-RN0136-14 |
Valid on 4 Mar 2014 till 22 Jun 2014 |
||
Contract 5 |
|||
1 |
Air
pollution Control (Construction Dust) Regulation |
Ref. No: 359338 |
Notified EPD on 13 May 2013 |
2 |
Chemical Waste Producer Registration |
Waste Producers Number No.:
5213-642-S3735-01 |
Valid form 8 Jun 2013 till
the end of Contract |
3 |
Water Pollution Control Ordinance - Discharge License |
No.: W5/1G44/1 |
Valid from 8 Jun 13 to 30
Jun 2018 |
4 |
Waste Disposal Regulation - Billing Account for
Disposal of Construction Waste |
Account No. 7017351 |
Valid form 29 Apr 13 till
the end of Contract |
5 |
Construction Noise Permit |
NA |
NA |
3.1.1
The Environmental Monitoring and Audit
requirements are set out in the Approved EM&A manual. Environmental issues
such as air quality, construction noise and water quality were identified as
the key issues during the construction phase of the Project.
3.1.2
A summary of construction phase EM&A
requirements are presented in the
sub-sections below.
3.2.1
The EM&A program of construction phase
monitoring shall cover the following environmental issues:
•
Air quality;
•
Construction noise; and
•
Water quality
3.2.2
A summary of the monitoring parameters is
presented in Table 3-1.
Table 3-1 Summary
of EM&A Requirements
Environmental Issue |
Parameters |
Air Quality |
1-hour
TSP by Real-Time Portable Dust Meter; and 24-hour
TSP by High Volume Air Sampler. |
Noise |
Leq(30min) in
normal working days (Monday to Saturday) 07:00-19:00 except public holiday;
and 3 sets
of consecutive Leq(5min) on restricted
hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday Supplementary
information for data auditing, statistical results such as L10 and
L90 shall also be obtained for reference. |
Water Quality |
In-situ Measurements Dissolved
Oxygen Concentration (mg/L); Dissolved
Oxygen Saturation (% ); Turbidity
(NTU); pH unit; Water
depth (m); and Temperature
(¢J). |
Laboratory Analysis
Suspended
Solids (mg/L) |
3.3.1
The designated monitoring locations as
recommended in the EM&A Manual
are shown in Appendix D. As the access to some of the designated
monitoring locations was questionable due to safety reason or denied by the
landlords, alternative locations therefore have had proposed. The proposed
alternative monitoring locations has updated in the revised EM&A Programme which verified by IEC and certified by ET Leader
prior submitted to EPD on 10 July 2013. Table 3-2, Table 3-3 and Table
3-4 are respectively listed the air quality, construction noise and
water quality monitoring locations for the Project and a map showing these
monitoring stations is presented in Appendix
E.
Table 3-2 Impact
Monitoring Stations - Air Quality
Station ID |
Description |
Works Area |
Related to the Work Contract |
AM1a* |
Garden Farm, Tsung Yuen Ha Village |
BCP |
Contract 5 |
AM2 |
Village House
near Lin Ma Hang Road |
LMH to Frontier
Closed Area |
Contract 5, Contract 6 |
AM3 |
Ta Kwu Ling Fire Service Station of Ta Kwu
Ling Village. |
LMH to Frontier
Closed Area |
Contract 5, Contract 6 |
AM4a |
A village house located at about
160m east side of the original point AM4 |
LMH to Frontier
Closed Area |
Contract 6 |
AM5 |
Ping Yeung
Village House |
Ping Yeung to Wo Keng Shan |
Contract 6 |
AM6 |
Wo Keng Shan Village House |
Ping Yeung to Wo Keng Shan |
Contract 6 |
AM7b@ |
Loi Tung Village House |
Sha Tau Kok Road |
Contract 2 |
AM8 |
Po Kat Tsai
Village No. 4 |
Po Kat Tsai |
Contract 2 |
AM9b# |
Nam Wa Po Village House No. 80 |
Fanling |
Contract 3 |
# Proposal for the change of air quality monitoring location from AM9a
to AM9b was submitted to EPD on 4 Nov 2013 after verified by the IEC and it was
approved by EPD (EPD¡¦s ref.: (15) in EP 2/N7/A/52 Pt.10 dated 8 Nov 2013).
* Proposal for the change of air quality monitoring location from AM1to
AM1a was submitted to EPD on 24 March 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (6) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
@ Proposal for the change of air quality monitoring location from AM7ato
AM1b was submitted to EPD on 4 June 2014 after verified by the IEC. It was
approved by EPD (EPD¡¦s ref.: (7) in EP 2/N7/A/52 Pt.12 dated 9 Jun 2014).
Table 3-3 Impact
Monitoring Stations - Construction Noise
Station ID |
Description |
Works Area |
Related to the Work Contract |
NM1 |
Tsung Yuen Ha Village House No. 63 |
BCP |
Contract 5 |
NM2 |
Village House near Lin Ma Hang
Road |
Lin Ma Hang to Frontier Closed
Area |
Contract 5, Contract 6 |
NM3 |
Ping Yeung Village House (facade
facing northeast) |
Ping Yeung to Wo
Keng Shan |
Contract 6 |
NM4 |
Wo Keng Shan Village House |
Ping Yeung to Wo
Keng Shan |
Contract 6 |
NM5 |
Village House, Loi
Tung |
Sha Tau Kok Road |
Contract 2, Contract 6 |
NM6 |
Tai Tong Wu Village House 2 |
Sha Tau Kok Rpad |
Contract 2, Contract 6 |
NM7 |
Po Kat Tsai Village |
Po Kat Tsai |
Contract 2 |
NM8 |
Village House, Tong Hang |
Fanling |
Contract 2 Contract 3 |
NM9 |
Village House, Kiu
Tau Village |
Fanling |
Contract 3 |
NM10 |
Nam Wa
Po Village House No. 80 |
Fanling |
Contract 3 |
Table 3-4 Impact
Monitoring Stations - Water Quality
Station ID |
Description |
Coordinates of Designated / Alternative Location |
Nature of the location |
Related to the Work Contract |
|
WM1 |
Downstream of Kong Yiu Channel |
833679 |
845421 |
Alternative location located at upstream 51m of the designated location |
Contract 5 |
WM1-Control |
Upstream of Kong Yiu Channel |
834185 |
845917 |
NA |
Contract 5 |
WM2A |
Downstream of River Ganges |
834204 |
844471 |
Alternative location located at downstream 81m of the designated
location |
Contract 6 |
WM2A-Control |
Upstream of River Ganges |
835270 |
844243 |
Alternative location located at upstream 78m of the designated location |
Contract 6 |
WM2B |
Downstream of River Ganges |
835433 |
843397 |
NA |
Contract 6 |
WM2B-Control |
Upstream of River Ganges |
835835 |
843351 |
Alternative location located at downstream 31m of the designated
location |
Contract 6 |
WM3 |
Downstream of River Indus |
836324 |
842407 |
NA |
Contract 6 |
WM3-Control |
Upstream of River Indus |
836763 |
842400 |
Alternative location located at downstream 26m of the designated
location |
Contract 6 |
WM4 |
Downstream of Ma Wat Channel |
833850 |
838338 |
Alternative location located at upstream 11m of the designated location |
Contract 3 |
WM4¡VControl A |
Kau Lung Hang
Stream |
834028 |
837695 |
Alternative location located at downstream 28m of the designated
location |
Contract 3 |
WM4¡VControl B |
Upstream of Ma Wat Channel |
833760 |
837395 |
Alternative location located at upstream 15m of the designated location |
Contract 3 |
The requirements of impact monitoring are stipulated in Sections 2.1.6, 3.1.5 and 4.1.6 of the approved EM&A Manual and presented as
follows.
Air Quality Monitoring
3.4.1
Frequency of impact air quality monitoring is
as follows:
1-hour TSP |
3 times every six
days during course of works |
24-hour TSP |
Once every 6 days during
course of works. |
Noise Monitoring
3.4.2
One set of Leq(30min)
as 6 consecutive Leq(5min)
between 0700-1900 hours on normal weekdays and once every week during course of
works. If construction work
necessary to carry out at other time periods, i.e. restricted time period
(19:00 to 07:00 the next morning and whole day on public holidays) (hereinafter
referred as ¡§the restricted hours¡¨), 3 consecutive Leq(5min)
measurement will depended CNP requirements to undertake. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for
reference.
Water Quality Monitoring
3.4.3
The water quality monitoring frequency shall
be 3 days per week during course of works.
The interval between two sets of monitoring shall not be less than 36
hours.
Air Quality Monitoring
3.5.1
The 24-hour and 1-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B. If the ET proposes to use a direct
reading dust meter to measure 1-hour TSP levels, it shall submit sufficient
information to the IEC to approve.
3.5.2
The filter paper of
24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.
3.5.3
All equipment to be used for air quality
monitoring is listed in Table 3-5.
Table 3-5 Air
Quality Monitoring Equipment
Equipment |
Model |
24-Hr TSP |
|
High
Volume Air Sampler |
TISCH High Volume
Air Sampler, HVS Model TE-5170 |
Calibration
Kit |
TISCH Model TE-5025A |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3B
Laser Dust monitor Particle Mass Profiler & Counter |
Wind Data Monitoring Equipment
3.5.4
According to the approved EM&A Manual,
wind data monitoring equipment shall also be provided and set up for logging
wind speed and wind direction near the dust monitoring locations. The equipment installation location
shall be proposed by the ET and agreed with the IEC. For installation and operation of wind
data monitoring equipment, the following points shall be observed:
1)
The wind sensors should be installed 10 m
above ground so that they are clear of obstructions or turbulence caused by
buildings.
2)
The wind data should be captured by a data
logger. The data shall be downloaded for analysis at least once a month.
3)
The wind data monitoring equipment should be
re-calibrated at least once every six months.
4)
Wind direction should be divided into 16
sectors of 22.5 degrees each.
3.5.5
ET has liaised with the landlords of the
successful granted HVS installation premises. However, the owners rejected to provide
premises for wind data monitoring equipment installation.
3.5.6
Under this situation, the ET proposed
alternative methods to obtain representative wind data. Meteorological information as extracted
from ¡§the Hong Kong Observatory Ta Kwu Ling Station¡¨
is alternative method to obtain representative wind data. For Ta Kwu
Ling Station, it is located nearby the Project site. Moreover, this station is located at 15m
above mean sea level while its anemometer is located at 13m above the existing
ground which in compliance with the general setting up requirement. Furthermore, this station also can be to
provide the humidity, rainfall, and air pressure and temperature etc.
meteorological information. In Hong
Kong of a lot development projects, weather information extracted from Hong
Kong Observatory is common alternative method if weather station installation
not allowed.
Noise Monitoring
3.5.7
Sound level meter in compliance with the
International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. The sound level meter shall be checked
using an acoustic calibrator. The
wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m s-1.
3.5.8
Noise monitoring equipment to be used for
monitoring is listed in Table 3-6.
Table 3-6 Construction
Noise Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
B&K Type 2238 or Rion
NL-14 or Rion NL-31 |
Calibrator |
B&K Type 4231 |
Portable Wind Speed Indicator |
Testo Anemometer |
3.5.9
Sound level meters listed above comply with
the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications, as recommended in TM issued
under the NCO. The acoustic
calibrator and sound level meter to be used in the impact monitoring will be
calibrated yearly.
Water Quality Monitoring
3.5.10
DO and water temperature should be measured
in-situ by a DO/temperature meter. The instrument should be portable and
weatherproof using a DC power source. It should have a membrane electrode with
automatic temperature compensation complete with a cable. The equipment should
be capable of measuring:
•
a DO level
in the range of 0-20 mg/l and 0-200% saturation; and
•
a
temperature of between 0 and 45 degree Celsius.
3.5.11
A portable pH meter capable of measuring a
range between 0.0 and 14.0 should be provided to measure pH under the specified
conditions accordingly to the APHA Standard Methods.
3.5.12
The instrument should be portable and
weatherproof using a DC power source. It should have a photoelectric sensor
capable of measuring turbidity between 0-1000 NTU.
3.5.13
A portable, battery-operated echo sounder or
tape measure will be used for the determination of water depth at each
designated monitoring station as appropriate.
3.5.14
A water sampler e.g. Kahlsico
Water Sampler, which is a transparent PVC cylinder with capacity not less than
2 litres, will be used for water sampling if water
depth over than 0.5m. For
sampling from very shallow water depths e.g. <0.5 m, water sample collection
will be directly from water surface below 100mm use sampling plastic bottle to
avoid inclusion of bottom sediment or humus. Moreover, Teflon/stainless steel bailer
or self-made sampling buckets maybe used for water sampling. The equipment used for sampling will be
depended the sampling location and depth situations.
3.5.15
Water samples for laboratory measurement of SS
will be collected in high density polythene bottles, packed in ice (cooled to 4
ºC without being frozen), and delivered to the laboratory in the same day as
the samples were collected.
3.5.16
Analysis of suspended solids should be
carried out in a HOKLAS or other accredited laboratory. Water samples of about
1L should be collected at the monitoring stations for carrying out the
laboratory suspended solids determination.
The SS determination work should start within 24 hours after collection
of the water samples. The SS analyses should follow the APHA Standard Methods 2540D with Limit of Reporting of 2 mg/L.
3.5.17
Water quality monitoring equipment used in
the impact monitoring is listed in Table 3-7. Suspended solids (SS)
analysis is carried out by a local HOKLAS-accredited laboratory, namely ALS Technichem
(HK) Pty Ltd.
Table 3-7 Water
Quality Monitoring Equipment
Equipment |
Model |
Water
Depth Detector |
Eagle
Sonar or tape measures |
Water Sampler |
A 2-litre transparent PVC cylinder with latex cups at
both ends or teflon/stainless steel bailer or
self-made sampling bucket |
Thermometer & DO meter |
YSI PRO20 Handheld Dissolved
Oxygen Instrument |
pH meter |
The EcoSense ® pH10A pen-style instrument |
Turbidimeter |
Hach 2100Q |
Sample Container |
High density polythene bottles (provided by laboratory) |
Storage
Container |
¡¥Willow¡¦
33-liter plastic cool box with Ice pad |
1-hour TSP
Monitoring
3.6.1
The 1-hour TSP monitor was a brand named ¡§Sibata LD-3B Laser Dust monitor Particle Mass Profiler
& Counter¡¨ which is a portable, battery-operated laser photometer. The 1-hour TSP meter provides a real
time 1-hour TSP measurement based on 90o light scattering. The 1-hour TSP monitor consists of the
following:
(a.)
A pump to draw sample aerosol through the
optic chamber where TSP is measured;
(b.)
A sheath air system to isolate the aerosol in
the chamber to keep the optics clean for maximum reliability; and
(c.)
A built-in data logger compatible with
Windows based program to facilitate data collection, analysis and reporting.
3.6.2
The 1-hour TSP meter is used within the valid
period as follow manufacturer¡¦s Operation and Service Manual.
3.6.3
The equipment used for 24-hour TSP
measurement is Thermo Andersen Model GS2310 TSP high volume air sampling
system, which complied with EPA Code of
Federal Regulation, Appendix B to Part 50. The High Volume Air Sampler
(HVS) consists of the following:
(a.)
An anodized aluminum shelter;
(b.)
A 8¡¨x10¡¨ stainless steel filter holder;
(c.)
A blower motor assembly;
(d.)
A continuous flow/pressure recorder;
(e.)
A motor speed-voltage control/elapsed time
indicator;
(f.)
A 7-day mechanical timer, and
(g.)
A power supply of 220v/50 Hz
3.6.4
The HVS is operated and calibrated on a
regular basis in accordance with the manufacturer¡¦s instruction using Tisch Calibration Kit Model TE-5025A. Calibration would carry out in two month
interval.
3.6.5
24-hour TSP is collected by the ET on filters
of HVS and quantified by a local HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd (ALS), upon receipt of the
samples. The ET keep all the
sampled 24-hour TSP filters in normal air conditioned room conditions, i.e. 70%
RH (Relative Humidity) and 25oC, for six months prior to disposal.
3.6.6
Noise measurements were taken in terms of the
A-weighted equivalent sound pressure level (Leq)
measured in decibels dB(A). Supplementary statistical
results (L10 and L90) were also obtained for reference.
3.6.7
During the monitoring, all noise measurements
would be performed with the meter set to FAST response and on the A-weighted
equivalent continuous sound pressure level (Leq). Leq(30min)
in six consecutive Leq(5min) measurements
will use as the monitoring parameter for the time period between 0700-1900
hours on weekdays; and also Leq(15min) in
three consecutive Leq(5min) measurements
would be used as monitoring parameter for other time periods (e.g. during
restricted hours), if necessary.
3.6.8
Prior of noise measurement, the accuracy of
the sound level meter is checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. The checking is performed before and
after the noise measurement.
Water
Quality
3.6.9
Water quality monitoring is conducted at the
designated locations. The sampling produce with the in-situ monitoring are
presented as below:
Sampling Procedure
3.6.10
A Digital Global
Positioning System (GPS) is used to identify the designated monitoring stations
prior to water sampling. A
portable, battery-operated echo sounder is used for the determination of water
depth at each station. At each
station, water sample would be collected from 0.1m below water surface or the
water surface to prevent the river bed sediment for stirring.
3.6.11
The sample container will be rinsed with a
portion of the water sample. The
water sample then will be transferred to the high-density polythene bottles as provided by the laboratory,
labeled with a unique sample number and sealed with a screw cap.
3.6.12
Before sampling, general information such as
the date and time of sampling, weather condition as well as the personnel
responsible for the monitoring would be recorded on the field data sheet.
3.6.13
A ¡¥Willow¡¦ 33-liter plastic cool box packed
with ice will be used to preserve the water samples prior to arrival at the
laboratory for chemical determination.
The water temperature of the cool box is maintained at a temperature as
close to 40C as possible without being frozen. Samples collected are delivered to the laboratory
upon collection.
In-situ Measurement
3.6.14
YSI PRO20 Handheld Dissolved Oxygen
Instrument is used for water in-situ
measures, which automates the measurements and data logging of
temperature, dissolved oxygen and dissolved oxygen saturation.
3.6.15
A portable EcoSense ®
pH10A pen-style instrument is used for in-situ pH measurement. The pH meter is capable of measuring pH
in the range of 0 ¡V 14 and readable to 0.1.
3.6.16
A portable Hach
2100Q Turbidimeter is used for in-situ turbidity
measurement. The turbidity meter is capable of measuring turbidity in the range
of 0 ¡V 1000 NTU.
3.6.17
All in-situ measurement equipment are calibrated by HOKLAS accredited laboratory of three
month interval.
Laboratory Analysis
3.6.18
All water samples analyzed Suspended Solids
(SS) will be carried out by a local HOKLAS-accredited testing laboratory (ALS Technichem (HK) Pty Ltd HOKLAS registration no. 66). SS determination using APHA
Standard Methods 2540D as specified in the EM&A Manual will start within
48 hours of water sample receipt.
3.7.1
Calibration of the HVS is performed upon
installation and thereafter at bimonthly intervals in accordance with the
manufacturer¡¦s instruction using the certified standard calibrator (TISCH Model
TE-5025A).
Moreover, the Calibration Kit would be calibrated annually. The calibration data are properly
documented and the records are maintained by ET for future reference.
3.7.2
The 1-hour TSP
meter was calibrated by the supplier prior to purchase. Zero response of the equipment would be
checked before and after each monitoring event. Annually calibration with the High
Volume Sampler (HVS) in same condition would be undertaken by the Laboratory.
3.7.3
The sound level
meter and calibrator are calibrated and certified by a laboratory accredited
under HOKLAS or any other international accreditation scheme at yearly basis.
3.7.4
All water quality monitoring equipment would
be calibrated by HOKLAS accredited laboratory of three month intervals.
3.7.5
The calibration
certificates of all monitoring equipment used for the impact monitoring program
in the Reporting Period and the HOKLAS accredited certificate of laboratory are attached in Appendix F.
3.8.1
The baseline results form the basis for
determining the environmental acceptance criteria for the impact
monitoring. According to the
approved Environmental Monitoring and Audit Manual, the air quality,
construction noise and water quality criteria were set up, namely Action and
Limit levels are listed in Tables 3-8, 3-9 and 3-10.
Table 3-8 Action and
Limit Levels for Air Quality Monitoring
Monitoring
Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
AM1a |
265 |
143 |
500 |
260 |
AM2 |
268 |
149 |
||
AM3 |
269 |
145 |
||
AM4a |
267 |
148 |
||
AM5 |
268 |
143 |
||
AM6 |
269 |
148 |
||
AM7b |
275 |
156 |
||
AM8 |
269 |
144 |
||
AM9b |
271 |
151 |
Table 3-9 Action
and Limit Levels for Construction Noise
Monitoring Location |
Action Level |
Limit Level in
dB(A) |
Time Period:
0700-1900 hours on normal weekdays |
||
NM1, NM2, NM3, NM4,
NM5, NM6, NM7, NM8, NM9, NM10 |
When one
or more documented complaints are received |
75 dB(A)Note 1
& Note 2 |
Note 1: Acceptable Noise Levels
for school should be reduced to 70 dB(A)
and65 dB(A) during examination period
Note 2: If works are to be
carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the NCA have to be followed.
Table 3-10 Action and
Limit Levels for Water Quality
Parameter |
Performance
criteria |
Monitoring
Location |
|||||
WM1 |
WM2A |
WM2B |
WM3 |
WM4 |
|||
DO (mg/L) |
Action Level |
(*)4.23 |
(**)4.00 |
(*)4.74 |
(**)4.00 |
(*)4.14 |
|
Limit Level |
(#)4.19 |
(**)4.00 |
(#)4.60 |
(**)4.00 |
(#)4.08 |
||
Turbidity (NTU) |
Action Level |
51.3 |
24.9 |
11.4 |
13.4 |
35.2 |
|
AND 120% of upstream control station of
the same day |
|||||||
Limit Level |
67.6 |
33.8 |
12.3 |
14.0 |
38.4 |
||
AND 130% of upstream control station of the same day |
|||||||
SS (mg/L) |
Action Level |
54.5 |
14.6 |
11.8 |
12.6 |
39.4 |
|
AND 120% of upstream control station of the
same day |
|||||||
Limit Level |
64.9 |
17.3 |
12.4 |
12.9 |
45.5 |
||
AND 130% of upstream control station of the same day |
|||||||
Remarks: (*) The
Proposed Action Level of Dissolved
Oxygen is adopted to be used 5%-ile of
baseline data (**) The
Proposed Action & Limit Level of Dissolved
Oxygen is used 4mg/L (#) The
Proposed Limit Level of Dissolved
Oxygen is adopted to be used 1%-ile of
baseline data |
|||||||
3.8.2
Should non-compliance of the environmental
quality criteria occurs, remedial actions will be triggered according to the
Event and Action Plan which presented in Appendix G.
3.9.1
All monitoring data will be handled by the ET¡¦s in-house data recording and management system. The monitoring data
recorded in the equipment will be downloaded directly from the equipment at the
end of each monitoring day. The
downloaded monitoring data will input into a computerized database maintained
by the ET. The laboratory results
will be input directly into the computerized database and checked by personnel
other than those who input the data.
3.9.2
For monitoring parameters that require
laboratory analysis, the local laboratory shall follow the QA/QC requirements
as set out under the HOKLAS scheme for the relevant laboratory tests.
4.1.1
In the Reporting Period, construction works under the
project have been commenced in Contracts 2,
3 and 5 and air quality monitoring was performed at 6 relevant designated
locations as below:
AM1a - Garden Farm, Tsung
Yuen Ha Village;
AM2 - Village House near Lin Ma Hang Road;
AM3 - Ta Kwu Ling
Fire Service Station of Ta Kwu Ling Village;
AM7b ¡V Loi Tung
Village;
AM8 - Po Kat Tsai Village;
AM9b - Nam Wa Po
Village House No. 80
4.1.2
The air quality monitoring schedule is presented
in Appendix H and the monitoring
results are summarized in the following sub-sections.
4.2.1
In the Reporting Period, a total of 90 events of 1-hour TSP and 29 events of 24-hours TSP
monitoring were carried out and the monitoring results are summarized in Tables
4-1 to 4-6. The detailed
24-hour TSP monitoring data are presented in Appendix I and the relevant graphical plots are shown in Appendix J.
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM1a
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
3-May-14 |
68
|
2-May-14 |
11:21 |
43 |
33 |
24 |
9-May-14 |
63
|
5-May-14 |
11:09 |
42 |
54 |
59 |
16-May-14# |
41
|
10-May-14 |
10:54 |
54 |
46 |
42 |
21-May-14 |
82
|
16-May-14 |
14:14 |
46 |
43 |
56 |
27-May-14 |
96
|
22-May-14 |
9:34 |
28 |
25 |
26 |
31-May-14 |
27
|
28-May-14 |
10:07 |
63 |
55 |
72 |
Average (Range) |
63 (27- 96) |
Average (Range) |
45 (24 ¡V 72) |
# Monitoring scheduled on 15 May 2014 was postponed to 16 May
2014 due to replacement of parts of HVS.
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM2
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
3-May-14 |
92
|
2-May-14 |
11:04 |
40 |
29 |
34 |
9-May-14 |
15
|
5-May-14 |
10:55 |
38 |
47 |
53 |
15-May-14 |
61
|
10-May-14 |
10:46 |
47 |
42 |
41 |
21-May-14 |
76
|
16-May-14 |
13:59 |
46 |
44 |
50 |
27-May-14 |
72
|
22-May-14 |
10:26 |
40 |
39 |
35 |
31-May-14 |
68
|
28-May-14 |
10:36 |
36 |
33 |
33 |
Average (Range) |
64 (15-92) |
Average (Range) |
40 (29 ¡V 53) |
Table 4-3 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM3
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
3-May-14 |
38
|
2-May-14 |
10:58 |
32 |
27 |
19 |
9-May-14 |
15
|
5-May-14 |
10:43 |
32 |
50 |
40 |
15-May-14 |
50
|
10-May-14 |
10:36 |
52 |
49 |
42 |
21-May-14 |
51
|
16-May-14 |
13:57 |
65 |
58 |
64 |
27-May-14 |
31
|
22-May-14 |
10:36 |
44 |
40 |
37 |
31-May-14 |
139
|
28-May-14 |
10:49 |
39 |
35 |
37 |
Average (Range) |
54 (15-139) |
Average (Range) |
42 (19 ¡V 65) |
Table 4-4 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM7b
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
26-May-14# |
82
|
20-May-14 |
13:21 |
30 |
25 |
20 |
31-May-14 |
48
|
26-May-14 |
10:42 |
53 |
37 |
28 |
|
31-May-14 |
11:41 |
27 |
27 |
32 |
|
Average (Range) |
46 (26 ¡V
69) |
Average (Range) |
31 (20 ¡V 53) |
# Power supply at new location AM7b was
connected on 26 May 2014.
Table 4-5 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM8
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
21-May-14 |
98
|
20-May-14 |
10:33 |
23 |
21 |
20 |
27-May-14 |
23
|
26-May-14 |
10:27 |
34 |
18 |
20 |
31-May-14 |
41 |
31-May-14 |
12:15 |
26 |
19 |
27 |
Average (Range) |
54 (23 ¡V 98) |
Average (Range) |
23 (18 ¡V 34) |
Table 4-6 Summary
of 24-hour and 1-hour TSP Monitoring Results ¡V AM9b
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st
reading |
2nd
reading |
3rd
reading |
||
3-May-14 |
36
|
2-May-14 |
10:10 |
32 |
24 |
21 |
9-May-14 |
19
|
8-May-14 |
11:38 |
68 |
65 |
58 |
15-May-14 |
54
|
14-May-14 |
10:29 |
45 |
41 |
35 |
21-May-14 |
38
|
20-May-14 |
10:07 |
20 |
18 |
16 |
27-May-14 |
61
|
26-May-14 |
14:03 |
22 |
23 |
27 |
31-May-14 |
25
|
31-May-14 |
10:07 |
32 |
17 |
14 |
Average (Range) |
39 (19-61) |
Average (Range) |
32 (14 ¡V 68) |
4.2.2
As shown in Tables 4-1 to 4-6,
the 24-hour and 1-hour TSP monitoring results were below the Action/ Limit
Level. No Notification of Exceedances (NOE) of air quality criteria or corrective
action was therefore required.
4.2.3
The meteorological data during the impact
monitoring days are summarized in Appendix
K.
5.1.1
In the Reporting Period, construction works under the
project have been commenced in Contracts 2,
3 and 5 and noise monitoring was performed at 8 relevant designated
locations as below:
NM1 - Tsung Yuen Ha
Village House No. 63;
NM2 - Village House near Lin Ma Hang Road;
NM5 - Village House, Loi
Tung
NM6 - Tai Tong Wu Village House 2
NM7 - Po Kat Tsai Village
NM8 - Village House, Tong Hang;
NM9 - Village House, Kiu
Tau Village; and
NM10 - Nam Wa Po
Village House No. 80
5.1.2
The noise monitoring schedule is presented in
Appendix H and the monitoring
results are summarized in the following sub-sections.
5.2.1
In the Reporting Period, a total of 39 event noise measurements were carried out at the designated
locations. The sound level meter
was set in 1m from the exterior of the building façade including noise
monitoring locations NM1, NM2, NM5, NM6, NM7, NM8 and NM9. Therefore, no façade correction (+3 dB(A)) is added according to acoustical principles and EPD
guidelines. However, free-field
status was performed at NM10. So,
façade correction (+3 dB(A)) has added according to
the requirement in this month. The
noise monitoring results at the designated locations are summarized in Table
5-1. The detailed noise
monitoring data are presented in Appendix
I and the relevant graphical plots are shown in Appendix J.
Table 5-1 Summary of Construction Noise Monitoring Results
Construction Noise Level (Leq30min), dB(A) |
|||||||||
Date |
NM1 |
NM2 |
Date |
NM5 |
NM6 |
NM7 |
NM8 |
NM9 |
(*)NM10 |
2-May-14 |
51
|
61
|
2-May-14 |
|
59
|
61
|
69
|
||
5-May-14 |
56
|
64
|
8-May-14 |
63
|
60
|
58
|
|||
10-May-14 |
51
|
56
|
14-May-14 |
61
|
56
|
63
|
|||
16-May-14 |
54
|
59
|
20-May-14 |
72
|
57
|
61
|
61
|
56
|
64
|
22-May-14 |
57
|
59
|
26-May-14 |
57
|
59
|
63
|
61
|
55
|
65
|
28-May-14 |
56
|
62
|
31-May-14 |
61
|
61
|
64
|
54
|
60
|
72
|
Limit Level |
75 dB(A) |
Remarks
(*) façade correction (+3 dB(A)
is added according to acoustical principles and EPD guidelines
5.2.2
As shown in Table
5-1, the noise level measured at the eight (8) designated monitoring
locations were below 75dB(A). Furthermore, there was no noise complaints (Action Level exceedance) received by the RE, Contractor or CEDD in the Reporting
Period. Therefore, no Action or
Limit Level exceedance was triggered and no
corrective action was required.
6.1.1
In the Reporting Period, construction works under the
project has been commenced in Contracts
3 and 5 and water quality monitoring was performed at 5 relevant designated
locations as below:
WM1 ¡V Contract 5 working site downstream at
Kong Yiu Channel;
WM1 ¡V Control ¡V Contract 5 working site
upstream at Kong Yiu Channel;
WM4 ¡V Contract 3 working site Downstream of
Ma Wat Channel
WM4 ¡V Control A - Contract 3 working site Kau Lung Hang Stream
WM4 ¡V Control B - Contract 3 working site
Upstream of Ma Wat Channel
6.1.2
The water quality monitoring schedule is
presented in Appendix H. The monitoring results are summarized in
the following sub-sections.
6.2.1
In the Reporting Period, a total of 13
sampling days were performed for water quality monitoring at Contracts 3 and 5. The key monitoring parameters including Dissolved Oxygen, Turbidity and Suspended
Solids are summarized in Tables 6-1 and 6-2. Breaches of water
quality monitoring criteria are shown in Table 6-3. Detailed
monitoring database including in-situ measurements and laboratory analysis data
are shown in Appendix I and the
relevant graphical plot are shown in Appendix
J.
Table 6-1 Summary
of Water Quality Monitoring Results for Contract 3
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
||||||
WM4 |
WM4-CA |
WM4-CB |
WM4 |
WM4-CA |
WM4-CB |
WM4 |
WM4-CA |
WM4-CB |
|
2-May-14 |
7.27 |
7.44 |
7.36 |
15.8 |
5.0 |
6.4 |
13.0 |
4.5 |
6.5 |
5-May-14 |
6.57 |
7.56 |
4.41 |
22.7 |
7.8 |
15.4 |
13.0 |
5.5 |
15.5 |
8-May-14 |
7.13 |
8.34 |
5.84 |
14.2 |
6.7 |
10.8 |
9.5 |
7.5 |
7.0 |
10-May-14 |
7.09 |
8.23 |
6.40 |
35.0 |
5.9 |
13.0 |
24.5 |
2.0 |
10.0 |
12-May-14 |
8.49 |
8.52 |
8.21 |
21.3 |
8.2 |
16.9 |
13.5 |
4.0 |
9.0 |
14-May-14 |
7.74 |
7.74 |
7.28 |
12.8 |
7.0 |
30.5 |
10.0 |
2.5 |
21.5 |
16-May-14 |
6.87 |
7.56 |
6.37 |
90.2 |
59.9 |
114.5 |
74.0 |
57.5 |
92.5 |
20-May-14 |
7.11 |
7.28 |
6.74 |
153.0 |
55.2 |
262.0 |
115.5 |
48.0 |
215.0 |
22-May-14 |
7.36 |
7.26 |
6.72 |
18.2 |
4.8 |
15.7 |
10.5 |
3.5 |
9.0 |
24-May-14 |
7.79 |
7.69 |
6.86 |
22.3 |
4.4 |
10.4 |
18.5 |
4.0 |
8.5 |
26-May-14 |
7.70 |
7.16 |
7.10 |
6.1 |
3.8 |
7.8 |
10.0 |
<2 |
5.0 |
28-May-14 |
7.86 |
6.74 |
5.47 |
8.3 |
3.8 |
6.7 |
7.0 |
2.5 |
5.0 |
31-May-14 |
7.99 |
6.92 |
5.60 |
9.9 |
5.1 |
12.1 |
9.0 |
2.5 |
14.0 |
Table 6-2 Summary
of Water Quality Monitoring Results for Contract 5
Date |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
|||
WM1 |
WM1- Control |
WM1 |
WM1- Control |
WM1 |
WM1- Control |
|
2-May-14 |
7.60 |
8.56 |
19.2 |
7.6 |
11.5 |
2.0 |
5-May-14 |
7.21 |
7.07 |
37.3 |
20.5 |
49.0 |
15.5 |
8-May-14 |
6.60 |
7.20 |
29.0 |
16.2 |
22.0 |
13.5 |
10-May-14 |
7.13 |
7.26 |
84.0 |
14.3 |
141.5 |
8.5 |
12-May-14 |
7.67 |
7.77 |
98.4 |
19.9 |
67.5 |
18.5 |
14-May-14 |
6.63 |
6.18 |
169.0 |
17.9 |
128.0 |
12.0 |
16-May-14 |
6.44 |
6.16 |
Over range |
Over range |
984.0 |
712.0 |
20-May-14 |
6.08 |
6.16 |
186.0 |
110.0 |
127.5 |
80.5 |
22-May-14 |
7.36 |
7.06 |
30.4 |
11.5 |
27.5 |
7.0 |
24-May-14 |
7.36 |
7.30 |
27.4 |
12.4 |
19.0 |
19.0 |
26-May-14 |
7.05 |
6.88 |
23.7 |
12.4 |
19.0 |
19.0 |
28-May-14 |
7.11 |
7.03 |
49.1 |
10.4 |
35.5 |
3.5 |
31-May-14 |
6.73 |
6.82 |
25.8 |
13.3 |
23.5 |
12.0 |
Remark: bold and underlined indicated Limit Level
exceedance.
Table 6-3 Breaches
of Water Quality Monitoring Criteria in Reporting Period
Location |
Dissolved Oxygen (mg/L) |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Total Exceedance |
||||
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
|
WM1 |
0 |
0 |
0 |
5 |
0 |
5 |
0 |
10 |
WM4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
No of Exceedance |
0 |
0 |
0 |
5 |
0 |
5 |
0 |
10 |
6.2.2
In view of the monitoring results of Dissolved Oxygen (DO) at W1 and W4, all the
measured results were higher than Action Level.
6.2.3
For
turbidity and SS, no exceedances were recorded at WM4
but a total of ten (10) Limit Level exceedances were
recorded at WM1. The Notification
on Exceedances (NOEs) were
issued to all relevant parties upon confirmation the results. The investigation for the cause of exceedance was completed and submitted to relevant parties. The investigation results are summarized
in below.
Investigation
for Exceedance at WM1 on 10, 12 and 14 2014
6.2.4
According to the site information provided by
SRJV, there was no construction activity carried out on 10, 12, 14 May 2014 due
to inclement weather. According to
records by the Hong Kong Observatory, there was continuous heavy rain recorded
from 8 to 14 May 2014, the Amber rainstorm warning was issued on 9 May 2014,
and the Amber and Red rainstorm warning were in force on 11 May 2014.
6.2.5
During the course of water sampling, muddy
water was observed throughout the channel.
Moreover, pollutant was found discharged from a pipe into the existing
stream by others near WM1-C. Due to
the continuous heavy rain, drain flood-water was occurred at Shenzhen River and
muddy backflow from was found accumulated near WM1. It is concluded that the exceedances were not due to the works under the project.
Investigation
for Exceedance at WM1 on 16 and 22 May 2014
6.2.6
According to the site information provided by
SRJV, there was no construction activity carried out on 16 and 20 May 2014 due
to inclement weather. According to records by the Hong Kong
Observatory, there was continuous heavy rain recorded from 16 to 20 May 2014
and the Amber Rainstorm Warning was issued on 20 May 2014.
6.2.7
Inspections carried out by the Contractor on
16 and 20 May 2014 observed flooding and muddy water at WM1, and the exceedances of turbidity and suspended solids were due to
the continuous heavy rain and backflow from Shenzhen River.
6.2.8
In view of the monitoring result at WM1-C, it
was noted that high turbidity and suspended solids results were obtained during
rainfall, which implies that the condition of the river is highly influenced by
the rainfall and backflow from Shenzhen River. Based on the above investigation, it is
considered that the exceedances were not related to
works under the Project.
7.1.1
Waste management was carried out by an
on-site Environmental Officer or an Environmental Supervisor from time to time.
7.2.1
All types of waste arising from the
construction work are classified into the following:
l Construction
& Demolition (C&D) Material;
l Chemical
Waste;
l General
Refuse; and
l Excavated
Soil.
7.2.2
The quantities of waste for disposal in this
Reporting Period are summarized in Tables 7-1 and 7-2 and the Monthly
Summary Waste Flow Table is shown in Appendix L. Whenever possible, materials were reused
on-site as far as practicable.
Table 7-1 Summary
of Quantities of Inert C&D Materials for the Project
Type of Waste |
Contract 2 |
Contract 3 |
Contract 5 |
Total Quantity |
|||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
Quantity |
Disposal Location |
||
C&D Materials (Inert) (in '000m3) |
0 |
-- |
2.740 |
- |
0 |
-- |
2.740 |
Reused in this Project (Inert) (in '000 m3) |
0.0643 |
- |
0.192 |
- |
0 |
-- |
0.192 |
Reused in other Projects (Inert) (in '000 m3) |
14.4032 |
C5 |
0 |
- |
0 |
-- |
0 |
Disposal as Public Fill (Inert) (in '000 m3) |
0.1094 |
Tuen Mun 38 |
2.548 |
Tuen Mun 38 |
0 |
-- |
2.548 |
Table 7-2 Summary
of Quantities of C&D Wastes for the Project
Type of Waste |
Contract 2 |
Contract 3 |
Contract 5 |
Total Quantity |
|||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
Quantity |
Disposal Location |
||
Recycled
Metal (in '000m3) |
0 |
- |
0 |
- |
- |
License collector |
0 |
Recycled
Paper / Cardboard Packing (in '000m3) |
0 |
- |
0 |
- |
0 |
-- |
0 |
Recycled Plastic (in '000m3) |
0 |
- |
0 |
- |
0 |
-- |
0 |
Chemical Wastes (in '000m3) |
0 |
- |
0.020 |
License collector |
0 |
-- |
0.020 |
General Refuses (in '000m3) |
0.0887 |
NENT |
0.195 |
NENT |
0.23 |
NENT |
|
8.1.1
According to the approved EM&A Manual, the
environmental site inspection shall be formulation by ET Leader. Weekly environmental site inspections should
carry out to confirm the environmental performance.
The Contract 2
8.2.1
In the Reporting Period, joint site
inspection for Contract 3 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 23 and 30 May 2014. No non-compliance was noted.
8.2.2
The findings / deficiencies of Contract
2 that observed during the weekly site inspection are listed in Table
8-1.
Table 8-1 Site
Observations for Contract 2
Date |
Findings / Deficiencies |
Follow-Up Status |
23 May 2014 |
Muddy surface runoff discharge from the
site during rain storm was observed at Mid Vent Portal, the Contractor was
reminded to pay attention to prevent discharge of any muddy water. |
No muddy water was accumulated in the site
area and no muddy surface runoff discharge from the site was observed during
site inspection on 30 May 2014. |
|
Free standing chemical containers without
drip trays were observed at North Portal. The Contractor was reminded to
provide drip trays to prevent leakage. |
Chemical containers were provided with drip
tray and covered with tarpaulin. |
|
Fencing for the tree protection zone was
observed to have not been installed properly at North Portal. The Contractor
was requested to provide proper maintenance for the tree protection zone. |
Proper fencing for the tree protection zone
was provided and maintained. |
30 May 2014 |
Chemical waste storage area at Mid Vent
Portal is only for the storage of chemical waste, and not for the storage of
used chemicals. |
Chemicals were stored in proper Chemical
Storage Area. |
|
Water spraying should be applied for
breaking activities to minimize dust generation at South Portal. |
Water spraying was applied to minimize dust
generation during breaking activities. |
|
The public road at South Portal leading to
the site should be kept clean, sand and mud was observed leading to the site.
|
No loose of sand and mud was observed on
public pathway and public road was kept in clean. |
|
Sand bag and earth bund should be provided
to direct the surface run-off to the sedimentation tank at South Portal. |
Sand bags have been provided to avoid any
muddy runoff into the U-channel. |
The Contract 3
8.2.3
In the Reporting Period, joint site
inspection for Contract 3 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 9, 14, 19 and 26 May 2014. No non-compliance was noted.
8.2.4
The findings / deficiencies of Contract
3 that observed during the weekly site inspection are listed in Table
8-2.
Table 8-2 Site
Observations for Contract 3
Date |
Findings / Deficiencies |
Follow-Up Status |
9 May 2014 |
The Contractor was reminded to treat the
stagnant water with sedimentation facilities prior to discharge from the
site. |
Housekeeping at the demolished vehicle
workshop has been improved. |
|
Housekeeping should be improved at the
demolished vehicle workshop. |
Stagnant water was removed after rainfall. |
14 May 2014 |
The Contractor was reminded to clean up the
stagnant water in all drip trays after rainy days to prevent mosquito
breeding. |
The reminder is noted. |
|
The Contractor was reminded to provide
wheel washing facilities at every construction entrance/exit. |
Wheel washing facilities have been provided
at all site entrance/exit. |
|
The Contractor was reminded to provide
washing facilities for workers¡¦ boots to prevent the spread of loose soil to
the public road. |
Washing facilities for workers have been
provided at site entrance/exit of SA3 |
19 May 2014 |
The Contractor was reminded to provide
valves to all drip trays in the construction site. |
Valve has been provided to drip tray. |
|
The Contractor was reminded to provide drip
tray for free-standing chemical to ensure no leakage of the chemical and to
clean the oil stain at bored pile A18. |
Drip tray was provided for free-standing
chemical and the oil stain was cleaned. |
26 May 2014 |
The Contractor should clean the
sedimentation tank at SA4 to prevent overflow and to ensure the suspended
solid level of the discharge complies with the discharge license. |
The sedimentation tank has been cleaned as
of site inspection on 3 June 2014. |
8.2.5
Moreover, the general housekeeping such as
tidiness of weekly and cleaniness of daily should be maintained in accordance
with the PS requirements.
The Contract 5
8.2.6
In the Reporting Period, joint site
inspection for Contract 5 to evaluate the site environmental performance has
been carried out by the RE, IEC, ET and the Contractor on 8, 15, 22 and 29 May 2014. No non-compliance was noted.
8.2.7
The findings / deficiencies of Contract
5 that observed during the weekly site inspection are listed in Table
8-3.
Table 8-3 Site
Observations for Contract 5
Date |
||
8 May 2014 |
The Contractor should clean up the vehicle washing bays
regularly to prevent muddy water in the bay and maintain effiency. |
The
water at vehicle washing bay was drained away and the sediment was removed to
improve the washing bay efficiency. |
|
Dusty trails at site exit in LMH was observed, the
Contractor was reminded to maintain mitigation measure to prevent loose dust
and surface runoff on public road. |
The
loose sand and dust at public road was cleaned up. |
|
Stagnant waster in drip tray was observed after the rain,
the Contractor was remidned to drain away any stagnant water to prevent
mosquitos breeding. |
Stagnant
water in trip tray was drained away to prevent mosquitoes breeding. |
15 May 2014 |
At the site exit at LMH, the road should be paved with concrete to reduce dust generation. |
The
exit/entrance road at LMH site office has been completely paved with concrete. |
|
Unplugged drip tray was observed on site, the Contractor
was reminded to re-plug the drip tray to prevent leakage. |
The
drip trays were re-plugged to prevent leakage. |
|
The Contractor was reminded to provide proper labels to air
compressor in pipe jacking area. |
The
Contractor provided clear and proper labels to the air compressor at the pipe
jacking area. |
22 May 2014 |
C&D waste was observed cumulated near the site exit of
temporary bridge area, the Contractor was reminded to clean and maintain a
clean and tidy site. |
Work
force was provided for site cleaning at the working area near the site exit
of temporary bridge area. |
29 May 2014 |
At the site exit of LMH site office, the Contractor was
reminded to tag the trees to indicate their condition. |
To
be followed. |
|
Contruction materials were found underneath the tree (to be
felled), the Contractor was reminded to remove or cover the stockpile. |
At
the exit in LMH site office, the stockpile was removed. |
|
Unplugged drip tray was observed, the Contractor was
reminded to re-plug the drip tray
to prevent leakage. |
The
drip tray was re-plugged to prevent leakage. |
8.2.8
Moreover, the general housekeeping such as
tidiness of weekly and cleaniness of daily should be maintained in accordance
with the PS requirements. Addition,
regular basis cleaning the wheel washing bay is
reminded. Furthermore, works at
Bridge J Area, tree protected fences should be provided to protect all retained
tree. Moreover, the Contractor was
reminded setting up storage area as for all chemical waste dispose on site.
Other Contracts
8.2.9
Since the construction works at the Contract
4 and Contract 6 have not yet been commenced, no site inspection is performed
for these Contracts.
Contract 2
9.1.1
In the Reporting Period, there were no summons and prosecution under
the EM&A Programme lodged for Contract 2.
However, one environmental complaint regarding muddy water discharge was
received for Contract 2 on 16 May 2014.
9.1.2
The EPD carried out a site inspection at the North Portal of Contract 2
on Sha Tau Kok on 16 May
2014 and observed muddy water being discharged into the surface drain between
the site office and Sha Tau Kok
Road. Although the surface drain was within site boundaries, there was no
demarcation of the works boundary, which might lead to public misunderstanding
of improper water discharge.
9.1.3
The Contractor
(DHK) figured out that the concerned surface drains are within the project
site, therefore no direct discharge of muddy water was made. Prompt remedial
actions were
taken by DHK to rectify the deficiencies and they are presented in follow:-
¡P
A catchpit has
been formed near the site entrance to collect water from surface drains. The
water collected is then pumped to the wastewater treatment facilities,
including AquaSed and sedimentation tank beneath for
treatment before discharge.
¡P
Sandbags have been placed along sections
of hoarding where seepage is likely to occur. The same arrangement is in place along
the section of surface channel near the junction of Sha
Tau Kok Road and Wo Keng Shan Road.
¡P
DHK has installed covers for the
drainage channel along the Sha Tau Kok road to minimise the
potential of muddy water complaints from the public.
¡P
A row of water barriers has been
provided to demarcate the site boundaries.
¡P
Water sampling has been carried out on
30 May 2014 as per Effluent Discharge License.
Contract 3 and 5
9.1.4
In
the Reporting Period, no environmental complaints, summons and prosecution
under the EM&A Programme was lodged for Contracts
3 and 5.
9.1.5
The
statistical summary table of environmental complaint is presented in Tables 9-1, 9-2 and 9-3.
Table 9-1 Statistical
Summary of Environmental Complaints
Reporting Period |
Contract No |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
06 Nov 2013 - 30 Apr 2014 |
Contract 3 |
0 |
1 |
(1) Construction Dust |
16 Aug 2013 - 30 Apr 2014 |
Contract 5 |
0 |
1 |
(1) Construction Dust |
1 ¡V 31 May 2014 |
Contract 2 |
1 |
1 |
(1)
Water Quality |
Contract 3 |
0 |
1 |
(1) Construction Dust |
|
Contract 5 |
0 |
1 |
(1) Construction Dust |
Table 9-2 Statistical
Summary of Environmental Summons
Reporting Period |
Contract No |
Environmental Summons Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
06 Nov 2013 - 30 Apr 2014 |
Contract 3 |
0 |
0 |
NA |
16 Aug 2013 - 30 Apr 2014 |
Contract 5 |
0 |
0 |
NA |
1 ¡V 31 May 2014 |
Contract 2 |
0 |
0 |
NA |
Contract 3 |
0 |
0 |
NA |
|
Contract 5 |
0 |
0 |
NA |
Table 9-3 Statistical
Summary of Environmental Prosecution
Reporting Period |
Contract No |
Environmental
Prosecution Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
||
06 Nov 2013 - 30 Apr 2014 |
Contract 3 |
0 |
0 |
NA |
16 Aug 2013 - 30 Apr 2014 |
Contract 5 |
0 |
0 |
NA |
1 ¡V 31 May 2014 |
Contract 2 |
0 |
0 |
NA |
Contract 3 |
0 |
0 |
NA |
|
Contract 5 |
0 |
0 |
NA |
The Other Contracts
9.1.6
Since the construction works at the Contract
4 and Contract 6 have not yet been commenced, no environmental complaint,
summons and prosecution under the EM&A Programme are
registered in the Reporting Period.
10.1.1
The environmental mitigation measures that
recommended in the Implementation Schedule for Environmental Mitigation
Measures (ISEMM) in the approved EM&A Manual covered the issues of dust,
noise, water and waste and they are summarized presented in Appendix
M.
10.1.2
All contracts under the Project shall be
implementing the required environmental mitigation measures according to the approved
EM&A Manual as subject to the site condition. Environmental mitigation measures
generally implemented by Contracts 3 and 5 in this Reporting Period are
summarized in Table 10-1.
Table 10-1 Environmental
Mitigation Measures
Issues |
Environmental
Mitigation Measures |
Water Quality |
¡P Wastewater to be treated by the
filtration systems i.e. sedimentation tank or AquaSed before to discharge. |
Air Quality |
¡P Maintain damp / wet surface
on access road ¡P Keep slow speed in the sites ¡P All vehicles must use wheel
washing facility before off site ¡P Sprayed water during
breaking works ¡P A cleaning truck was
regularly performed on the public road to prevent fugitive dust emission |
Noise |
¡P Restrain operation time of
plants from 07:00 to 19:00 on any working day except for Public Holiday and Sunday. ¡P Keep good maintenance of
plants ¡P Place noisy plants away from
residence or school ¡P Provide noise barriers or
hoarding to enclose the noisy plants or works ¡P Shut down the plants when
not in used. |
Waste and Chemical Management |
¡P On-site sorting prior to disposal ¡P Follow requirements and
procedures of the ¡§Trip-ticket System¡¨ ¡P Predict required quantity of
concrete accurately ¡P Collect
the unused fresh concrete at designated locations in the sites for subsequent
disposal |
General |
¡P The site was generally kept tidy
and clean. |
10.2.1
Construction activities as undertaken in the
coming month for the Project lists below:
Contract 2
Project wide ¡V Minor Structures Demolition
Project wide ¡V Watermains
Connection
Hoarding and Fencing
Removal of Boulders
SA01 ¡V Erection of Project Office
Mid Vent Portal ¡V Soil Nails Works
Mid Vent Portal ¡V Workshop Erection
Mid Vent Portal ¡V Wetsep
Erection
Mid Vent Portal ¡V Shotcrete
Trial
Mid Vent Portal ¡V Excavation Works
North Portal ¡V Excavation Works
North Portal ¡V Haul Road
South Portal ¡V Geotechnical Instrumentation
Works
South Portal ¡V Bridge Construction
South Portal ¡V Mini Piling Works
South Portal ¡V Instrumentation and Monitoring
Works for Temporary Steel Bridge Construction
Temporary Bridge - Trial Pit for Water Mains
Inspection
Site Office and Workshop Containers
Installation at CR6A
Contract 3
Cable detection and trial trenches
Pre-drilling works and piling works
Tree felling and transplanting works
Pile cap works
Waterworks
Slope upgrading works
Noise barrier footing
Laying of concrete pipe works
Bored pile wall construction
Pier Construction
Site formation
Demolition
Mini pile construction
Contract 5
Construction of retaining wall No.1
Construction of Village House at RS4
Piling works at footbridge
Construction of Western pedestrian subway at
LMH
Pipe jacking across Kong Yuen River
Transplantation, Pruning/felling of existing
tree
Drainage works at proposed and existing LMH
Road
Formation Works at BCP Area
Construction of Depressed Road at BCP3
Filing Works for ArcHD
permanent office
Construction of substructure and superstructe of Bridge J
Water works at proposed and existing LMH Road
Water works at proposed and existing LMH Road
Construction of footbridge and staircase at
RS4
Construction of Eastern pedestrian subway and
pump room at LMH.
10.3.1
Key issues to be considered in the coming
month for Contracts 2, 3 and 5 include:
Implementation of
control measures for rainstorm;
Regular clearance of
stagnant water during wet season;
Implementation of dust
suppression measures at all times;
Potential wastewater
quality impact due to surface runoff;
Potential fugitive
dust quality impact due from the dry/loose/exposure soil surface/dusty material;
Disposal of empty
engine oil containers within site area;
Ensure dust suppression measures are
implemented properly;
Sediment catch-pits and silt removal
facilities should be regularly maintained;
Management of chemical wastes;
Discharge of site effluent to the nearby
wetland, stockpiling or disposal of materials, and any dredging or construction
area at this area are prohibited;
Follow-up of improvement on general waste
management issues; and
Implementation of construction noise
preventative control measures
10.3.2
For other Contracts, no environmental issue
is considered due to these contracts still yet to commence.
11.1.1
This is 10th
monthly EM&A report presenting the monitoring results and inspection
findings for the Reporting Period from 1 to 31 May 2014.
11.1.2
No 24-hour or 1-hour TSP monitoring results
that triggered the Action or Limit Levels were recorded. No NOEs or the
associated corrective actions were therefore issued.
11.1.3
No noise complaint (which is an Action Level exceedance) was received and no construction noise
measurement results that exceeded the Limit Level were recorded in the
Reporting Period. No NOEs or the associated corrective
actions were therefore issued.
11.1.4
For water quality monitoring, ten (10) Limit
Level exceedances in parameters of turbidity and SS were
recorded at WM1. The Notification
on Exceedances (NOEs) was issued to all relevant
parties. Investigation findings concluded
that that all the exceedances were not due to the
Project works.
11.1.5
In the Reporting Period, one environmental
complaint was received for Contract 2 on 16 May 2014 regarding direct discharge
of muddy water. Investigation report for the complaint has completed and it
reveals that no direct discharge of muddy water from Contract 2 was found.
11.1.6
No environmental complaint, notification of
summons or successful prosecution under the EM&A Programme
of the Liantang/Heung
Yuen Wai Boundary Control Point and Associated Works was received in the reporting period for
Contract 3 and 5.
11.1.7
During the Reporting Period, two (2), five (5)
and five (5) events of joint site inspection by the RE, IEC, ET and
Main-contractor were carried out for Contracts 2, 3 and 5 respectively in
accordance with the EM&A Manual stipulation. No non-compliance observed during the
site inspection. The environmental
performance of the Project of Contracts 3 and 5 was therefore considered as
satisfactory.
11.2.1
During wet season, muddy water or other water
pollutants from site surface runoff into Kong Yiu
Channel and Ma Wat
Channel will be key environment issue. Water quality mitigation measures to
prevent surface runoff into nearby water bodies should be fully implemented.
11.2.2
Special attention should
also be paid on the potential construction dust impact since most of the
construction sites are adjacent to villages. The Contractor should fully implement
the construction dust mitigation measures properly.
11.2.3
Construction noise
should be a key environmental impact during the works. The noise mitigation measures such as
use of quiet plants or temporary noise barrier installation at the construction
noise predominate area should be implemented as accordance with the EM&A
requirement.